State of Illinois
90th General Assembly
Legislation

   [ Search ]   [ Legislation ]   [ Bill Summary ]
[ Home ]   [ Back ]   [ Bottom ]



90_SB1770

          Makes appropriations and reappropriations to the  Capital
      Development  Board  for permanent improvements, minor capital
      improvements, repair and maintenance,  and  related  purposes
      for   the   fiscal   year  beginning  July  1,  1998.   Makes
      reappropriations to various  state  agencies  for  continuing
      Build Illinois projects for the fiscal year beginning July 1,
      1998.
                        CAPITAL PROJECTS - TO CDB
      FUND              NEW APPROPS.    REAPPROPS.           TOTAL
      General Revenue      $20,000.0     $41,524.6       $61,524.6
      School
        Construction       200,000.0            .0       200,000.0
      School
        Infrastructure      38,000.0      30,000.0        68,000.0
      Capital
        Development        370,508.9     938,144.7     1,308,757.4
      Asbestos
        Abatement                  0         272.2           272.2
      TOTAL                628,508.9   1,009,941.5     1,638,554.2
                     CAPITAL PROJECTS - TO AGENCIES
      CAPITAL DEVELOPMENT FUND
      Sec. of St.                 $0          $4.6            $4.6
      Space Needs
        Comm.                      0           4.8             4.8
      EIU                          0          37.9            37.9
      ISU                          0       1,534.7         1,534.7
      NEIU                         0       4,000.0         4,000.0
      NIU                          0          65.5            65.5
      SIU-Carbondale               0          38.8            38.8
      UofI-Urbana-Cham.            0         154.4           154.4
      TOTAL                        0       5,840.7         5,840.7
      GENERAL REVENUE FUND
      Historic Preservation        0         400.0           400.0
      TOTAL GRF             20,000.0      41,924.6        61,924.6
      TOTAL CDF            370,508.9     943,985.5     1,314,598.1
                         BUILD ILLINOIS PROJECTS
      FUND                                          REAPPROPRIATIONS
      Build Illinois Purposes                            $5,306.8
      Build Illinois Bond                               144,072.8
      TOTAL                                            $149,379.6
                                                      BOB-CAPITAL99
                                                BOB-CAPITAL99
 1        AN ACT making appropriations and reappropriations.
 2        Be  it  enacted  by  the People of the State of Illinois,
 3    represented in the General Assembly:
 4                              ARTICLE 1
 5        Section 1.  The  following  named  amounts,  or  so  much
 6    thereof  as  may  be  necessary,  are  appropriated  from the
 7    Capital Development Fund to the Capital Development Board for
 8    the Department of Agriculture for  the  projects  hereinafter
 9    enumerated:
10                               DUQUOIN
11    For constructing four livestock barns
12      (Phase II) ................................... $    688,000
13                             SPRINGFIELD
14    For replacing and renovating
15      racehorse barns (Phase II) ...................    1,000,000
16    For rehabilitating sidewalks, curbs,
17      streets, and gutters, in addition to funds
18      previously appropriated ......................    1,421,000
19    For replacing and rehabilitating roofs .........    1,279,000
20    For renovating #26 Barn ........................      736,000
21        Total, Section 1                               $5,124,000
22        Section  1a.  The  following  named  amount,  or  so much
23    thereof as may be necessary, is appropriated from the General
24    Revenue  Fund  to  the  Capital  Development  Board  for  the
25    Department  of  Agriculture  for  the   project   hereinafter
26    enumerated:
27                             SPRINGFIELD
28    For surveying the electrical system ............ $    195,000
29        Total, Section 1a                                $195,000
                            -2-                 BOB-CAPITAL99
 1        Section  2.  The  following  named  amounts,  or  so much
 2    thereof as  may  be  necessary,  are  appropriated  from  the
 3    Capital Development Fund to the Capital Development Board for
 4    the   Department  of  Central  Management  Services  for  the
 5    projects hereinafter enumerated:
 6                 ILLINOIS CENTER FOR REHABILITATION
 7                 AND EDUCATION (ROOSEVELT) - CHICAGO
 8    For converting and renovating tub rooms ........ $    425,000
 9                 JAMES R. THOMPSON CENTER - CHICAGO
10    For replacing roofing system and
11      insulation, in addition to funds
12      previously appropriated ......................      950,000
13                   MARION REGIONAL OFFICE BUILDING
14    For replacing HVAC system and interior
15      lighting .....................................    1,600,000
16                         OTTAWA STATE GARAGE
17    For replacing state garage .....................    1,400,000
18                   SUBURBAN NORTH REGIONAL OFFICE
19                       BUILDING - DES PLAINES
20    For renovating offices for Environmental
21      Protection Agency, in addition to funds
22      previously appropriated ......................    1,635,000
23        Total, Section 2                               $6,010,000
24        Section 2a.  The  following  named  amount,  or  so  much
25    thereof as may be necessary, is appropriated from the General
26    Revenue  Fund  to  the  Capital  Development  Board  for  the
27    Department  of  Central  Management  Services for the project
28    hereinafter enumerated:
29           CHICAGO MEDICAL CENTER - OFFICE AND LABORATORY
30    For rehabilitating exterior .................... $    390,000
31        Total, Section 2a                                $390,000
32        Section 3.  The  following  named  amounts,  or  so  much
                            -3-                 BOB-CAPITAL99
 1    thereof  as  may  be  necessary,  are  appropriated  from the
 2    Capital Development Fund to the Capital Development Board for
 3    the Department of Corrections for  the  projects  hereinafter
 4    enumerated:
 5                        HANNA CITY WORK CAMP
 6    For upgrading electrical system ................ $    600,000
 7                HILL CORRECTIONAL CENTER - GALESBURG
 8    For upgrading and expanding freezer
 9      capacity, in addition to funds
10      previously appropriated ......................      950,000
11    For replacing domestic water lines .............      410,000
12                          IYC - ST. CHARLES
13    For planning upgrade of existing
14      facility .....................................      600,000
15                   IYC - VALLEY VIEW - ST. CHARLES
16    For completing upgrade of restrooms, in
17      addition to funds previously appropriated ....      300,000
18                 LOGAN CORRECTIONAL CENTER - LINCOLN
19    For planning replacement of the Dietary
20      and Medical Buildings ........................      400,000
21                MENARD CORRECTIONAL CENTER - CHESTER
22    For completing upgrade of North Cellhouse
23      plumbing system, in addition to funds
24      previously appropriated ......................      400,000
25    For planning upgrade of the storm tunnel .......      100,000
26    For replacing toilets and waste lines
27      at E/W Cellhouse .............................    2,600,000
28                     PONTIAC CORRECTIONAL CENTER
29    For completing replacement of hot water
30      lines, in addition to funds previously
31      appropriated .................................    1,100,000
32               STATEVILLE CORRECTIONAL CENTER - JOLIET
33    For replacing power plant ......................   10,000,000
34    For planning, design, construction,
                            -4-                 BOB-CAPITAL99
 1      equipment and all other necessary costs
 2      for an Adult Reception and Classification
 3      Center .......................................   44,000,000
 4    For upgrading storm drainage and
 5      wastewater systems ...........................    1,200,000
 6    For upgrading electrical system and elevator
 7      and installing HVAC system ...................    1,200,000
 8                     VIENNA CORRECTIONAL CENTER
 9    For completing upgrade of the steam
10      distribution system, in addition to
11      funds previously appropriated ................      940,000
12    For upgrading electrical system and
13      installing emergency generator ...............    1,200,000
14                              STATEWIDE
15    For planning, design, construction,
16      equipment and all other necessary costs
17      for a juvenile facility ......................   20,000,000
18    For replacing locks and doors at the
19      following locations at the approximate
20      cost set forth below .........................    1,090,000
21        Dwight Correctional Center ......... 275,000
22        Illinois River Correctional
23         Center - Canton ................... 150,000
24        IYC - Joliet ....................... 500,000
25        IYC - Pere Marquette - Grafton ..... 165,000
26    For replacing roofing systems at the following
27      locations at the approximate cost set forth
28      below ........................................    2,875,000
29        Dixon Correctional Center,
30         four buildings .................... 900,000
31        IYC - St. Charles, two buildings ... 455,000
32        Joliet Correctional Center,
33         six buildings ..................... 875,000
34        Logan Correctional Center - Lincoln
                            -5-                 BOB-CAPITAL99
 1         three buildings ................... 115,000
 2        Menard Correctional Center - Chester
 3         six buildings ..................... 275,000
 4        Pontiac Correctional Center,
 5         one building ...................... 255,000
 6    For inspecting and upgrading water towers
 7      at the following locations at the approximate
 8      costs set forth below ........................    3,590,000
 9        Dixon Correctional Center,
10         Upgrade Water Tower ............. 1,000,000
11        Graham Correctional Center - Hillsboro
12         Upgrade Water Tower  .............. 215,000
13        Joliet Correctional Center,
14         Upgrade Water Tower ............... 150,000
15        Logan Correctional Center - Lincoln
16         Complete Water Tower Upgrade  ..... 600,000
17        Menard Correctional Center - Chester
18         Upgrade Water Tower  .............. 325,000
19        Stateville Correctional Center - Joliet
20         Upgrade Water Tower  ............ 1,000,000
21        Statewide, Inspect and Upgrade
22         Water Towers ...................... 300,000
23    For upgrading fire and safety systems at
24      the following locations at the approximate
25      costs set forth below, in addition to
26      funds previously appropriated ................    3,370,000
27        Menard Correctional Center -
28         Chester ......................... 2,200,000
29        Sheridan Correctional Center ....... 320,000
30        Vienna Correctional Center ......... 850,000 ____________
31        Total, Section 3                              $96,925,000
32        Section  4.  The  following  named  amounts,  or  so much
33    thereof as  may  be  necessary,  are  appropriated  from  the
                            -6-                 BOB-CAPITAL99
 1    Capital Development Fund to the Capital Development Board for
 2    the Historic Preservation Agency for the projects hereinafter
 3    enumerated:
 4                BEISMAN HOUSE - GALENA HISTORIC SITE
 5    For rehabilitating Beisman House ............... $    427,000
 6                     BISHOP HILL HISTORIC SITE -
 7                            HENRY COUNTY
 8    For rehabilitating Bjorkland Hotel .............    1,010,000
 9                  LEWIS AND CLARK STATE MEMORIAL -
10                           MADISON COUNTY
11    For constructing interpretive center,
12      in addition to funds previously
13      appropriated .................................    1,700,000
14                  LINCOLN LOG CABIN HISTORIC SITE -
15                            COLES COUNTY
16    For constructing visitors center, Phase II,
17      and developing day use area ..................    1,669,000
18           LINCOLN'S NEW SALEM HISTORIC SITE - PETERSBURG
19    For renovating village entrance and
20      completing visitors center ...................      735,000
21                    LINCOLN PRESIDENTIAL CENTER -
22                             SPRINGFIELD
23    For planning Lincoln Presidential Center,
24      in addition to funds previously
25      appropriated .................................    2,200,000
26                   OLD STATE CAPITOL - SPRINGFIELD
27    For rehabilitating Old State Capitol ...........    1,159,000
28                POSTVILLE COURTHOUSE HISTORIC SITE -
29                               LINCOLN
30    For rehabilitating Courthouse and site .........      368,000
31                  VACHEL LINDSAY HOME - SPRINGFIELD
32    For rehabilitating home ........................      762,000
33                 VANDALIA STATE HOUSE HISTORIC SITE
34    For replacing roof and rehabilitating
                            -7-                 BOB-CAPITAL99
 1      exterior .....................................      508,000
 2        Total, Section 4                              $10,538,000
 3        Section  4a.  The  following  named  amounts,  or so much
 4    thereof as  may  be  necessary,  are  appropriated  from  the
 5    General Revenue Fund to the Capital Development Board for the
 6    Historic  Preservation  Agency  for  the projects hereinafter
 7    enumerated:
 8                  FORT DE CHARTRES HISTORIC SITE -
 9                           RANDOLPH COUNTY
10    For planning restoration of powder magazine .... $    100,000
11                 LINCOLN'S NEW SALEM HISTORIC SITE -
12                             PETERSBURG
13    For removing sewage lagoon and treatment
14      plant ........................................      407,000
15    For rehabilitating saw mill and grist
16      mill .........................................      219,000
17                  METAMORA COURTHOUSE HISTORIC SITE
18    For rehabilitating courthouse ..................      474,000
19        Total, Section 4a                              $1,200,000
20        Section 5.  The  following  named  amounts,  or  so  much
21    thereof  as  may  be  necessary,  are  appropriated  from the
22    Capital Development Fund to the Capital Development Board for
23    the Department of  Human  Services  (formerly  Department  of
24    Mental   Health   and  Developmental  Disabilities)  for  the
25    projects hereinafter enumerated:
26                    CHESTER MENTAL HEALTH CENTER
27    For renovating kitchen area .................... $    967,000
28                  CHICAGO-READ MENTAL HEALTH CENTER
29    For upgrading fire/life safety systems,
30      in addition to funds previously appropriated .      235,000
31                 CHOATE MENTAL HEALTH CENTER - ANNA
32    For rehabilitating Cypress Building ............    1,546,000
                            -8-                 BOB-CAPITAL99
 1                     ELGIN MENTAL HEALTH CENTER
 2    For replacing power plant and engineering
 3      building .....................................    8,029,000
 4                  FOX DEVELOPMENTAL CENTER - DWIGHT
 5    For renovating dietary, in addition to funds
 6      previously appropriated ......................      857,000
 7                     HOWE DEVELOPMENTAL CENTER -
 8                             TINLEY PARK
 9    For replacing roofs ............................       81,000
10    For planning access to water supply from
11      village ......................................       78,000
12    For planning and rehabilitation of
13      utility tunnels ..............................      250,000
14                    LINCOLN DEVELOPMENTAL CENTER
15    For upgrading power plant and installing
16      EMS, in addition to funds previously
17      appropriated .................................    1,795,000
18    For renovating Elmhurst Cottage ................    1,905,000
19                   LUDEMAN DEVELOPMENTAL CENTER -
20                             PARK FOREST
21    For replacing plumbing, HVAC and boiler
22      systems ......................................      796,000
23                  MCFARLAND MENTAL HEALTH CENTER -
24                             SPRINGFIELD
25    For renovating Stevenson Hall ..................      984,000
26                   SHAPIRO DEVELOPMENTAL CENTER -
27                              KANKAKEE
28    For planning upgrade of steam and
29      condensate lines .............................      320,000
30    For rehabilitating HVAC systems ................    1,166,000
31               SINGER MENTAL HEALTH CENTER - ROCKFORD
32    For replacing roofs ............................      248,000
33                  TINLEY PARK MENTAL HEALTH CENTER
34    For upgrading fire/life safety systems
                            -9-                 BOB-CAPITAL99
 1      and bedroom lighting, in addition to
 2      funds previously appropriated ................      236,000
 3        Total, Section 5                              $19,493,000
 4        Section 5a.  The following  named  amounts,  or  so  much
 5    thereof  as  may  be  necessary,  are  appropriated  from the
 6    General Revenue Fund to the Capital Development Board for the
 7    Department of Human Services (formerly Department  of  Mental
 8    Health  and  Developmental  Disabilities)  for  the  projects
 9    hereinafter enumerated:
10                  FOX DEVELOPMENTAL CENTER - DWIGHT
11    For replacing windows .......................... $    578,000
12                  JACKSONVILLE DEVELOPMENTAL CENTER
13    For replacing stoker and controls ..............      206,000
14    For planning the rehabilitation of
15      smokestack ...................................       80,000
16                              STATEWIDE
17    For resurfacing roads at Chicago-Read,
18      Tinley Park and Murray .......................    2,000,000
19        Total, Section 5a                              $2,864,000
20        Section  5.1.  The  following  named  amounts, or so much
21    thereof as  may  be  necessary,  are  appropriated  from  the
22    Capital Development Fund to the Capital Development Board for
23    the  Department  of  Human  Services  (formerly Department of
24    Rehabilitation  Services)  for   the   projects   hereinafter
25    enumerated:
26                   ILLINOIS SCHOOL FOR THE DEAF -
27                            JACKSONVILLE
28    For installing HVAC and upgrading electrical
29      and replacing doors .......................... $  1,400,000
30                  ILLINOIS SCHOOL FOR THE VISUALLY
31                       IMPAIRED - JACKSONVILLE
32    For installing sewers ..........................    1,200,000
                            -10-                BOB-CAPITAL99
 1    For constructing a new building to
 2      replace buildings 2, 3 and 4,
 3      in addition to funds previously
 4      appropriated .................................    3,300,000
 5        Total, Section 5.1                             $5,900,000
 6        Section  5a.1.  The  following  named amounts, or so much
 7    thereof as  may  be  necessary,  are  appropriated  from  the
 8    General Revenue Fund to the Capital Development Board for the
 9    Department   of   Human   Services  (formerly  Department  of
10    Rehabilitation  Services)  for   the   projects   hereinafter
11    enumerated:
12                   ILLINOIS SCHOOL FOR THE DEAF -
13                            JACKSONVILLE
14    For installing humidity controls ............... $    155,000
15    For installing an all-weather
16      running track ................................      190,000
17        Total, Section 5a.1                              $345,000
18        Section  6.  The  following  named  amounts,  or  so much
19    thereof as  may  be  necessary,  are  appropriated  from  the
20    Capital Development Fund to the Capital Development Board for
21    the   Department   of   Military  Affairs  for  the  projects
22    hereinafter enumerated:
23                          CRESTWOOD ARMORY
24    For replacing roofing system and
25      rehabilitating exterior ...................... $  1,228,000
26                      SPRINGFIELD CAMP LINCOLN
27    For renovating heating system and
28      replacing windows ............................      908,000
29                            DIXON ARMORY
30    For upgrading mechanical and electrical
31      systems ......................................    1,866,000
32                        WEST FRANKFORT ARMORY
                            -11-                BOB-CAPITAL99
 1    For replacing roofs and rehabilitating
 2      exterior .....................................    1,197,000
 3                           WAUKEGAN ARMORY
 4    For replacing roofing system ...................      415,000
 5        Total, Section 6                               $5,614,000
 6        Section 7.  The  following  named  amounts,  or  so  much
 7    thereof  as  may  be  necessary,  are  appropriated  from the
 8    Capital Development Fund to the Capital Development Board for
 9    the  Department  of  Natural  Resources  for   the   projects
10    hereinafter enumerated:
11                 BABE WOODYARD STATE NATURAL AREA -
12                          VERMILION COUNTY
13    For developing the site and associated
14      land acquisition ............................. $  3,300,000
15                BEALL WOODS STATE CONSERVATION AREA -
16                            WABASH COUNTY
17    For replacing a visitors center ................      488,000
18                      CAVE-IN-ROCK STATE PARK -
19                            HARDIN COUNTY
20    For constructing a shower building
21      and upgrading the campground .................      650,000
22                      FERNE CLYFFE STATE PARK -
23                           JOHNSON COUNTY
24    For rehabilitating shower building .............      215,000
25                 FOX RIDGE STATE PARK - COLES COUNTY
26    For upgrading campground .......................      340,000
27                 HORSESHOE LAKE CONSERVATION AREA -
28                          ALEXANDER COUNTY
29    For replacing the hunter check station .........      150,000
30                     ILLINOIS BEACH STATE PARK -
31                             LAKE COUNTY
32    For constructing an office building ............      650,000
33    For replacing sanitary sewer lines .............      505,000
                            -12-                BOB-CAPITAL99
 1                LINCOLN TRAIL STATE RECREATION AREA -
 2                            CLARK COUNTY
 3    For rehabilitating the day use area
 4      and site .....................................    1,281,000
 5                 NAUVOO STATE PARK - HANCOCK COUNTY
 6    For replacing water distribution
 7      system .......................................      241,000
 8                     PERE MARQUETTE STATE PARK -
 9                            JERSEY COUNTY
10    For replacing the lodge HVAC condensing unit, in
11      addition to funds previously appropriated ....      334,000
12                      RAMSEY LAKE STATE PARK -
13                           FAYETTE COUNTY
14    For rehabilitating shower building .............      188,000
15                             SPRINGFIELD
16    For constructing an office building and
17      interpretive center ..........................   30,000,000
18                     STATE MUSEUM - SPRINGFIELD
19    For renovating or replacing exhibits in,
20      addition to funds previously appropriated ....    5,500,000
21    For planning replacement of the state
22      museum .......................................      800,000
23              STARVED ROCK STATE PARK - LASALLE COUNTY
24    For rehabilitating the sewer system ............    1,055,000
25    For rehabilitating trails, in addition
26      to funds previously appropriated .............      500,000
27    For upgrading the HVAC system ..................      445,000
28             TUNNEL HILL-CACHE RIVER STATE NATURAL AREA
29    For constructing a visitor center and
30      purchasing land ..............................    4,000,000
31                      WATER SURVEY - CHAMPAIGN
32    For upgrading and replacing the mechanical
33      system, in addition to funds
34      previously appropriated ......................    2,200,000
                            -13-                BOB-CAPITAL99
 1                              STATEWIDE
 2    For replacing roofing systems at the
 3      following locations at the approximate
 4      costs set forth below ........................      370,000
 5        Lincoln Trail Homestead State
 6         Park, Four buildings ............... 38,000
 7        Silver Springs State Park, Three
 8         Buildings ......................... 278,000
 9        Weldon Springs State Park, Nine
10         Buildings .......................... 54,000
11    For constructing vault toilets at the following
12      locations at the approximate costs set forth
13      below ........................................      852,000
14        Cave-In-Rock State Park ............ 192,000
15        Frank Holten State Park ............ 285,000
16        Golconda/Rauchfuss Hill ............. 79,000
17        I&M Canal - Gebhard Woods State
18         Park ............................... 35,000
19        Prophetstown State Park ............ 155,000
20        William W. Powers State Park ....... 106,000
21    For constructing hazardous material storage
22      buildings ....................................      275,000
23        Total, Section 7                              $54,339,000
24        Section  7a.  The  following  named  amounts,  or so much
25    thereof as  may  be  necessary,  are  appropriated  from  the
26    General Revenue Fund to the Capital Development Board for the
27    Department  of Natural Resources for the projects hereinafter
28    enumerated:
29                   APPLE RIVER CANYON STATE PARK -
30                          JO DAVIESS COUNTY
31    For stabilizing the river bank ................. $    150,000
32                    GOLCONDA MARINA - POPE COUNTY
33    For constructing a sewage lift station .........       50,000
                            -14-                BOB-CAPITAL99
 1                     ILLINOIS BEACH STATE PARK -
 2                             LAKE COUNTY
 3    For stabilizing the shoreline ..................      400,000
 4                      STARVED ROCK STATE PARK -
 5                           LASALLE COUNTY
 6    For constructing erosion controls ..............      300,000
 7                              STATEWIDE
 8    For maintaining lodge and concession
 9      facilities ...................................      400,000
10    For rehabilitating or replacing playground
11      equipment ....................................      300,000
12        Total, Section 7a                              $1,600,000
13        Section 8a.  The  following  named  amount,  or  so  much
14    thereof as may be necessary, is appropriated from the General
15    Revenue  Fund  to  the  Capital  Development  Board  for  the
16    Department of Revenue for the project hereinafter enumerated:
17                 WILLARD ICE BUILDING - SPRINGFIELD
18    For resealing and replacing atrium windows ..... $  1,208,000
19        Total, Section 8a                              $1,208,000
20        Section  9.  The  following  named  amounts,  or  so much
21    thereof as  may  be  necessary,  are  appropriated  from  the
22    Capital Development Fund to the Capital Development Board for
23    the  Department  of State Police for the projects hereinafter
24    enumerated:
25                         SPRINGFIELD ARMORY
26    For planning and design of the rehabilitation
27      and site improvements of the Springfield
28      Armory, in addition to funds previously
29      appropriated .................................    1,500,000
30                              STATEWIDE
31    For replacing the roofing systems at various
32      facilities at the approximate costs set
                            -15-                BOB-CAPITAL99
 1      forth below ..................................      167,000
 2        District 17 - LaSalle ............... 41,000
 3        Springfield, Radio Repair
 4         Laboratory ......................... 36,000
 5        Springfield, Communications
 6         Building ........................... 90,000
 7    For replacing radio communication towers,
 8      equipment buildings and installing emergency
 9      power generators at the following locations:
10      Pecatonica, Elwood, Kingston, Mason
11      City .........................................    2,000,000
12        Total, Section 9                               $3,667,000
13        Section 9a.  The  following  named  amount,  or  so  much
14    thereof as may be necessary, is appropriated from the General
15    Revenue  Fund  to  the  Capital  Development  Board  for  the
16    Department  of  State  Police  for  the  project  hereinafter
17    enumerated:
18                     TRAINING FACILITY - PAWNEE
19    For rehabilitating the driving track ........... $    513,000
20        Total, Section 9a                                $513,000
21        Section  10.  The  following  named  amounts,  or so much
22    thereof as  may  be  necessary,  are  appropriated  from  the
23    Capital Development Fund to the Capital Development Board for
24    the   Department   of  Veterans'  Affairs  for  the  projects
25    hereinafter enumerated:
26                       MANTENO VETERANS' HOME
27    For constructing a multi-purpose
28      building ..................................... $    439,000
29                        QUINCY VETERANS' HOME
30    For improvements to meet licensure
31      standards ....................................    9,000,000
32        Total, Section 10                              $9,439,000
                            -16-                BOB-CAPITAL99
 1        Section 10a.  The following named  amounts,  or  so  much
 2    thereof  as  may  be  necessary,  are  appropriated  from the
 3    General Revenue Fund to the Capital Development Board for the
 4    Department of Veterans' Affairs for the projects  hereinafter
 5    enumerated:
 6                   ILLINOIS VETERANS' HOME - ANNA
 7    Complete visitors center, in addition
 8      to funds previously appropriated ............. $    100,000
 9    For installing lighting, benches,
10      landscaping and ADA improvements .............      934,000
11                  ILLINOIS VETERANS' HOME - LASALLE
12    For installing wall protection .................      107,000
13                  ILLINOIS VETERANS' HOME - QUINCY
14    For resurfacing Schapers Hospital
15      parking lot ..................................       91,000
16                  ILLINOIS VETERANS' HOME - MANTENO
17    For tuckpointing and repairing masonry .........    1,026,000
18        Total, Section 10a                             $2,258,000
19        Section  11.01.  The  following named amounts, or so much
20    thereof as  may  be  necessary,  are  appropriated  from  the
21    Capital Development Fund to the Capital Development Board for
22    projects hereinafter enumerated:
23                  FIFTH DISTRICT APPELLATE COURT -
24                             MT. VERNON
25    For expanding the courthouse ................... $  1,625,000
26                SUPREME COURT BUILDING - SPRINGFIELD
27    For replacing plumbing system ..................    1,000,000
28                     ATTORNEY GENERAL'S OFFICE -
29                             SPRINGFIELD
30    For planning an annex or addition and
31      parking facilities ...........................      200,000
32        Total, Section 11.01                           $2,825,000
                            -17-                BOB-CAPITAL99
 1        Section  11.01a.  The following named amounts, or so much
 2    thereof as  may  be  necessary,  are  appropriated  from  the
 3    General  Revenue  Fund  to  the Capital Development Board for
 4    projects hereinafter enumerated:
 5               SECOND DISTRICT APPELLATE COURT - ELGIN
 6    For upgrading mechanical systems
 7      and building exterior ........................      190,000
 8                   EXECUTIVE MANSION - SPRINGFIELD
 9    For renovating interior, exterior and site,
10      in addition to funds previously appropriated .      190,000
11        Total, Section 11.01a                            $380,000
12        Section 11.02.  The following named amounts, or  so  much
13    thereof  as  may  be  necessary,  are  appropriated  from the
14    Capital Development Fund to the Capital Development Board for
15    projects hereinafter enumerated:
16                           CAPITOL COMPLEX
17    For upgrading HVAC system at the Archives
18      Building, in addition to funds previously
19      appropriated ................................. $    375,000
20    For renovating 222 South College
21      Building .....................................    2,500,000
22        Total, Section 11.02                           $2,875,000
23        Section 11.03.  The following named amounts, or  so  much
24    thereof  as  may  be  necessary,  are  appropriated  from the
25    Capital Development Fund to the Capital Development Board for
26    projects hereinafter enumerated:
27    For surveys and modifications to buildings
28      to meets requirements of the federal
29      Americans With Disabilities Act .............. $  5,000,000
30    For retrofitting or upgrading mechanized
31      refrigeration equipment (CFCs) ...............    7,000,000
32    For abating hazardous materials ................    5,000,000
                            -18-                BOB-CAPITAL99
 1    For upgrading and remediating underground
 2      storage tanks ................................    7,500,000
 3        Total, Section 11.03                          $24,500,000
 4        Section 11.03a.  The following named amounts, or so  much
 5    thereof  as  may  be  necessary,  are  appropriated  from the
 6    General Revenue Fund to the  Capital  Development  Board  for
 7    projects hereinafter enumerated:
 8                              STATEWIDE
 9    For surveying and abating asbestos-
10      containing materials .........................  $ 1,000,000
11    For remediating minor problems
12      and emergencies ..............................    3,002,000
13    For conducting construction site
14      archeological studies ........................      245,000
15    For demolishing buildings ......................    4,800,000
16        Total, Section 11.03a                          $9,047,000
17        Section  12.  The  following  named  amounts,  or so much
18    thereof as  may  be  necessary,  are  appropriated  from  the
19    Capital Development Fund to the Capital Development Board for
20    the   Illinois  Community  College  Board  for  the  projects
21    hereinafter enumerated:
22                CITY COLLEGES OF CHICAGO/KENNEDY KING
23    For remodeling for a culinary arts
24      educational facility ......................... $ 10,875,000
25                JOHN WOOD COMMUNITY COLLEGE - QUINCY
26    For planning campus buildings and site
27      improvements .................................    1,871,800
28                        JOLIET JUNIOR COLLEGE
29    For remodeling campus buildings ................      220,900
30                     LAKE LAND COLLEGE - MATTOON
31    For constructing a classroom/administration
32      building and purchasing equipment, in addition
                            -19-                BOB-CAPITAL99
 1      to funds previously appropriated .............    5,336,800
 2             LEWIS AND CLARK COMMUNITY COLLEGE - GODFREY
 3    For constructing a classroom/administration
 4      building .....................................   10,125,000
 5            LINCOLN LAND COMMUNITY COLLEGE - SPRINGFIELD
 6    For constructing an addition and remodeling
 7      Sangamon and Menard Halls ....................    3,777,700
 8           MORAINE VALLEY COMMUNITY COLLEGE - PALOS HILLS
 9    For constructing a classroom/administration
10      building, providing site improvements and
11      purchasing equipment, in addition to
12      funds previously appropriated ................    8,309,200
13                       REND LAKE COLLEGE - INA
14    For replacing utility piping ...................    1,546,400
15        Total, Section 12                             $42,062,800
16        Section 13.  The following  named  amounts,  or  so  much
17    thereof  as  may  be  necessary,  are  appropriated  from the
18    Capital Development Fund to the Capital Development Board for
19    the Board of Higher Education for  the  projects  hereinafter
20    enumerated:
21                  MATH AND SCIENCE ACADEMY - AURORA
22    For replacing carpeting, constructing storage
23      building and various site improvements,
24      including extending communications
25      conduit system ............................... $  1,310,000
26               CHICAGO STATE UNIVERSITY - COOK COUNTY
27    For upgrading campus infrastructure, in
28      addition to the funds previously appropriated .   2,700,000
29              EASTERN ILLINOIS UNIVERSITY - CHARLESTON
30    For upgrading campus buildings for health,
31      safety and environmental improvements ........    1,302,100
32              GOVERNORS STATE UNIVERSITY - PARK FOREST
33    For planning main building renovations,
                            -20-                BOB-CAPITAL99
 1      a child development center, and
 2      faculty offices ..............................    1,500,000
 3                 ILLINOIS STATE UNIVERSITY - NORMAL
 4    For remodeling Julian and Moulton Halls ........    7,050,000
 5             NORTHEASTERN ILLINOIS UNIVERSITY - CHICAGO
 6    For replacing fire alarm systems, lighting
 7      and ceilings .................................    2,561,800
 8                NORTHERN ILLINOIS UNIVERSITY - DEKALB
 9    For upgrading storm waterway controls in
10      addition to funds previously appropriated ....    6,716,000
11              SOUTHERN ILLINOIS UNIVERSITY - CARBONDALE
12    For upgrading and remodeling Anthony
13      Hall .........................................    3,131,100
14             SOUTHERN ILLINOIS UNIVERSITY - EDWARDSVILLE
15    For purchasing equipment for the Engineering
16      Building .....................................    6,000,000
17                   SOUTHERN ILLINOIS UNIVERSITY -
18                      EDWARDSVILLE/E. ST. LOUIS
19    For planning a classroom/administration
20      facility in addition to funds previously
21      appropriated .................................    1,179,600
22                  UNIVERSITY OF ILLINOIS - CHICAGO
23    For remodeling the Clinical
24      Sciences Building ............................   15,000,000
25                      UNIVERSITY OF ILLINOIS -
26                          URBANA/CHAMPAIGN
27    For remodeling the Mechanical Engineering
28      Laboratory Building ..........................    7,365,000
29                UNIVERSITY OF ILLINOIS - SPRINGFIELD
30    For constructing and improving campus
31      roadways, in addition to funds previously
32      appropriated .................................    2,412,700
33                WESTERN ILLINOIS UNIVERSITY - MACOMB
34    For constructing a utility tunnel and
                            -21-                BOB-CAPITAL99
 1      installing piping, lines and cables ..........    6,313,400
 2    For remodeling Horrabin and Simpkins
 3      Halls, in addition to funds
 4      previously appropriated.......................    1,655,400
 5        Total, Section 13                             $66,197,100
 6        Section  14.  The  sum of $11,244,000, or so much thereof
 7    as  may  be  necessary,  is  appropriated  from  the  Capital
 8    Development Fund to the Capital  Development  Board  for  the
 9    Board   of   Higher   Education   for  miscellaneous  capital
10    improvements including construction, capital facilities, cost
11    of planning, various  universities  set  forth  below.   This
12    appropriation  shall be in addition to any other appropriated
13    amounts which can be expended for these purposes.
14    For Chicago State University ........... 226,000
15    For Eastern Illinois University ........ 423,100
16    For Governors State University ......... 136,200
17    For Illinois State University .......... 863,000
18    For Northeastern Illinois University ... 317,800
19    For Northern Illinois University ....... 965,800
20    For Western Illinois University ........ 646,800
21    For Southern Illinois University -
22      Carbondale ......................... 1,493,600
23    For Southern Illinois University -
24      Edwardsville ......................... 563,600
25    For University of Illinois - Chicago . 2,460,300
26    For University of Illinois -
27      Springfield .......................... 162,600
28    For University of Illinois -
29      Urbana-Champaign ................... 2,985,200
30        Section 15.  The sum of $3,756,000, or so much thereof as
31    may  be  necessary,  is   appropriated   from   the   Capital
32    Development  Fund  to  the  Capital Development Board for the
                            -22-                BOB-CAPITAL99
 1    Illinois Community College Board  for  miscellaneous  capital
 2    improvements including construction, capital facilities, cost
 3    of planning, supplies, equipment, materials, services and all
 4    other  expenses  required to complete the work at the various
 5    universities set forth below.  This appropriation shall be in
 6    addition to any  other  appropriated  amounts  which  can  be
 7    expended for these purposes.
 8        Section  16.  The  sum of $38,000,000, or so much thereof
 9    as  may  be  necessary,  is  appropriated  from  the   School
10    Infrastructure  Fund  to  the  Capital  Development Board for
11    school   construction   grants   pursuant   to   the   School
12    Construction Law.
13        Section 17.  The sum of $200,000,000, or so much  thereof
14    as   may  be  necessary,  is  appropriated  from  the  School
15    Construction Fund to the Capital Development Board for school
16    construction grants pursuant to the School Construction Law.
17        Section  95.  No  contract  shall  be  entered  into   or
18    obligation  incurred for any expenditures from appropriations
19    made in this Article until after  the  purposes  and  amounts
20    have been approved in writing by the Governor.
21                              ARTICLE 2
22        Section  1.  The  following  named  amounts,  or  so much
23    thereof as may be necessary  and  remain  unexpended  at  the
24    close  of  business on June 30, 1998, from appropriations and
25    reappropriations heretofore made for such purposes in Section
26    52 of Public Act 90-0550 and Article 94, Sections 1 and 1A of
27    Public Act  90-0010,  are  reappropriated  from  the  Capital
28    Development  Fund  to  the  Capital Development Board for the
29    Department  of  Agriculture  for  the  projects   hereinafter
                            -23-                BOB-CAPITAL99
 1    enumerated:
 2                ANIMAL DISEASE LABORATORY - CENTRALIA
 3    (From Article 94, Section 1A of Public Act 90-0010)
 4    For upgrading the diagnostic laboratory
 5      facility, in addition to funds previously
 6      appropriated ................................. $    200,000
 7    (From Article 94, Section 1 of Public Act 90-0010)
 8    For purchasing and upgrading
 9      diagnostic laboratory ........................      506,979
10                      DUQUOIN STATE FAIRGROUNDS
11    (From Section 52 of Public Act 90-0550)
12    For planning the renovation of the
13      Round Houses .................................       40,000
14    (From Article 94, Section 1 of Public Act 90-0010):
15    For replacement of the grandstand
16      bleachers ....................................      759,335
17    For planning and construction of
18      a livestock complex ..........................        6,837
19    For rehabilitation of the Grandstand ...........       13,403
20    For upgrading the racetrack, including the
21      racetrack walls ..............................    2,621,797
22              ILLINOIS STATE FAIRGROUNDS - SPRINGFIELD
23    (From Section 52 of Public Act 90-0550)
24    For replacing the HVAC system in the
25      Administration Building ......................      929,000
26    (From Article 94, Section 1A of Public Act 90-0010)
27    For replacing and/or repairing sidewalks,
28      curbs, gutters and streets, in addition
29      to funds previously appropriated .............      726,766
30    For upgrading the storm/sanitary and water
31      systems, in addition to funds previously
32      appropriated .................................    1,569,538
33    For renovation or replacement of
34      comfort stations, in addition
                            -24-                BOB-CAPITAL99
 1      to funds previously appropriated .............    1,273,000
 2    For upgrading Building 13, in addition to
 3      funds previously appropriated ................      354,035
 4    (From Article 94, Section 1 of Public Act 90-0010)
 5    For renovation of the comfort stations-
 6      Phase I ......................................       74,803
 7    For upgrading Building #13 .....................       19,844
 8    For renovation of the Coliseum .................       17,122
 9    For renovation of the Jr. Livestock Building,
10      including the cover over the outdoor
11      arena, roof, HVAC, plumbing and electrical
12      systems and installation of an elevator
13      for accessibility, and for upgrading
14      the sewer system .............................       71,858
15    For rehabilitation of the Administration
16      Building, including planning & upgrading
17      laboratories .................................       49,869
18    For planning the renovation of the show
19      horse barns ..................................      257,229
20    For rehabilitation of six racehorse barns-
21      Phase I ......................................      165,046
22    For planning the rehabilitation of sidewalks,
23      curbs, gutters and streets ...................      108,724
24        Total, Section 1                               $9,765,185
25        Section  2.  The  following  named  amounts,  or  so much
26    thereof as may be necessary  and  remain  unexpended  at  the
27    close  of  business on June 30, 1998, from appropriations and
28    reappropriations heretofore made for such purposes in Section
29    61 of Public Act 90-0550; Article 93, Section 11.01 of Public
30    Act 90-0010; and Article 94, Section 2, of Public Act 90-0010
31    are reappropriated from the Capital Development Fund  to  the
32    Capital  Development Board for the Courts of Illinois for the
33    projects hereinafter enumerated:
                            -25-                BOB-CAPITAL99
 1          SECOND DISTRICT APPELLATE COURT BUILDING - ELGIN
 2    (From Article 93, Section 11.01 of Public Act 90-0010)
 3    For replacing the roof ......................... $    104,000
 4                SPRINGFIELD - SUPREME COURT BUILDING
 5    (From Section 61 of Public Act 90-0550)
 6    For planning the library upgrade ...............      127,000
 7    (From Article 94, Section 2 of Public Act 90-0010)
 8    For installation of an elevator and
 9      replacement of the exterior lights ...........       29,564
10    For repairing the ramp, drainage system,
11      retaining wall and landscaping ...............       19,767
12        Total, Section 2                                 $280,331
13        Section 2.1.  The following  named  amount,  or  so  much
14    thereof  as  may  be  necessary and remains unexpended at the
15    close of business on June 30,  1998,  from  an  appropriation
16    heretofore  made  for  such  purposes  in Article 93, Section
17    11.01a of Public Act  90-0010,  is  reappropriated  from  the
18    General Revenue Fund to the Capital Development Board for the
19    project hereinafter enumerated:
20                SUPREME COURT BUILDING - SPRINGFIELD
21    For tuckpointing and cleaning exterior ...........$   220,000
22        Section  3.  The  following  named  amounts,  or  so much
23    thereof as may be necessary  and  remain  unexpended  at  the
24    close  of  business on June 30, 1998, from appropriations and
25    reappropriations heretofore made for such purposes in Section
26    53 of Public Act 90-0550; Article 93, Section 2 of Public Act
27    90-0010; Article 94, Section 3, of Public  Act  90-0010;  and
28    Section 3A of Public Act 90-0010, are reappropriated from the
29    Capital Development Fund to the Capital Development Board for
30    the   Department  of  Central  Management  Services  for  the
31    projects hereinafter enumerated:
32                   ELGIN REGIONAL OFFICE BUILDING
                            -26-                BOB-CAPITAL99
 1    (From Section 53 of Public Act 90-0550)
 2    For replacing the utility system ............... $  2,625,000
 3               ILLINOIS CENTER FOR REHABILITATION AND
 4                     EDUCATION (WOOD) - CHICAGO
 5    (From Article 93, Section 2 of Public Act 90-0010)
 6    For replacing the skylight system
 7      and roof flashing ............................       45,000
 8    For installing security system and
 9      perimeter lighting ...........................      375,000
10               ILLINOIS CENTER FOR REHABILITATION AND
11                   EDUCATION (ROOSEVELT) - CHICAGO
12    (From Article 94, Section 3a of Public Act 90-0010)
13    For upgrading the HVAC system ..................    2,250,000
14                 CENTRAL STATE GARAGE - SPRINGFIELD
15    (From Article 93, Section 2 of Public Act 90-0010)
16    For replacing the roof and drainage system .....      425,000
17                 CHICAGO - STATE OF ILLINOIS CENTER
18    (From Article 94, Section 3 of Public Act 90-0010)
19    For completing the installation of elevators, in
20      addition to funds previously appropriated ....      650,760
21    For the correction of design/construction
22      deficiencies, including remedial work in
23      the heating, refrigeration, temperature
24      control and ventilation systems at the
25      State of Illinois Center at Chicago ..........      269,259
26                CHICAGO - STATE OF ILLINOIS BUILDING
27    For planning, renovation, equipment and all
28      other costs associated with the renovation
29      of the State of Illinois Building located
30      at 160 North LaSalle in Chicago, in addition
31      to any other amounts heretofore
32      appropriated for such purpose ................       16,879
33    For planning for renovation of the building
34      at 160 North LaSalle .........................       46,367
                            -27-                BOB-CAPITAL99
 1                       CHICAGO MEDICAL CENTER
 2          ILLINOIS CENTER FOR REHABILITATION AND EDUCATION
 3    For completing the upgrade of HVAC system, in
 4      addition to funds previously appropriated ....       81,448
 5    For construction of an independent living
 6      apartment building ...........................      104,140
 7    For rehabilitation of the air conditioning
 8      system, installation of a sprinkler system
 9      and improvements for handicapped
10      accessibility ................................      105,913
11                       CHICAGO MEDICAL CENTER
12                        EVELYN EDWARDS CENTER
13    For replacement of the heating system ..........       25,274
14                       CHICAGO MEDICAL CENTER
15                   OFFICE AND LABORATORY FACILITY
16    For replacement of the electric autoclave
17      boilers ......................................       13,222
18                       CHICAGO MEDICAL CENTER
19                   VISUALLY HANDICAPPED INSTITUTE
20    For renovation of the loading dock .............       46,058
21                REGIONAL OFFICE BUILDING - CHAMPAIGN
22    For replacement of roofing system and
23      rooftop heating and cooling unit .............       88,451
24    (From Article 94, Section 3A of Public Act 90-0010)
25              SUBURBAN NORTH REGIONAL OFFICE BUILDING -
26                             DES PLAINES
27    For renovation of Suburban North Regional
28      Office Building (formerly Maine Township
29      North High School building), in addition
30      to funds previously appropriated for such
31      purpose, Phase III ...........................    5,400,000
32    For renovation and expansion of garage .........      375,000
33    (From Article 94, Section 3 of Public Act 90-0010)
34    For designing the renovation, phase III ........      562,615
                            -28-                BOB-CAPITAL99
 1    For the purchase and renovation of the high
 2      school .......................................       17,210
 3                         OTTAWA STATE GARAGE
 4    For rehabilitation of the lighting and
 5      electrical systems ...........................      106,694
 6                    SPRINGFIELD - CAPITOL COMPLEX
 7    For construction of a day care center, in
 8      addition to funds previously appropriated
 9      for such purpose .............................      950,000
10    For construction of a day care center in the
11      Capitol Complex in Springfield ...............      244,348
12                   COMPUTER FACILITY - SPRINGFIELD
13    (From Article 94, Section 3A of Public Act 90-0010)
14    For replacement of the halon fire
15      suppression system ...........................      861,030
16    (From Article 94, Section 3 of Public Act 90-0010)
17                        ASH STREET COMPLEX -
18                   MUSEUM AND COLLECTION CENTER -
19                             SPRINGFIELD
20    For replacement of the roofing system ..........      667,928
21    (From Article 94, Section 3A of Public Act 90-0010)
22                   MARION REGIONAL OFFICE BUILDING
23    For construction of a Regional Office
24      Building Addition ............................    2,000,000
25        Total, Section 3                              $18,352,596
26        Section 3.1.  The following named  amounts,  or  so  much
27    thereof  as  may  be  necessary  and remain unexpended at the
28    close of business on June 30, 1998, from  appropriations  and
29    reappropriations heretofore made for such purposes in Article
30    93, Section 2a of Public Act 90-0010, and Article 94, Section
31    3.1  of  Public  Act  90-0010,  are  reappropriated  from the
32    General Revenue Fund to the Capital Development Board for the
33    Department of Central Management Services  for  the  projects
                            -29-                BOB-CAPITAL99
 1    hereinafter enumerated:
 2                 JAMES R. THOMPSON CENTER - CHICAGO
 3    (From Article 93, Section 2a of Public Act 90-0010)
 4    For restoring the exterior plaza ............... $    890,000
 5                  EAST ST. LOUIS - REGIONAL OFFICE
 6    For replacing windows ..........................       65,000
 7                       CHICAGO MEDICAL CENTER
 8          ILLINOIS CENTER FOR REHABILITATION AND EDUCATION
 9    (From Article 94, Section 3.1 of Public Act 90-0010)
10    For rehabilitation for fire safety and
11      accessibility ................................       11,086
12                       CHICAGO MEDICAL CENTER
13                     JUVENILE RESEARCH INSTITUTE
14    For rehabilitation of the interior and
15      exterior walls, planning the rehabilitation
16      of the HVAC system and renovation of
17      the elevator .................................       23,433
18        Total, Section 3.1                               $989,519
19        Section  4.  The  following  named  amounts,  or  so much
20    thereof as may be necessary, and  remain  unexpended  at  the
21    close  of  business on June 30, 1998, from appropriations and
22    reappropriations heretofore made for such purposes in Section
23    58 of Public Act 90-0550; Article 93, Section 7 of Public Act
24    90-0010; Article 94, Section 4 of  Public  Act  90-0010;  and
25    Article 4A of Public Act 90-0010, are reappropriated from the
26    Capital Development Fund to the Capital Development Board for
27    the   Department   of  Natural  Resources  for  the  projects
28    hereinafter enumerated:
29             CHAIN O' LAKES STATE PARK - MCHENRY COUNTY
30    (From Article 94, Section 4A of Public Act 90-0010)
31    For construction of a concession building
32      and upgrading the horse concession, in
33      addition to funds previously appropriated .... $    500,000
                            -30-                BOB-CAPITAL99
 1    (From Article 94, Section 4 of Public Act 90-0010)
 2    For Chain O'Lakes State Park for replacement
 3      of overhead power lines ......................       21,036
 4    For Chain O'Lakes State Park for planning
 5      the replacement of concession buildings ......       37,734
 6    (From Article 94, Section 4A of Public Act 90-0010)
 7                DELABAR STATE PARK - HENDERSON COUNTY
 8    For replacement of waterlines and
 9      fountains ....................................       99,925
10    (From Article 94, Section 4A of Public Act 90-0010)
11             FOR EAGLE CREEK STATE PARK - SHELBY COUNTY
12    For rehabilitation of the sewage treatment
13      system, in addition to funds previously
14      appropriated .................................      312,000
15    (From Article 94, Section 4 of Public Act 90-0010)
16    For Eagle Creek State Park for planning and
17      rehabilitation of the sewage treatment
18      system .......................................      269,450
19    For Fort Massac State Park for planning the
20      reconstruction of the fort ...................      141,700
21    (From Article 93, Section 7 of Public Act 90-0010)
22          HENNEPIN CANAL PARKWAY STATE PARK AND ACCESS AREA
23    For stabilizing the feeder canal bank ..........      500,000
24    (From Article 94, Section 4A of Public Act 90-0010)
25    For replacement and rehabilitation
26      of arch culverts and canal ...................      575,148
27    (From Article 94, Section 4 of Public Act 90-0010)
28    For Heron Pond-Little Black Slough for
29      improvements for erosion control .............      213,537
30    For Horseshoe Lake Conservation Area for
31      dam rehabilitation and land acquisition ......      858,655
32    For Horseshoe Lake State Fish and Wildlife
33      Area for construction of a pole building
34      and hunter check station .....................       83,816
                            -31-                BOB-CAPITAL99
 1    For Illinois Beach State Park for
 2      stabilization of shoreline ...................      177,565
 3    For Illinois-Michigan Canal State Park for
 4      stabilization of the aqueduct ................      504,341
 5    (From Article 94, Section 4A of Public Act 90-0010)
 6          FOR JOHNSON SAUK TRAIL STATE PARK - HENRY COUNTY
 7    For rehabilitation of the concession
 8      building, in addition to funds
 9      previously appropriated ......................      140,000
10    (From Article 94, Section 4 of Public Act 90-0010)
11    For Johnson Sauk Trail State Park for
12      rehabilitation of the concession building ....       87,975
13    (From Section 58 of Public Act 90-0550)
14              FOR KANKAKEE STATE PARK - KANKAKEE COUNTY
15    For planning and constructing a
16      sanitary sewer system ........................      200,000
17    (From Article 94, Section 4A of Public Act 90-0010)
18             FOR KICKAPOO STATE PARK - VERMILION COUNTY
19    For construction of a sewage treatment
20      plant, in addition to funds
21      previously appropriated ......................      918,194
22    (From Article 94, Section 4 of Public Act 90-0010)
23    For Mason State Forest Tree Nursery for
24      installation of an emergency power system
25      and upgrading the irrigation system ..........        5,155
26    (From Section 58 of Public Act 90-0550)
27          FOR MERMET LAKE CONSERVATION AREA - MASSAC COUNTY
28    For rehabilitating the levee system ............      225,000
29    (From Article 94, Section 4A of Public Act 90-0010)
30            FOR MORAINE HILLS STATE PARK - MCHENRY COUNTY
31    For renovation of the trail ....................      338,496
32    (From Article 94, Section 4 of Public Act 90-0010)
33    For Moraine Hills State Park for replacement
34      of restrooms and upgrading the
                            -32-                BOB-CAPITAL99
 1      water system .................................      839,952
 2    (From Article 94, Section 4A of Public Act 90-0010)
 3             FOR MORAINE VIEW STATE PARK - MCLEAN COUNTY
 4    For construction of a sewage treatment
 5      system and plant .............................    1,609,600
 6    (From Article 94, Section 4 of Public Act 90-0010)
 7    For North Point Marina for construction of
 8      a breakwater structure .......................    2,714,211
 9    For North Point Marina for modifying
10      the marina's docking system ..................    2,122,839
11    (From Article 94, Section 4A of Public Act 90-0010)
12            FOR PERE MARQUETTE STATE PARK - JERSEY COUNTY
13    For renovation of two buildings and
14      replacement of a storage building ............      180,000
15    (From Section 58 of Public Act 90-0550)
16             FOR RED HILLS STATE PARK - LAWRENCE COUNTY
17    For replacing the sewage treatment system,
18      in addition to funds previously appropriated .      510,000
19    For rehabilitating the dam .....................       90,000
20    (From Article 94, Section 4 of Public Act 90-0010)
21    For Sam Dale Lake Conservation Area for
22      construction of a sewage disposal system .....       29,162
23    (From Section 58 of Public Act 90-0550)
24                  FOR SANGANOIS CONSERVATION AREA -
25                  CASS, MASON AND SCHUYLER COUNTIES
26    For rehabilitating the levee system ............      315,000
27    (From Article 94, Section 4 of Public Act 90-0010)
28    For Springfield Illinois State Fairgrounds
29      for the upgrade of access roads,
30      parking lots, and visitor trails at
31      Conservation World and the Conservation
32      Service Center ...............................       55,173
33    (From Article 94, Section 4A of Public Act 90-0010)
34              STARVED ROCK STATE PARK - LASALLE COUNTY
                            -33-                BOB-CAPITAL99
 1    For construction of a Visitors'
 2      Center, in addition to funds
 3      previously appropriated ......................      365,000
 4    For rehabilitation of trails, in addition
 5      to funds previously appropriated .............    1,000,000
 6    For reconstruction of the seawall, in
 7      addition to funds previously
 8      appropriated .................................      149,726
 9    For rehabilitation of the sewer
10      system - Phase I .............................      171,500
11    (From Article 94, Section 4 of Public Act 90-0010)
12    For Starved Rock State Park for planning the
13      rehabilitation of the trails .................       71,900
14    For Starved Rock State Park for planning the
15      reconstruction of the seawall ................       57,340
16    For Stephen A. Forbes State Park for extending
17      water and electrical services ................       99,656
18    For Tri-County Park for planning
19      a park .......................................      104,040
20    For Volo Bog Natural Area for rehabilitation
21      of the visitors' center ......................       13,008
22    For Wayne Fitzgerrell State Park for
23      rehabilitation of the sewage treatment
24      plant ........................................      214,249
25    For Wayne Fitzgerrell State Park for
26      planning and construction of a marina,
27      installation of additional sewage lines,
28      recreational development and overnight
29      accommodations to be located on Rend
30      Lake .........................................       14,599
31      NATURAL HISTORY SURVEY - NATURAL HISTORY RESEARCH CENTER
32                     (FORMERLY BURNHAM HOSPITAL)
33    (From Article 94, Section 4A of Public Act 90-0010)
34    For renovation of Natural History
                            -34-                BOB-CAPITAL99
 1      Research Center (formerly Burnham
 2      Hospital) in Champaign .......................    6,000,000
 3    (From Article 94, Section 4 of Public Act 90-0010)
 4    For planning and initiating the renovation of the
 5      Natural History Research Center (formerly
 6      Burnham Hospital) ............................    3,112,305
 7    For acquisition, planning, construction,
 8      reconstruction, rehabilitation, and all
 9      costs for the conversion of the Natural
10      History Research Center (formerly Burnham
11      Hospital) to a laboratory facility
12      for the Natural History Survey ...............       46,527
13                 NATURAL HISTORY SURVEY - CHAMPAIGN
14    For upgrading laboratories and installation
15      of storage units .............................      725,491
16                   STATE WATER SURVEY - CHAMPAIGN
17    (From Article 94, Section 4A of Public Act 90-0010)
18    For renovation of office and
19      laboratory buildings .........................      751,538
20    For replacement and upgrade of the
21      exterior lighting system .....................      140,283
22    (From Article 94, Section 4 of Public Act 90-0010)
23    For planning and replacement of vehicle
24      storage/shop facilities ......................       21,150
25    (From Section 58 of Public Act 90-0550)
26                     DICKSON MOUNDS - LEWISTOWN
27    For renovating Canton Liverpool
28      Toll Booth ...................................       73,000
29    (From Article 94, Section 4 of Public Act 90-0010)
30                     DICKSON MOUNDS - LEWISTOWN
31    For renovation and expansion of the building,
32      including exhibits ...........................       81,340
33    (From Article 94, Section 4A of Public Act 90-0010)
34      STATE MUSEUM RESEARCH AND COLLECTION CENTER - SPRINGFIELD
                            -35-                BOB-CAPITAL99
 1    For the completion of site improvements ........      559,000
 2                     STATE MUSEUM - SPRINGFIELD
 3    For planning and replacement of the main
 4      museum exhibits, in addition to funds
 5      previously appropriated ......................      700,000
 6    (From Article 94, Section 4 of Public Act 90-0010)
 7    For planning renovation of main museum
 8      exhibits and for renovation of basement
 9      galleries ....................................       36,266
10              BENTON - SOUTHERN ILLINOIS MINING OFFICE
11                   (FORMERLY MINE RESCUE STATION)
12    For upgrading the roofing and HVAC systems
13      and replacing exterior doors .................       25,524
14                              STATEWIDE
15    (From Section 58 of Public Act 90-0550)
16    For replacing concession buildings and
17      upgrading support facilities at the following
18      locations at the approximate costs set
19      forth below: .................................    2,895,000
20       Kickapoo State Park ..................538,000
21       Rock Cut State Park ..................525,000
22       Stephen A. Forbes State Park .......1,832,000
23                              STATEWIDE
24    For constructing vault toilets at the
25      following locations at the approximate
26      cost set forth below: ........................    1,593,000
27       Apple River Canyon State Park ........285,000
28       Des Plaines Conservation Area ........240,000
29       Kankakee River State Park ............410,000
30       Lake Le-Aqua-Na State Park ...........295,000
31       Marshall County Conservation Area .....83,000
32       Morrison-Rockwood State Park .........195,000
33       Rice Lake Conservation Area ...........85,000
34    (From Article 93, Section 7 of Public Act 90-0010)
                            -36-                BOB-CAPITAL99
 1                              STATEWIDE
 2    For replacing roofing systems and structural
 3      repairs at the following locations at the
 4      approximate costs set forth below: ...........      452,000
 5       Mine Rescue Station, One building .....36,000
 6       Castle Rock State Park,
 7        One building .........................37,000
 8       Dixon Springs State Park,
 9        Three buildings ......................49,000
10       Cave-In-Rock State Park,
11        One building .........................30,000
12       Ferne Clyffe State Park,
13        One building .........................30,000
14       Hamilton County Conservation
15        Area, One building ...................30,000
16       Lake Murphysboro State Park
17        Two buildings ........................54,000
18       Red Hills State Park, Two
19        buildings ............................34,000
20       Fox Ridge State Park, Six
21        buildings ............................73,000
22       Shelbyville Fish and Wildlife
23        Area, Two buildings ..................49,000
24       Newton Lake Fish and Wildlife
25        Area, One building ...................30,000
26    (From Article 94, Section 4 of Public Act 90-0010)
27    For repair or replacement of roofs and
28      parapet walls and reconstruction of
29      chimneys at the following locations
30      at the approximate costs set forth below .....      599,198
31       Geological Survey - Applied Lab ......234,000
32       Water Survey - Eight Buildings .......125,000
33       Natural History Survey - Natural
34        Resources Studies Annex ..............70,000
                            -37-                BOB-CAPITAL99
 1       Geological Survey - Natural
 2        Resources Building ...................10,000
 3       Water Survey - Parapet walls at
 4        Buildings No. 4, 5 and 6 .............10,000
 5       Dickson Mounds - Exterior restroom
 6        and picnic shelter ...................14,530
 7       Jake Wolf Fish Hatchery -
 8        one building ........................135,668
 9    For land acquisition ...........................      915,505
10    For maintaining the lodge and concession
11      facilities ...................................      130,476
12    For repairing and maintaining facilities .......       55,065
13    For construction of hazardous material
14      storage buildings ............................      316,662
15    For abating hazards caused by the presence
16      of asbestos-containing materials .............       51,622
17    For planning, construction, reconstruction,
18      land acquisition and related costs,
19      utilities, site improvements, and all other
20      expenses necessary for various capital
21      improvements at parks, conservation areas,
22      and other facilities under the jurisdiction
23      of the Department of Natural Resources .......   14,134,450
24    For rehabilitation of the recreational
25      vehicle campground electrical systems at
26      the following locations at the approximate
27      costs set forth below: .......................       68,550
28       Kankakee River State Park .............68,550
29    For construction and development of
30      multiple use facilities on lands owned
31      or managed by the Department of
32      Natural Resources, including all costs
33      for supplies, materials, labor, and
34      services required for the completion
                            -38-                BOB-CAPITAL99
 1      of the following projects at the
 2      approximate costs set forth below: ...........       25,786
 3       For Volo Bog Natural Area
 4        for replacement of a roof
 5        and rehabilitation of the
 6        emergency exit stairs at the
 7        visitor center ........................5,786
 8       For Volo Bog Natural Area for
 9        the upgrading of the
10        Interpretive Center, including
11        the heating, ventilation, and
12        air conditioning system ..............20,000 ____________
13        Total, Section 4                              $50,446,420
14        Section 4.1.  The following named  amounts,  or  so  much
15    thereof   as   may  be  necessary,  from  appropriations  and
16    reappropriations heretofore made for such purposes in Article
17    93, Section 7A of Public Act 90-0010, and Article 94, Section
18    4.1 of  Public  Act  90-0010,  are  reappropriated  from  the
19    General Revenue Fund to the Capital Development Board for the
20    Department  of Natural Resources for the projects hereinafter
21    enumerated:
22    (From Article 93, Section 7A of Public Act 90-0010)
23                      ILLINOIS BEACH STATE PARK
24    For stabilizing the shoreline .................. $    400,000
25    (From Article 94, Section 4.1 of Public Act 90-0010)
26    For stabilization of the shoreline .............      371,052
27                              STATEWIDE
28    (From Article 93, Section 7A of Public Act 90-0010)
29    For maintaining lodge and concession
30      facilities at various DNR locations ..........      400,000
31    For rehabilitating or replacing
32      playground equipment, in addition
33      to funds previously appropriated .............      300,000
                            -39-                BOB-CAPITAL99
 1    (From Article 94, Section 4.1 of Public Act 90-0010)
 2    For maintenance of lodge and
 3      concession facilities ........................      133,387
 4    For rehabilitation or replacement
 5      of playground equipment ......................      250,000
 6    For rehabilitation of trail systems ............      140,000
 7    For maintenance of the lodge and
 8      concession facilities ........................       10,231
 9    For rehabilitation and replacement of
10      playground equipment .........................      323,000
11    For Chain O'Lakes State Park for replacement
12      of windows and floor tile in Region 2
13      headquarters .................................       87,000
14    For Illinois Beach State Park for
15      stabilization of the shoreline ...............       57,840
16    For Spring Grove Hatchery for upgrading the
17      septic system ................................       30,000
18        Total, Section 4.1                             $2,502,510
19        Section 5.  The  following  named  amounts,  or  so  much
20    thereof  as  may  be  necessary  and remain unexpended at the
21    close of business on June 30, 1998, from  appropriations  and
22    reappropriations heretofore made for such purposes in Section
23    54 of Public Act 90-0550; Article 93, Section 3 of Public Act
24    90-0010;  and  Article  94,  Sections  5 and 5A of Public Act
25    90-0010, are reappropriated from the Capital Development Fund
26    to the  Capital  Development  Board  for  the  Department  of
27    Corrections for the projects hereinafter enumerated:
28    (From Section 54 of Public Act 90-0550)
29    For planning, design, construction,
30      equipment and other necessary costs
31      for a Maximum Security Correctional
32      Center, in addition to funds previously
33      appropriated ................................. $  95,000,000
                            -40-                BOB-CAPITAL99
 1    (From Article 94, Section 5A of Public Act 90-0010)
 2                    DANVILLE CORRECTIONAL CENTER
 3    For renovation of interior and
 4      exterior walls, in addition to
 5      funds previously appropriated ................    3,898,027
 6    (From Article 94, Section 5 of Public Act 90-0010)
 7    For renovation of interior walls and
 8      exterior masonry walls .......................       26,591
 9    For correction of construction defects .........      263,178
10    For planning, utilities, site improvements,
11      and other expenses necessary for the
12      construction of a correctional facility ......       32,511
13    (From Article 94, Section 5A of Public Act 90-0010)
14                 DECATUR WOMEN'S CORRECTIONAL CENTER
15    For the planning and conversion of
16      Meyer Mental Health Center into a
17      correctional facility ........................   22,448,629
18                      DIXON CORRECTIONAL CENTER
19    For renovation of the groundwater
20      storage tank and abatement of crawl-
21      space pipes in Bldgs. 26, 27 and 29 ..........      671,564
22    (From Article 94, Section 5 of Public 90-0010)
23    For upgrading the steam distribution system
24      and replacement of the boiler system
25      including asbestos abatement .................       87,937
26                     DWIGHT CORRECTIONAL CENTER
27    (From Article 93, Section 3 of Public Act 90-0010)
28    For upgrading water and sewer systems ..........    1,000,000
29    For renovating buildings, in addition
30      funds previously appropriated ................      600,000
31    For constructing a gatehouse and
32      sallyport and upgrading the
33      security system ..............................    2,375,000
34    (From Article 94, Section 5A of Public Act 90-0010)
                            -41-                BOB-CAPITAL99
 1    For completion of medical unit,
 2      in addition to funds previously
 3      appropriated .................................    2,771,159
 4    For expansion of the Education Building
 5      and Dietary and construction of
 6      a warehouse ..................................    4,514,821
 7    (From Article 94, Section 5 of Public Act 90-0010)
 8    For renovation of buildings ....................       68,958
 9                   EAST MOLINE CORRECTIONAL CENTER
10    (From Article 93, Section 3 of Public Act 90-0010)
11    For upgrading the electrical
12      system .......................................    2,300,000
13    (From Article 94, Section 5A of Public Act 90-0010)
14    For upgrading locking system, in addition
15      to funds previously appropriated .............      800,000
16    (From Article 94, Section 5 of Public Act 90-0010)
17    For planning the upgrade of locking
18      systems in nine buildings ....................       32,815
19                 ILLINOIS YOUTH CENTER - HARRISBURG
20    (From Article 94, Section 5A of Public Act 90-0010)
21    For upgrading the domestic water system ........      675,000
22    For upgrading the HVAC system ..................      532,000
23                   ILLINOIS YOUTH CENTER - JOLIET
24    (From Article 94, Section 5A of Public Act 90-0010)
25    For planning, site improvements,
26      utility upgrade, equipment and all
27      costs necessary to construct a
28      housing unit and dietary facility ............    6,374,770
29    (From Article 94, Section 5 of Public Act 90-0010)
30    For completing the upgrade of electrical
31      systems, in addition to funds
32      previously appropriated ......................      327,692
33    For upgrading the fire alarm system ............      191,768
34    For completing the upgrade of the utilities, in
                            -42-                BOB-CAPITAL99
 1      addition to funds previously appropriated ....       40,647
 2               ILLINOIS YOUTH CENTER - PERE MARQUETTE
 3    (From Article 94, Section 5A of Public Act 90-0010)
 4    For upgrading the electrical
 5      distribution system ..........................      215,000
 6    (From Article 94, Section 5 of Public Act 90-0010)
 7                 ILLINOIS YOUTH CENTER - ST. CHARLES
 8    For completing the upgrade of the water
 9      distribution system, in addition to funds
10      previously appropriated ......................      131,555
11                 ILLINOIS YOUTH CENTER - VALLEY VIEW
12    (From Article 94, Section 5A of Public Act 90-0010)
13    For upgrading dormitory restrooms
14      and fixtures, in addition to
15      funds previously appropriated ................      550,000
16    (From Article 94, Section 5 of Public Act 90-0010)
17    For planning the upgrade of dormitory restrooms
18      and fixtures .................................       68,560
19                     JOLIET CORRECTIONAL CENTER
20    (From Article 93, Section 3 of Public Act 90-0010)
21    For correcting erosion and
22      stabilizing the masonry wall .................    1,800,000
23    (From Article 94, Section 5A of Public Act 90-0010)
24    For upgrading the power house and
25      installation of a generator ..................      398,400
26    (From Article 94, Section 5 of Public Act 90-0010)
27    For completing the west cellhouse renovation,
28      including asbestos abatement, in addition
29      to funds previously appropriated .............    1,654,475
30    For renovation of the west cellhouse, in
31      addition to funds previously appropriated ....       19,405
32    For planning the rehabilitation of the
33      West Cellhouse ...............................        4,924
34                     LINCOLN CORRECTIONAL CENTER
                            -43-                BOB-CAPITAL99
 1    (From Article 94, Section 5A of Public Act 90-0010)
 2    For upgrading the water softener system ........      150,000
 3    (From Article 94, Section 5 of Public Act 90-0010)
 4    For upgrading the locking systems and doors ....       77,700
 5    For upgrading the water supply .................      356,077
 6    For renovation of the Dietary, construction
 7      of a cooler addition and installation
 8      of blast chillers ............................      487,520
 9                      LOGAN CORRECTIONAL CENTER
10    For renovation of sewer system .................      826,383
11    For renovation of the water tower ..............      124,144
12    For rehabilitation of the roof ventilation
13      systems ......................................       77,948
14                MENARD CORRECTIONAL CENTER - CHESTER
15    (From Article 93, Section 3 of Public Act 90-0010)
16    For renovating the Old Hospital
17      Building, in addition to funds
18      previously appropriated ......................    4,700,000
19    For replacing and installing
20      water storage tank ...........................    1,200,000
21    For replacing Boiler #2, in addition
22      to funds previously appropriated .............      800,000
23    For converting a room into a shower room .......      395,000
24    (From Article 94, Section 5A of Public Act 90-0010)
25    For upgrading roads and sidewalks ..............      276,632
26    For upgrading the plumbing systems in
27      two buildings ................................      292,524
28    For upgrading the coal handling system
29      and repair or replace boiler system ..........      646,253
30    For conversion of the Maintenance Building
31      to an inmate dormitory .......................      250,000
32    For conversion of the Administration
33      Building basement to a courtroom and
34      attorney offices .............................      100,000
                            -44-                BOB-CAPITAL99
 1    For upgrading the steam and water distribution
 2      systems, in addition to funds previously
 3      appropriated .................................    2,341,716
 4    (From Article 94, Section 5 of Public Act 90-0010)
 5    For replacement of East and West
 6      Cellhouse windows and boilers ................       91,662
 7    For improving the south yard for outdoor
 8      recreation ...................................       32,606
 9    For repairs due to the Great Flood of
10      1993 and projects to protect the facility
11      from future floods ...........................       62,559
12    For upgrading the steam and water distribution
13      systems and replacement of the MSU
14      "C" Building .................................      146,107
15    For replacement of the chimney stack and
16      boilers, in addition to funds previously
17      appropriated .................................      107,664
18    For replacement of hot water heaters and
19      deairing tanks ...............................      110,000
20    For planning the renovation of the old
21      hospital building ............................      207,540
22    For renovation of elements of the power
23      plants, including the main generator .........       22,982
24    For planning for renovation of the
25      Administration Building ......................       15,604
26                     PONTIAC CORRECTIONAL CENTER
27    (From Article 94, Section 5A of Public Act 90-0010)
28    For renovation of main sally port ..............      300,000
29    (From Article 94, Section 5 of Public Act 90-0010)
30                     SHAWNEE CORRECTIONAL CENTER
31    For upgrading the heating and hot
32      water system .................................      498,563
33               STATEVILLE CORRECTIONAL CENTER - JOLIET
34    (From Article 94, Section 5A of Public Act 90-0010)
                            -45-                BOB-CAPITAL99
 1    For replacement of the MSU .....................    6,500,000
 2    (From Article 94, Section 5 of Public Act 90-0010)
 3    For upgrading the doors, locks and hardware
 4      in B Cellhouse ...............................       58,700
 5    For upgrading the water supply to B house  .....      187,633
 6             SOUTHWESTERN ILLINOIS CORRECTIONAL FACILITY
 7    For providing equipment and telecomm,
 8      constructing a warehouse and upgrading
 9      a parking lot, in addition to funds
10      previously appropriated ......................       27,876
11    For completing the conversion of existing
12      buildings into a minimum security
13      correctional facility, in addition to
14      funds previously appropriated ................       15,001
15                    VANDALIA CORRECTIONAL CENTER
16    (From Article 94, Section 5A of Public Act 90-0010)
17    For renovation of dormitory shower rooms .......      450,000
18                     VIENNA CORRECTIONAL CENTER
19    (From Article 93, Section 3 of Public Act 90-0010)
20    For renovating the kitchen .....................    2,000,000
21    (From Article 94, Section 5A of Public Act 90-0010)
22    For upgrading the steam distribution system
23      and renovation of Powerhouse, in addition
24      to funds previously appropriated .............    3,979,634
25    For installation of security fencing ...........      959,796
26    For upgrading air conditioning system
27      and replacement of cooling tower .............    1,100,000
28    For upgrading the electrical, plumbing and
29      HVAC systems in four buildings ...............      850,000
30    (From Article 94, Section 5 of Public Act 90-0010)
31    For completing the rehabilitation of duct
32      systems and walls, in addition to funds
33      previously appropriated ......................      806,456
34    For planning the upgrade of the steam
                            -46-                BOB-CAPITAL99
 1      distribution system ..........................      190,881
 2    For planning the replacement of the
 3      absorption chiller and cooling tower .........       40,848
 4    For upgrading the water and sewer
 5      utilities ....................................      141,688
 6                              STATEWIDE
 7    (From Article 93, Section 3 of Public Act 90-0010)
 8    For replacing roofing systems at the
 9      following locations at the approximate
10      costs set forth below: .......................    2,100,000
11       Big Muddy Correctional Center, Ina
12        Two buildings ...................... 425,000
13       East Moline Correctional Center,
14        Three buildings .................... 500,000
15       Graham Correctional Center, Hillsboro
16        Seven buildings .................... 600,000
17       Sheridan Correctional Center, LaSalle
18        Three buildings .................... 410,000
19       Stateville Correctional Center, Joliet
20        One building ....................... 165,000
21    For replacing doors and locks at the
22      following locations at the approximate
23      costs set forth below: .......................    2,575,000
24       IYC - St. Charles ................... 585,000
25       Lincoln Correctional Center .......... 50,000
26       Jacksonville Correctional Center .... 975,000
27       Sheridan Correctional Center ........ 965,000
28    For upgrading fire safety systems at the
29      following locations at the approximate
30      costs set forth below, in addition to
31      funds previously appropriated: ...............    6,500,000
32       Menard Correctional Center ........ 2,000,000
33       Pontiac Correctional Center ....... 3,000,000
34       Stateville Correctional Center .... 1,500,000
                            -47-                BOB-CAPITAL99
 1    For upgrading water and wastewater
 2      systems at the following locations
 3      at the approximate costs set forth below: ....    4,465,000
 4       Big Muddy Correctional Center
 5        for installing mechanical
 6        bar screen ......................... 300,000
 7       Centralia Correctional Center
 8        for upgrading water
 9        treatment plant .................. 1,500,000
10       East Moline Correctional Center
11        for upgrading sewer system ......... 655,000
12       Ed Jenison Work Camp (Paris)
13        for installing mechanical
14        bar screen ......................... 120,000
15       IYC - Harrisburg for upgrading
16        water distribution system .......... 500,000
17       Kankakee MSU for constructing
18        well #2 ............................ 300,000
19       IYC - St. Charles for upgrading
20        sewage/storm system ................ 850,000
21       IYC - Valley View for installing
22        mechanical bar screen .............. 240,000
23    (From Article 94, Section 5A of Public Act 90-0010)
24    For correction of deficiencies in
25      water systems at three correctional
26      facilities ...................................      100,000
27    For replacement of locks, windows and
28      doors at the following locations
29      as set forth below: ..........................    3,951,402
30       Dwight .............................. 291,400
31       IYC Harrisburg ...................... 291,400
32       IYC Joliet .......................... 367,500
33       Menard ............................ 1,350,000
34       Pontiac ............................. 680,102
                            -48-                BOB-CAPITAL99
 1       IYC Valley View ..................... 500,000
 2       Vienna .............................. 471,000
 3    For planning, design, construction,
 4      equipment and other necessary costs
 5      for a Correctional Facility for
 6      juveniles ....................................   42,750,000
 7    For planning, design, construction,
 8      equipment and other necessary costs
 9      for a Medium Security Correctional
10      Facility .....................................   68,574,985
11    (From Article 94, Section 5 of Public Act 90-0010)
12    For planning, design, construction,
13      equipment and all other necessary
14      costs for a youth boot camp at a
15      site to be chosen from the list of
16      finalists not selected for the
17      super maximum security prison  ...............       27,649
18    For completion of planning, site improvements,
19      utility upgrade, equipment and construction
20      of three housing units to add 672 cells
21      to the adult correctional system .............       22,310
22    For planning, construction, utilities, site
23      improvements, equipment and other expenses
24      necessary for the construction of a close
25      supervision super maximum security prison ....    3,246,135
26    For upgrading for fire safety at five
27      locations and replacing boilers...............      418,088
28    For correcting defects in the food preparation
29      areas, including roofs .......................      128,591
30    For planning, construction, utilities,
31      site improvements, and other expenses
32      necessary for the construction of two
33      minimum and one medium security
34      prisons ......................................       29,224
                            -49-                BOB-CAPITAL99
 1    For renovation and improvements at various
 2      correctional facilities at the approximate
 3      costs set forth below: .......................      117,693
 4       Roof Replacement ......................70,000
 5       Road Repavement .......................47,693
 6    For replacement of cell doors and locks
 7      and rehabilitation of locking systems at
 8      the following locations at the approximate
 9      costs set forth below: .......................      118,902
10       Kankakee MSU
11        For rehabilitation of locking
12        systems .............................118,902
13    For renovation of roads and parking lots
14      and replacement of boilers at the
15      following locations at the approximate
16      costs set forth below ........................      107,551
17       Dixon Correctional Center
18        For roads and parking .................6,000
19       Logan Correctional Center
20        For roads and parking .................5,656
21       Menard Correctional Center
22        For roads and parking and
23         replacement of boilers...............87,695
24       Vienna Correctional Center
25        For roads .............................8,200
26    For replacement of roofs at various Department of
27      Corrections locations ........................      269,592
28    For roof replacement at the following
29      locations at the approximate costs
30      set forth below: .............................      578,422
31       Dixon Correctional Center
32        Five Buildings .......................25,000
33       Dwight Correctional Center
34        Three buildings ......................10,425
                            -50-                BOB-CAPITAL99
 1       Graham Correctional Center
 2        Five buildings ........................6,268
 3       Graham Correctional Center
 4        Thirty-two buildings .................14,512
 5       Hanna City Work Camp
 6        Thirteen  buildings ...................2,500
 7       Joliet Correctional Center
 8        Five buildings .......................14,512
 9       Logan Correctional Center
10        Two buildings .........................9,920
11       Menard Psychiatric Center
12        Six buildings ........................33,624
13       Menard Correctional Center
14        Warehouse Building ...................55,093
15       Menard Correctional Center
16        Five buildings ......................269,508
17       Pontiac Correctional Center
18        Nine buildings .......................23,222
19       Pontiac Correctional Center
20        Eight buildings ......................10,686
21       Illinois Youth Center-St. Charles
22        Three buildings .......................3,580
23       Sheridan Correctional Center
24        Six buildings ........................15,482
25       Stateville Correctional Center
26        Seven buildings ......................38,000
27       Ill Youth Center-Valley View
28        Administration Building and
29         Kitchen Addition ....................23,954
30       Illinois Youth Center-Warrenville
31        One residential building .............22,136 ____________
32        Total, Section 5                             $317,961,627
33        Section  5.1.  The  following  named  amounts, or so much
                            -51-                BOB-CAPITAL99
 1    thereof as may be necessary  and  remain  unexpended  at  the
 2    close  of  business on June 30, 1998, from appropriations and
 3    reappropriations heretofore made for such purposes in Article
 4    93, Section 3A of Public Act 90-0010, and Article 94, Section
 5    5.1 of  Public  Act  90-0010,  are  reappropriated  from  the
 6    General Revenue Fund to the Capital Development Board for the
 7    Department   of  Corrections  for  the  projects  hereinafter
 8    enumerated:
 9                      DIXON CORRECTIONAL CENTER
10    (From Article 94, Section 5.1 of Public Act 90-0010)
11    For replacement of two freezer compressors
12      and motors ................................... $     24,579
13                   EAST MOLINE CORRECTIONAL CENTER
14    For retubing boiler #3 .........................      132,683
15                MENARD CORRECTIONAL CENTER - CHESTER
16    (From Article 93, Section 3A of Public Act 90-0010)
17    For stabilizing dams ...........................      100,000
18    For repairing masonry and
19      waterproofing exterior .......................      245,000
20               STATEVILLE CORRECTIONAL CENTER - JOLIET
21    For tuckpointing buildings .....................      200,000
22                    VANDALIA CORRECTIONAL CENTER
23    (From Article 93, Section 3A of Public Act 90-0010)
24    For tuckpointing, waterproofing and
25      replacing facade .............................      165,000
26                              STATEWIDE
27    (From Article 94, Section 5.1 of Public Act 90-0010)
28    For energy conservation improvements at the
29      following locations at the approximate
30      costs set forth below: .......................       56,018
31       Dwight Correctional Center ............ 7,000
32       Joliet Correctional Center
33        School Building ...................... 4,500
34       Menard Psychiatric Center
                            -52-                BOB-CAPITAL99
 1        Randolph Hall ........................ 7,500
 2       Stateville Correctional Center
 3        Law Library .......................... 7,400
 4       Pontiac Correctional Center .......... 27,893
 5       Vienna Correctional Center ............ 1,725
 6    For upgrading doors and locking systems at
 7      the following locations at the approximate
 8      costs set forth below: .......................      577,182
 9       Illinois Youth Center-Warrenville
10        For replacement of doors
11         and locking systems ............... 577,182 ____________
12        Total, Section 5.1                             $1,500,462
13        Section 5.2.  The sum of $2,666,667, or so  much  thereof
14    as  may  be  necessary and remains unexpended at the close of
15    business on June 30, 1998, from a reappropriation  heretofore
16    made  for  such purposes in Article 94, Section 5.2 of Public
17    Act 90-0010, is reappropriated from the  Capital  Development
18    Fund  to  the  Capital  Development  Board  for  the  State's
19    one-third   share   of   land   acquisition,   equipment  and
20    construction of a boot camp in the Cook County area.
21        Section 5.3.  The amount of $21,874, or so  much  thereof
22    as  may  be  necessary and remains unexpended at the close of
23    business on June 30, 1998, from a reappropriation  heretofore
24    made  for  such purposes in Article 94, Section 5.3 of Public
25    Act 90-0010, is reappropriated from the  Capital  Development
26    Fund  to  the Capital Development Board for the Department of
27    Corrections for planning and other expenses necessary  for  a
28    medical unit facility at Dwight Correctional Center.
29        Section  5.4.  The  amount  of  $2,876,193,  or  so  much
30    thereof  as  may be necessary and remains unexpended from the
31    General Revenue Fund at the close of  business  on  June  30,
                            -53-                BOB-CAPITAL99
 1    1998,   from  a  reappropriation  heretofore  made  for  such
 2    purposes in Article 94, Section 5.4 of Public Act 90-0010, is
 3    reappropriated to  the  Capital  Development  Board  for  the
 4    Department  of  Corrections for all costs associated with the
 5    completion of the super maximum  security  prison  at  Tamms,
 6    Illinois.
 7        Section  5.5.  The  amount  of  $6,108,093,  or  so  much
 8    thereof  as  may  be  necessary and remains unexpended at the
 9    close of business on June 30, 1998,  from  a  reappropriation
10    heretofore  made for such purposes in Article 94, Section 5.5
11    of Public Act 90-0010, is  reappropriated  from  the  General
12    Revenue  Fund  to  the  Capital  Development  Board  for  the
13    Department   of  Corrections  for  the  projects  hereinafter
14    enumerated at the approximate costs set forth below:
15    Danville Correctional Center -
16    For upgrading the hot water
17      distribution system ..................$514,393
18    Joliet Correctional Center -
19    For replacement of the deep well ........270,046
20    Stateville Correctional Center-
21    For upgrading the plumbing systems in
22      four buildings ......................3,790,252
23    Menard Correctional Center -
24    For planning and to begin upgrading
25      the plumbing systems in two
26      buildings .............................144,440
27    Pontiac Correctional Center -
28    For upgrading the mechanical systems
29      and renovation of shower rooms ........339,166
30    Shawnee Correctional Center -
31    For upgrading the hot water
32      distribution system .................1,049,796
                            -54-                BOB-CAPITAL99
 1        Section 5.6.  The following named  amounts,  or  so  much
 2    thereof  as  may  be  necessary  and remain unexpended at the
 3    close of business  on  June  30,  1998,  from  appropriations
 4    heretofore  made for such purposes in Article 94, Section 5.6
 5    of Public Act 90-0010, are reappropriated  from  the  General
 6    Revenue  Fund  to  the  Capital  Development  Board  for  the
 7    Department   of  Corrections  for  the  projects  hereinafter
 8    enumerated:
 9                      DIXON CORRECTIONAL CENTER
10    For tuckpointing two buildings ................. $     65,000
11               STATEVILLE CORRECTIONAL CENTER - JOLIET
12    For tuckpointing seven buildings ...............      268,592
13        Total                                            $333,592
14        Section 6.  The  following  named  amounts,  or  so  much
15    thereof  as  may  be  necessary and remains unexpended at the
16    close of business on June 30, 1998, from  appropriations  and
17    reappropriations heretofore made for such purposes in Section
18    55 of Public Act 90-0550; Article 93, Section 4 of Public Act
19    90-0010;  and  Article  94,  Sections  6 and 6A of Public Act
20    90-0010 are reappropriated from the Capital Development  Fund
21    to   the   Capital   Development   Board   for  the  Historic
22    Preservation Agency for the projects hereinafter enumerated:
23    (From Article 94, Section 6A of Public Act 90-0010)
24             CAHOKIA COURTHOUSE STATE MEMORIAL - CAHOKIA
25    For renovation of the Cahokia Courthouse
26      and the Jarrot House ......................... $    387,000
27             CAHOKIA MOUNDS HISTORIC SITE - COLLINSVILLE
28    For replacement of Monk's Mounds stairs ........      465,000
29    For restoration of Monk's Mound ................    1,380,220
30    (From Article 94, Section 6 of Public Act 90-0010)
31    To extend a water line for providing
32      reliable water service .......................      145,288
33    For purchasing private land within historic
                            -55-                BOB-CAPITAL99
 1      site boundary ................................      210,245
 2    For replacement of Monk's Mounds stairs ........      207,252
 3                  DAVID DAVIS MANSION - BLOOMINGTON
 4    (From Article 94, Section 6A of Public Act 90-0010)
 5    For renovation of the David Davis Mansion
 6      to eliminate basement leakage ................      231,000
 7                          DAVID DAVIS HOME
 8    (From Article 94, Section 6 of Public Act 90-0010)
 9    To acquire a residence to be
10      converted to a Visitors Center ...............      250,000
11    (From Section 55 of Public Act 90-0550)
12                 FORT DE CHARTRES - RANDOLPH COUNTY
13    For replacing Maintenance Building .............      264,000
14                     FT. KASKASKIA HISTORIC SITE
15    (From Article 94, Section 6 of Public Act 90-0010)
16    For providing a new water supply ...............      138,463
17                 LEWIS AND CLARK STATE HISTORIC SITE
18    For the construction of an interpretive
19      center .......................................      440,000
20             LINCOLN LOG CABIN HISTORIC SITE - CAMPBELL
21    (From Article 94, Section 6A of Public Act 90-0010)
22    For construction of a visitors center ..........    1,373,611
23    For replacement of bridges .....................      180,000
24    (From Article 94, Section 6 of Public Act 90-0010)
25    For rehabilitation of historic structures ......       16,424
26    For construction of a visitor center and
27      museum, Phase I ..............................       90,783
28            LINCOLN NEW SALEM HISTORIC SITE - PETERSBURG
29    (From Article 94, Section 6A of Public Act 90-0010)
30    For renovation of the River Ridge
31      Restaurant and improvements to the
32      domestic water system ........................      248,726
33    (From Article 94, Section 6 of Public Act 90-0010)
34    For rehabilitation of the sewage treatment
                            -56-                BOB-CAPITAL99
 1      plant ........................................       92,450
 2               PULLMAN FACTORY HISTORIC SITE - CHICAGO
 3    For stabilization of the structure and for planning
 4      and beginning restoration ....................      793,764
 5                   OLD STATE CAPITOL - SPRINGFIELD
 6    (From Article 93, Section 4 of Public Act 90-0010)
 7    For renovating garage ramp .....................      419,000
 8    (From Article 94, Section 6A of Public Act 90-0010)
 9    For renovation of the Old State
10      Capitol to eliminate basement
11      leakage ......................................      598,626
12    (From Article 94, Section 6 of Public Act 90-0010)
13                         VACHEL LINDSAY HOME
14    For mechanical/system replacement,
15      restoration of the foundation and other
16      structural improvements ......................       22,340
17                        VANDALIA STATE HOUSE
18    (From Section 55 of Public Act 90-0550)
19    For rehabilitating HVAC and electrical
20      systems and interior .........................      378,000
21                              STATEWIDE
22    (From Article 93, Section 4 of Public Act 90-0010)
23    For replacing roofing systems at the
24      following locations at the approximate
25      costs set forth below: .......................      462,000
26       Fort De Chartres, Randolph County .... 93,000
27       Washburne House, Galena .............. 50,000
28       David Davis Mansion, Bloomington ..... 25,000
29       Bishop Hill House, Henry County ..... 294,000
30    (From Article 94, Section 6A of Public Act 90-0010)
31    For matching ISTEA federal grant funds .........      500,000
32    (From Article 94, Section 6 of Public Act 90-0010)
33    For land acquisition and related costs .........       19,411
34        Total, Section 6                               $9,313,603
                            -57-                BOB-CAPITAL99
 1        Section 6.1.  The amount of $54,510, or so  much  thereof
 2    as  may  be  necessary and remains unexpended at the close of
 3    business on June 30, 1998, from a reappropriation  heretofore
 4    made  for  such  purpose in Article 94, Section 6.1 of Public
 5    Act 90-0010, is reappropriated from the  Capital  Development
 6    Fund  to  the  Capital  Development  Board  for  the Historic
 7    Preservation Agency for the purchase  and  rehabilitation  of
 8    the State Journal Register Building in Springfield.
 9        Section  6.2.  The  amount of $52,326, or so much thereof
10    as may be necessary and remains unexpended at  the  close  of
11    business  on June 30, 1998, from a reappropriation heretofore
12    made for such purpose in Article 94, Section  6.2  of  Public
13    Act  90-0010,  is reappropriated from the Capital Development
14    Fund to  the  Capital  Development  Board  for  the  Historic
15    Preservation    Agency    for    acquiring    the   Zimmerman
16    archaeological site in  LaSalle  County  and  for  associated
17    costs,  planning,  stabilization,  restoration  and all other
18    expenses  necessary  to  comply  with  the  intent  of   this
19    appropriation.
20        Section  6.3.  The  amount  of  $2,300,000,  or  so  much
21    thereof  as  may  be  necessary and remains unexpended at the
22    close of business on June 30, 1998,  from  a  reappropriation
23    heretofore  made for such purposes in Article 94, Section 6.3
24    of Public Act 90-0010, is  reappropriated  from  the  Capital
25    Development   Fund  to  the  Capital  Development  Board  for
26    planning a new historical library and Lincoln Center.
27        Section 6.4.  The amount of $400,000, or so much  thereof
28    as  may  be necessary and remains unexpended from the General
29    Revenue Fund, from the reappropriations heretofore  made  for
30    such  purposes  in  Article  94,  Section  6.4  of Public Act
31    90-0010,  is  reappropriated  to  the  Historic  Preservation
                            -58-                BOB-CAPITAL99
 1    Agency (formerly to Capital Development  Board  for  Historic
 2    Preservation  Agency)  for  planning a new historical library
 3    and Lincoln Center.
 4        Section 6.5.  The following named  amounts,  or  so  much
 5    thereof  as  may  be  necessary  and remain unexpended at the
 6    close of business  on  June  30,  1998,  from  appropriations
 7    heretofore  made  for such purposes in Article 93, Section 4A
 8    of Public Act 90-0010, are reappropriated  from  the  General
 9    Revenue  Fund  to  the  Capital  Development  Board  for  the
10    Historic  Preservation  Agency  for  the projects hereinafter
11    enumerated:
12               JOURNAL REGISTER BUILDING - SPRINGFIELD
13    For renovating building ........................ $    702,000
14                   DANA THOMAS HOUSE - SPRINGFIELD
15    For restoring the exterior and interior ........      417,000
16        Total, Section 6.5                             $1,119,000
17        Section 7.  The sum of $103,997, or so  much  thereof  as
18    may  be  necessary  and  remains  unexpended  at the close of
19    business on June 30, 1998, from a reappropriation  heretofore
20    made for such purposes in Article 94, Section 8 of Public Act
21    90-0010,  is reappropriated from the Capital Development Fund
22    to the Capital Development Board for  the  Legislative  Space
23    Needs    Commission   for   architectural/engineering   fees,
24    planning, construction, reconstruction,  rehabilitation,  and
25    all  other  necessary  costs for remodeling and relocation of
26    various legislative services agencies located in the  Capitol
27    and  Stratton  Office  buildings at the approximate costs set
28    forth below:
29        For the Joint Committee on
30          Administrative Rules .......................$   103,997
31        Section 8.  The  following  named  amounts,  or  so  much
                            -59-                BOB-CAPITAL99
 1    thereof  as  may  be  necessary  and remain unexpended at the
 2    close of business on June 30, 1997, from  appropriations  and
 3    reappropriations heretofore made for such purposes in Section
 4    56 of Public Act 90-0550; Article 93, Section 5 of Public Act
 5    90-0010;  and  Article  94,  Sections  9 and 9A of Public Act
 6    90-0010, are reappropriated from the Capital Development Fund
 7    to the Capital Development Board for the Department of  Human
 8    Services  (formerly  the  Department  of  Mental  Health  and
 9    Developmental  Disabilities)  for  the  projects  hereinafter
10    enumerated:
11             ALTON MENTAL HEALTH CENTER - MADISON COUNTY
12    (From Section 56 of Public Act 90-0550)
13    For constructing two building additions
14      at the Forensic Complex ......................   11,924,000
15    (From Article 94, Section 9A of Public Act 90-0010)
16    For rehabilitation of the central dietary ......    1,950,000
17    For replacement of life/safety and
18      security system in a residential
19      building .....................................      234,550
20    (From Article 94, Section 9 of Public Act 90-0010)
21    For replacement of domestic hot water
22      lines in seven buildings .....................        4,859
23    For upgrading fire safety systems in
24      eight buildings   ............................        5,708
25    For replacement of the chiller and
26      connection of the HVAC to the energy
27      management system ............................       14,911
28    For replacement of two cooling towers in
29      the Willow Building ..........................       35,169
30               CHESTER MENTAL HEALTH CENTER - CHESTER
31    (From Article 93, Section 5 of Public Act 90-0010)
32    For replacing fencing and upgrading
33      recreational yard ............................    1,400,000
34    For renovating support and residential
                            -60-                BOB-CAPITAL99
 1      area .........................................    3,910,000
 2    (From Article 94, Section 9A of Public Act 90-0010)
 3    For installation of emergency generator
 4      and upgrading EMS system .....................      350,000
 5    (From Article 94, Section 9 of Public Act 90-0010)
 6    For construction of a storage building  ........       76,610
 7    For construction of a Rehabilitative
 8      Services building ............................       54,775
 9    For replacement of the emergency generator .....       61,354
10                          CHICAGO METRO C&A
11    For planning and renovation of residential
12      and program units for children and
13      adolescent services ..........................      794,770
14             CHICAGO READ MENTAL HEALTH CENTER - CHICAGO
15    (From Article 94, Section 9A of Public Act 90-0010)
16    For renovating residential units, in
17      addition to funds previously
18      appropriated .................................    2,171,000
19    (From Article 94, Section 9 of Public Act 90-0010)
20    For renovation of utility rooms and installation
21      of drinking fountains ........................      218,000
22    For renovation of the West Campus Nurses'
23      Stations .....................................      619,788
24    For renovation of Henry Horner Children's
25      Center and West Campus for fire and
26      life safety codes ............................    1,365,057
27    For renovation of the West Campus shower
28      and toilet rooms .............................      385,908
29    For rehabilitation of the bathroom shower
30      walls in ten buildings .......................       58,147
31        CHOATE MENTAL HEALTH AND DEVELOPMENTAL CENTER - ANNA
32    (From Article 93, Section 5 of Public Act 90-0010)
33    For completing HVAC system upgrade,
34      in addition to funds previously
                            -61-                BOB-CAPITAL99
 1      appropriated .................................    1,433,000
 2    (From Article 94, Section 9A of Public Act 90-0010)
 3    For upgrading the mechanical equipment,
 4      in addition to funds previously
 5      appropriated .................................      837,000
 6    For renovating a residential building,
 7      in addition to funds previously
 8      appropriated .................................    2,334,000
 9    (From Article 94, Section 9 of Public Act 90-0010)
10    For upgrading the mechanical equipment,
11      in addition to funds previously
12      appropriated .................................      367,430
13    For planning and beginning the renovation of a
14      residential building .........................       70,714
15    For renovation of the kitchen and residential
16      units for rethermalization and air
17      condition the kitchen, in addition to
18      funds previously appropriated  ...............       17,051
19    For separating and upgrading of the combined
20      sewer system, in addition to funds
21      previously appropriated ......................      154,660
22    For rehabilitation of resident buildings
23      and upgrading of temperature controls ........       81,260
24              ELGIN MENTAL HEALTH CENTER - KANE COUNTY
25    (From Article 93, Section 5 of Public Act 90-0010):
26    For renovating the central dietary
27      and kitchen ..................................    3,994,000
28    (From Article 94, Section 9A of Public Act 90-0010)
29    For construction of an Adult Psychiatric
30      Building, in addition to funds previously
31      appropriated .................................    3,681,000
32    For construction of roads, parking lots
33      and street lights ............................    2,500,000
34    For upgrading and expanding the mechanical
                            -62-                BOB-CAPITAL99
 1      infrastructure, in addition to funds
 2      previously appropriated ......................    4,005,100
 3    For construction of a forensic services complex
 4      at Elgin Mental Health Center, in addition
 5      to funds previously appropriated .............    4,815,500
 6    (From Article 94, Section 9 of Public Act 90-0010)
 7    For construction of a forensic services
 8      complex, in addition to funds previously
 9      appropriated .................................    1,784,500
10    For upgrading and expanding the mechanical
11      infrastructure, in addition to funds
12      previously appropriated ......................      105,305
13    For renovation of the HVAC systems,
14      replacement of windows and installation
15      of security screens, in addition
16      to funds previously appropriated .............    2,092,543
17    For construction of a Forensic Services
18      Facility, in addition to funds
19      previously appropriated  .....................    2,787,866
20    For upgrading and expanding mechanical
21      infrastructure, in addition to funds
22      previously appropriated ......................      142,140
23    For upgrading for fire and life safety .........      880,849
24    For planning the renovation of the Forensic
25      Building and abating asbestos ................      251,946
26    For renovation of the Central Stores
27      Building .....................................       85,679
28    For upgrading the security systems and
29      constructing a multi-purpose building
30      for the Forensic Complex .....................       64,550
31    For the demolition of the Old Main Building
32      and construction of an Adult
33      Psychiatric Center ...........................      836,748
34                      FOX DEVELOPMENTAL CENTER
                            -63-                BOB-CAPITAL99
 1    (From Article 94, Section 9A of Public Act 90-0010)
 2    For replacement of absorbers and
 3      upgrading HVAC system ........................      738,000
 4    For renovation of dietary ......................      826,400
 5    (From Article 94, Section 9 of Public Act 90-0010)
 6    For renovation of Building #8 and
 7      window replacement of Building
 8      #1, in addition to funds
 9      previously appropriated ......................      323,575
10               HOWE DEVELOPMENTAL CENTER - TINLEY PARK
11    (From Article 94, Section 9A of Public Act 90-0010)
12    For renovation of residential buildings ........    2,557,600
13    (From Article 94, Section 9 of Public Act 90-0010)
14    For replacement of steam and
15      condensate lines .............................      113,418
16    For renovation of the boilers in the power
17      plant ........................................       29,856
18          JACKSONVILLE DEVELOPMENTAL CENTER - MORGAN COUNTY
19    (From Article 93, Section 5 of Public Act 90-0010)
20    For extending chilled water line ...............      327,000
21    (From Article 94, Section 9A of Public Act 90-0010)
22    For rehabilitation of bathrooms and
23      replacing doors ..............................    1,286,023
24    For rehabilitation of the electrical
25      distributions system, in addition to
26      Funds previously appropriated ................    1,257,000
27    (From Article 94, Section 9 of Public Act 90-0010)
28    For replacement of code compliance
29      generators ...................................        8,833
30    For planning and beginning electrical
31      distribution renovation ......................       21,950
32    For replacement of piping and heating units ....       56,809
33    For rehabilitation of bathrooms and replacement
34      of doors .....................................       75,048
                            -64-                BOB-CAPITAL99
 1    For installation of fire safety systems in
 2      four buildings and replacement of a
 3      code compliance generator ....................      235,941
 4                KILEY DEVELOPMENTAL CENTER - WAUKEGAN
 5    (From Article 93, Section 5 of Public Act 90-0010)
 6    For renovating homes ...........................      741,000
 7    (From Article 94, Section 9 of Public Act 90-0010)
 8    For renovation of homes ........................       79,434
 9             LINCOLN DEVELOPMENTAL CENTER - LOGAN COUNTY
10    (From Article 94, Section 9A of Public Act 90-0010)
11    For installation of a rethermalization food
12      service system, in addition to funds
13      previously appropriated ......................      732,000
14    (From Article 94, Section 9 of Public Act 90-0010)
15    For upgrading the architectural and mechanical
16      systems, in addition to funds
17      previously appropriated ......................    1,339,313
18    For installation of a code compliance
19      generator ....................................       99,238
20    For rehabilitation of the coal bunker
21      in the Powerhouse ............................       33,640
22    For installation of rethermalization food
23      service system ...............................       83,274
24    For expansion of the sprinkler system in
25      four buildings ...............................      185,080
26    For renovation of the boilers, replacement of
27      controls and tuckpointing the exterior .......      106,984
28    For installation of air conditioning in
29      Coty and Dietary Buildings ...................       44,883
30    For upgrading the HVAC systems, including
31      chillers .....................................       25,157
32             LUDEMAN DEVELOPMENTAL CENTER - PARK FOREST
33    (From Article 94, Section 9A of Public Act 90-0010)
34    For renovation of residential buildings,
                            -65-                BOB-CAPITAL99
 1      in addition to funds previously
 2      appropriated .................................    1,888,500
 3    For rehabilitation of the roads and parking
 4      areas and constructing walks .................      800,000
 5    (From Article 94, Section 9 of Public Act 90-0010)
 6    For renovation of residences ...................      460,189
 7    For renovation of residences ...................      156,005
 8    For renovation of restrooms for accessibility
 9      in two buildings .............................       19,460
10    For renovation of bathrooms in 15 residences ...       94,368
11                 MADDEN MENTAL HEALTH CENTER - HINES
12    (From Article 93, Section 5 of Public Act 90-0010)
13    For renovating dietary .........................      930,000
14    (From Article 94, Section 9A of Public Act 90-0010)
15    For renovation of pavilions, in addition
16      to funds previously appropriated .............      844,000
17    (From Article 94, Section 9 of Public Act 90-0010)
18    For renovation of pavilions ....................      347,956
19    For upgrading residences for safety and
20      security .....................................      279,521
21    For replacement of a cooling tower and
22      chiller ......................................      225,987
23    For replacement of hot water heaters ...........       86,160
24            MCFARLAND MENTAL HEALTH CENTER - SPRINGFIELD
25    (From Article 94, Section 9A of Public Act 90-0010)
26    For replacement of the HVAC management
27      control panel, in addition to funds
28      previously appropriated ......................      150,000
29    For rehabilitation of the dietary facility .....      398,120
30    (From Article 94, Section 9 of Public Act 90-0010)
31    For renovation of a residential building .......       49,591
32    For replacement of the HVAC control panel ......       86,105
33               MURRAY DEVELOPMENTAL CENTER - CENTRALIA
34    (From Article 93, Section 5 of Public Act 90-0010)
                            -66-                BOB-CAPITAL99
 1    For rehabilitating the emergency
 2      electrical system ............................      314,000
 3    For renovating Elm Cottage .....................    3,082,000
 4    (From Article 94, Section 9A of Public Act 90-0010)
 5    For replacement of the boiler
 6      shells and controls, in addition
 7      to funds previously appropriated .............       85,067
 8    For rehabilitation of the hot water
 9      distribution system, in addition to
10      funds previously appropriated ................      189,713
11    For replacement of cooling towers and
12      support beams, in addition to funds
13      previously appropriated ......................      228,082
14    (From Article 94, Section 9 of Public Act 90-0010)
15    For installation of fire safety systems ........      582,763
16    For replacement of the boiler shell and
17      controls .....................................        5,747
18    For rehabilitation of the hot water
19      distribution system ..........................       30,968
20               SHAPIRO DEVELOPMENTAL CENTER - KANKAKEE
21    (From Article 93, Section 5 of Public Act 90-0010)
22    For replacing cooling towers and
23      rehabilitating absorbers .....................    1,040,000
24    (From Article 94, Section 9A of Public Act 90-0010)
25    For completion of the HVAC system, in
26      addition to funds previously
27      appropriated .................................      598,000
28    For replacement of boiler, in
29      addition to funds previously
30      appropriated .................................      765,000
31    For replacement of electrical feeder
32      cable, in addition to the funds
33      previously appropriated ......................      586,000
34    For rehabilitation of sewers and
                            -67-                BOB-CAPITAL99
 1      manholes, in addition to funds
 2      previously appropriated ......................      756,707
 3    For replacement of water mains
 4      and valves ...................................    1,826,000
 5    (From Article 94, Section 9 of Public Act 90-0010)
 6    For replacement of valves in the powerhouse ....        9,451
 7    For replacement of electrical feeder cable .....      102,461
 8    For planning and beginning sewer and
 9      manhole renovation ...........................       53,183
10    For rehabilitation of the boilers ..............      231,521
11    For planning and replacement of windows ........      234,721
12    For installation of an emergency generator .....      115,703
13    For upgrading fire safety systems in the
14      support buildings ............................      169,663
15    For installation of air conditioning in
16      Building #704, in addition to funds
17      previously appropriated ......................      104,551
18    For replacement of hot water tanks in the
19      Laundry Building .............................       38,476
20    For replacement of cooling towers in
21      Buildings #100A and #100B ....................       97,836
22    For planning the installation of an air
23      conditioning system for Building #704 ........       45,376
24    For installation of air conditioning in
25      Buildings #502 and #514 ......................      167,543
26    For upgrading the electrical system ............       15,706
27               SINGER MENTAL HEALTH CENTER - ROCKFORD
28    (From Article 93, Section 5 of Public Act 90-0010)
29    For renovating mechanicals and
30      residential areas ............................    2,736,000
31    (From Article 94, Section 9A of Public Act 90-0010)
32    For replacement of absorbers ...................      711,769
33                  TINLEY PARK MENTAL HEALTH CENTER/
34                      HOWE DEVELOPMENTAL CENTER
                            -68-                BOB-CAPITAL99
 1    (From Article 94, Section 9A of Public Act 90-0010)
 2    For replacement of the bar screen and
 3      renovating the sewer system, in
 4      addition to funds previously appropriated ....      439,450
 5    For rehabilitation of the electrical
 6      distribution system, in addition to
 7      funds previously appropriated ................    2,250,000
 8    (From Article 94, Section 9 of Public Act 90-0010)
 9    For renovating and making mechanical
10      improvements to Spruce Hall and Maple Hall ...      169,802
11    For planning the rehabilitation of the
12      electrical distribution system ...............       30,132
13    For renovation for accessibility in four
14      buildings ....................................      175,591
15    For planning the sewer system renovation and
16      replacement of the rag catcher ...............      263,742
17    For renovation for fire and life safety in
18      three residences .............................      267,054
19    For renovation of nursing stations and
20      medication rooms in three residences .........       20,019
21    For replacement of the windows in nine
22      buildings ....................................       28,935
23                ZELLER MENTAL HEALTH CENTER - PEORIA
24    (From Article 94, Section 9A of Public Act 90-0010)
25    For renovation of the nurses' stations,
26      in addition to funds previously
27      appropriated .................................    1,720,000
28    (From Article 94, Section 9 of Public Act 90-0010)
29    For renovation of Nurses' Stations and
30      seclusion rooms ..............................      181,271
31    For replacement of the heating and cooling
32      pumps ........................................       10,803
33                              STATEWIDE
34    (From Article 93, Section 5 of Public Act 90-0010)
                            -69-                BOB-CAPITAL99
 1    For replacing roofing systems at the
 2      following locations at the approximate
 3      costs set forth below: .......................      392,000
 4       Elgin Mental Health Center,
 5         five buildings .....................256,000
 6       Jacksonville Mental Health and
 7         Developmental Center,
 8       two buildings.........................136,000
 9    (From Article 94, Section 9A of Public Act 90-0010)
10    For replacement of roofing systems at the
11      following locations at the approximate costs
12      set forth below: .............................    2,282,452
13        Alton Mental Health Center ..........216,400
14        Choate Mental Health Center .........134,900
15        Chester Mental Health Center ......1,320,000
16        Fox Developmental Center .............85,152
17        Howe Developmental Center ...........161,000
18        Jacksonville Developmental Center ....21,000
19        Lincoln Developmental Center ........344,000
20    (From Article 94, Section 9 of Public Act 90-0010)
21                      ALTON/ELGIN
22    For construction of a forensic services complex
23      at Alton Mental Health Center and Elgin
24      Mental Health Center, in addition to funds
25      previously appropriated ......................       37,216
26    For conducting the preliminary design to
27      construct, convert and/or rehabilitate
28      a forensic facility ..........................       94,918
29    For upgrading and rehabilitation of roads,
30      parking lots and drainage systems at the
31      following locations at the approximate
32      costs set forth below: .......................       59,885
33        Chester Mental Health Center
34          For rehabilitation of the
                            -70-                BOB-CAPITAL99
 1          drainage system and upgrading
 2          parking lots .......................59,885
 3    For upgrading roads and parking lots at
 4      the following locations at the
 5      approximate costs set forth below: ...........       38,106
 6        McFarland Mental Health Ctr ...........5,544
 7        Shapiro Developmental Center .........32,562
 8    For rehabilitation of water towers -
 9      Murray and Chester ...........................      403,532
10    For replacement of roofs at the following
11      locations at the approximate costs set
12      forth below: .................................    1,257,411
13        Alton Mental Health Center -
14          Five buildings .....................50,000
15        Choate Mental Health Center -
16          Three buildings ....................17,479
17        Choate Mental Health and
18          Developmental Center -
19          Five buildings .....................15,034
20        Chester Mental Health Center -
21          21 buildings .......................39,775
22        Elgin Mental Health Center -
23          Three buildings ....................52,000
24        Elgin Mental Health Center -
25          Six Buildings .....................115,000
26        Lincoln Developmental Center -
27          Three buildings ....................80,000
28        Lincoln Developmental Center -
29          Four buildings ......................6,601
30        Ludeman Developmental Center -
31          Support buildings ..................91,447
32        Ludeman Developmental Center-
33          Residences .........................22,158
34        Mabley Developmental Center -
                            -71-                BOB-CAPITAL99
 1          One building ......................103,517
 2        Madden Mental Health Center -
 3          Buildings and covered walkways .....72,822
 4        McFarland Mental Health Center -
 5          Three buildings .....................5,000
 6        Meyer Mental Health Center -
 7          One building ......................180,314
 8        Shapiro Developmental Center -
 9          Three buildings ...................187,000
10        Shapiro Developmental Center -
11          Two buildings ......................16,351
12        Shapiro Developmental Center -
13          Five buildings .....................67,831
14        Tinley Park Mental Health Center -
15          One building .......................26,048
16        Tinley Park Mental Health Center -
17          Oak Hall ..........................109,034
18                       STATEWIDE - FIRE SAFETY
19    To renovate fire safety systems, including
20      installation of sprinklers, at the following
21      locations at the approximate costs set
22      forth below: .................................      347,511
23        Anna Mental Health and
24          Developmental Center ...............12,490
25        Singer Mental Health and
26          Developmental Center ..............335,021
27    For fire safety and other work necessary to meet
28      state and federal certification standards for
29      the following projects:
30    For installation of sprinkler systems at
31      Chicago-Read Mental Health Center ............      122,117
32    For installation of sprinkler systems at
33      Murray Developmental Center ..................        2,000
34        Total, Section 8                             $102,618,819
                            -72-                BOB-CAPITAL99
 1        Section  8A.  The  following  named  amounts,  or so much
 2    thereof as may be necessary  and  remain  unexpended  at  the
 3    close  of  business on June 30, 1998, from appropriations and
 4    reappropriations  heretofore  made  for  such   purposes   in
 5    Article  93,  Section  5.1 of Public Act 90-0010, and Article
 6    94,  Sections  11  and  11A  of  Public  Act   90-0010,   are
 7    reappropriated  from  the  Capital  Development  Fund  to the
 8    Capital  Development  Board  for  the  Department  of   Human
 9    Services   (formerly   the   Department   of   Rehabilitation
10    Services) for the projects hereinafter enumerated:
11    (From Article 93, Section 5.1 of Public Act 90-0010)
12             ILLINOIS SCHOOL FOR THE DEAF -JACKSONVILLE
13    For completing the HVAC system upgrade,
14      in addition to funds previously
15      appropriated ................................. $    300,000
16    For replacing the storm and sanitary
17      system .......................................    2,000,000
18    For renovating Unit 5 ..........................      215,000
19    (From Article 94, Section 11A of Public Act 90-0010)
20    For replacement of roofing systems .............      510,471
21    For planning the upgrade of the heat
22      and smoke detection system ...................      100,000
23    For the renovation of Cullom Hall ..............    2,100,000
24    (From Article 94, Section 11 of Public Act 90-0010)
25    For construction of a Vocational Auto Body
26      and Service Facility .........................      119,018
27    For replacement of the HVAC system .............       73,151
28    For replacement of HVAC system in
29      Building #6 ..................................       78,386
30    For construction of an addition to Unit #5 .....      160,787
31    For rehabilitation of the domestic hot and
32      cold water piping in six buildings ...........      312,471
33    For replacement of domestic hot water tanks
34      in seven buildings ...........................       34,157
                            -73-                BOB-CAPITAL99
 1    (From Article 93, Section 5.1 of Public Act 90-0010)
 2       ILLINOIS SCHOOL FOR THE VISUALLY IMPAIRED -JACKSONVILLE
 3    For rehabilitating the power house .............      275,000
 4    (From Article 94, Section 11A of Public Act 90-0010)
 5    For upgrading campus lighting ..................      118,259
 6    For the replacement of Buildings
 7      #2, #3, and #4 ...............................      700,000
 8    (From Article 94, Section 11 of Public Act 90-0010)
 9    For completion of the boiler system
10      conversion, in addition to funds
11      previously appropriated ......................        5,315
12    For replacement of Buildings 5 and 6 for
13      an Independent Living Center .................    1,251,154
14        Total, Section 8A                              $8,353,169
15        Section 8.1.  The following named  amounts,  or  so  much
16    thereof  as  may  be  necessary  and remain unexpended at the
17    close of business on June 30, 1998, from  appropriations  and
18    reappropriations   heretofore   made  for  such  purposes  in
19    Article 93, Section 5a of Public Act 90-0010, and Article 94,
20    Section 9.1 of Public Act 90-0010,  are  reappropriated  from
21    the General Revenue Fund to the Capital Development Board for
22    the  Department of Human Services (formerly the Department of
23    Mental  Health  and  Developmental  Disabilities)   for   the
24    projects hereinafter enumerated:
25                     ALTON MENTAL HEALTH CENTER
26    (From Article 93, Section 5a of Public Act 90-0010)
27    For replacing windows in four buildings ........   $1,181,000
28                    CHESTER MENTAL HEALTH CENTER
29    For replacing backflow prevention
30      devices ......................................      160,000
31    (From Article 94, Section 9.1 of Public Act 90-0010)
32            CHOATE MENTAL HEALTH AND DEVELOPMENTAL CENTER
33    For renovation of turbines in the powerhouse ...       37,596
                            -74-                BOB-CAPITAL99
 1                     JACKSONVILLE MENTAL HEALTH
 2                      AND DEVELOPMENTAL CENTER
 3    (From Article 94, Section 9.1 of Public Act 90-0010)
 4    For the demolition of Carriel Hall,
 5      rerouting utility lines,
 6      providing parking lot, and planning
 7      the demolition of Building 41 ................      133,436
 8                    LINCOLN DEVELOPMENTAL CENTER
 9    (From Article 93, Section 5a of Public Act 90-0010)
10    For replacing windows ..........................      756,000
11               SHAPIRO DEVELOPMENTAL CENTER - KANKAKEE
12    For replacing windows in complex
13      buildings ....................................      486,000
14                  TINLEY PARK MENTAL HEALTH CENTER
15    (From Article 93, Section 5a of Public Act 90-0010)
16    For installing windows in residential
17      buildings ....................................      775,000
18    (From Article 94, Section 9.1 of Public Act 90-0010)
19    For repairing the exterior of Spruce Hall ......       56,350
20                ZELLER MENTAL HEALTH CENTER - PEORIA
21    (From Article 93, Section 5a of Public Act 90-0010)
22    For replacing windows ..........................    1,499,000
23                              STATEWIDE
24    (From Article 94, Section 9.1 of Public Act 90-0010)
25    For repair of the exterior masonry
26      walls, in addition to funds previously
27      appropriated .................................      519,704
28           TINLEY PARK MENTAL HEALTH CENTER - COOK COUNTY
29    For rehabilitating exterior of
30      residential building at Tinley ...............       43,495
31    For repair of the exterior masonry walls
32      at Fox, Shapiro and Tinley Park/Howe .........      138,521
33    For the following projects at the approximate
34      costs set forth below: .......................       28,433
                            -75-                BOB-CAPITAL99
 1        Elgin Mental Health Center
 2          For improvements to roads and
 3          parking areas ......................28,233
 4        Madden Mental Health Center
 5          For handicapped accessibility
 6          improvements in the
 7          Administration Building ...............200
 8                              STATEWIDE
 9    For road resurfacing and parking lots at
10      the following locations at the approximate
11      costs set forth below: .......................       27,891
12        Meyer Mental Health and
13          Developmental Center ...............27,891
14                       STATEWIDE - FIRE SAFETY
15    For renovation of fire safety systems at the
16      following locations at the approximate
17      costs set forth below: .......................      124,815
18        Chicago Read Mental Health Ctr .......65,294
19        Madden Mental Health Center ..........40,000
20        Murray Developmental Center ..........17,400
21        Singer Mental Health and
22          Developmental Center ..................200
23        Kiley Developmental Center ............1,921
24    For installation of smoke detection systems,
25      smoke compartmentation, and other fire
26      safety and certification improvements at
27      Murray Developmental Center ..................      324,774
28        Total, Section 8.1                             $6,292,015
29        Section  8A.1.  The  following  named amounts, or so much
30    thereof as may be necessary  and  remain  unexpended  at  the
31    close  of  business on June 30, 1998, from appropriations and
32    reappropriations heretofore made for such purposes in Article
33    93, Section 5a.1 of  Public  Act  90-0010,  and  Article  94,
                            -76-                BOB-CAPITAL99
 1    Section  11.1  of Public Act 90-0010, are reappropriated from
 2    the General Revenue Fund to the Capital Development Board for
 3    the Department of Human Services (formerly the Department  of
 4    Rehabilitation   Services)   for   the  projects  hereinafter
 5    enumerated:
 6             ILLINOIS SCHOOL FOR THE DEAF - JACKSONVILLE
 7    (From Article 93, Section 5a.1 of Public Act 90-0010)
 8    For installing an emergency generator .......... $    550,000
 9    For installing security systems in
10      three buildings ..............................       50,000
11    (From Article 94, Section 11.1 of Public Act 90-0010)
12    For renovation of buildings and lead
13      paint abatement ..............................      693,530
14                              STATEWIDE
15    For energy conservation improvements
16      for the Illinois School for the Deaf,
17      Jacksonville and the Illinois School
18      for the Visually Impaired, Jacksonville ......       37,113
19        Total Section 8A.1                             $1,330,643
20        Section 9.  The  following  named  amounts,  or  so  much
21    thereof  as  may  be  necessary  and remain unexpended at the
22    close of business on June 30, 1998, from  appropriations  and
23    reappropriations   heretofore   made  for  such  purposes  in
24    Section 57 of Public Act 90-0550, and Article 94, Sections 10
25    and 10A of Public Act 90-0010, are  reappropriated  from  the
26    Capital Development Fund to the Capital Development Board for
27    the   Department   of   Military  Affairs  for  the  projects
28    hereinafter enumerated:
29                            AURORA ARMORY
30    (From Article 94, Section 10 of Public Act 90-0010)
31    For planning an armory ......................... $     10,820
32                       BROADWAY AVENUE ARMORY
33    For replacement of the steam distribution
                            -77-                BOB-CAPITAL99
 1      system, including two boilers ................      154,256
 2                     CAMP LINCOLN - SPRINGFIELD
 3    For site improvements and construction for
 4      a military academy facility, including
 5      repair and reconstruction of access
 6      roads and drives at Camp Lincoln .............       24,062
 7    For planning, design, site improvements, and
 8      other costs associated with the conversion
 9      of the old "Castle" or Commissary Building
10      for use as a military museum .................      122,068
11                          CARBONDALE ARMORY
12    (From Section 57 of Public Act 90-0550)
13    For upgrading mechanical systems ...............    1,440,000
14                           DANVILLE ARMORY
15    (From Article 94, Section 10 of Public Act 90-0010)
16    For planning and construction of a new armory ..    1,070,000
17                           DECATUR ARMORY
18    For the state's share for additional planning
19      and construction of a new armory and
20      Organizational Maintenance Shop ..............       18,890
21                      DIXON ARMORY - LEE COUNTY
22    (From Article 94, Section 10A of Public Act 90-0010)
23    For construction of an addition,
24      remodeling, extending utilities and
25      installing a kitchen .........................      273,074
26    (From Article 94, Section 10 of Public Act 90-0010)
27    For rehabilitation of the parking lot,
28      including the drive and walks ................      128,007
29                         DONNELLEY BUILDING
30    For the rehabilitation and renovation of
31      the Donnelley Building and purchase of
32      land for parking .............................      356,259
33                        GENERAL JONES ARMORY
34    For renovation of the exterior and interior,
                            -78-                BOB-CAPITAL99
 1      mechanical areas and expansion of the
 2      parking lot, in addition to amounts
 3      previously appropriated ......................    1,826,412
 4    For renovation of the exterior, including
 5      windows ......................................       11,405
 6    For replacement of the Assembly Hall
 7      roofing system including its structural
 8      system .......................................      448,935
 9    For renovation of the armory, including
10      equipment, in addition to amounts
11      previously appropriated ......................       36,086
12    For renovation of the armory, including
13      equipment, in addition to amounts
14      previously appropriated for this purpose .....       11,276
15    For the state's share for renovation ...........       10,796
16                           KANKAKEE ARMORY
17    For providing the State's share for
18      construction of an Armory and Army
19      Reserve Center, including equipment ..........       14,752
20    For the state's share for planning an
21      armory and Army Reserve Center ...............        2,064
22                          LITCHFIELD ARMORY
23    For rehabilitation of exterior and upgrading
24      the interior .................................       60,022
25                  MACHESNEY PARK ARMORY (ROCKFORD)
26    For moveable equipment for the new armory ......       12,864
27    For the state's share for additional planning
28      and construction of an armory and
29      Organizational Maintenance Shop ..............      226,706
30                          MARSEILLES ARMORY
31    For planning four buildings and
32      wastewater facilities ........................        7,444
33                     NORTHWEST ARMORY - CHICAGO
34    (From Article 94, Section 10A of Public Act 90-0010)
                            -79-                BOB-CAPITAL99
 1    For renovation of interior and exterior,
 2      in addition to funds previously
 3      appropriated for such purposes ...............    1,200,000
 4    (From Article 94, Section 10 of Public Act 90-0010)
 5    For planning interior and exterior renovation ..        3,000
 6                            PARIS ARMORY
 7    For rehabilitation of the exterior and
 8      upgrading the interior .......................      393,000
 9                            PEORIA ARMORY
10    For providing the State's share for
11      construction of an armory and Army
12      Reserve Center, including equipment ..........        5,596
13                         ROCK ISLAND ARMORY
14    For construction of an armory and
15      maintenance shop .............................      158,346
16                    SALEM ARMORY - MARION COUNTY
17    (From Article 94, Section 10A of Public Act 90-0010)
18    For replacement of the boiler and
19      all domestic plumbing, piping and
20      fixtures .....................................      764,379
21    (From Article 94, Section 10 of Public Act 90-0010)
22                 SAUK AREA CAREER SCHOOL - CRESTWOOD
23    For the purchase and renovation of the
24      former Sauk Area Career School, converting
25      to an armory and upgrading the parking
26      lot ..........................................       89,022
27    (From Article 94, Section 10 of Public Act 90-0010)
28                     SPRINGFIELD - CAMP LINCOLN
29    For construction of a military academy
30      facility .....................................      638,820
31    For rehabilitation of the mechanical systems
32      and interior .................................       95,454
33                  STREATOR ARMORY - LASALLE COUNTY
34    (From Article 94, Section 10A of Public Act 90-0010)
                            -80-                BOB-CAPITAL99
 1    For renovation of the mechanical
 2      systems, in addition to funds
 3      previously appropriated ......................      268,729
 4    (From Article 94, Section 10 of Public Act 90-0010)
 5    For renovation of mechanical systems ...........       53,392
 6                           WAUKEGAN ARMORY
 7    For renovation of exterior walls, and
 8      replacement of doors and windows .............       70,281
 9                        WEST FRANKFORT ARMORY
10    For remodeling and installation of a kitchen ...       68,592
11                      WILLIAMSON COUNTY ARMORY
12    For providing the State's share for planning
13      and construction of a new armory, in
14      addition to amounts previously
15      appropriated .................................       14,316
16                          WOODSTOCK ARMORY
17    For the state's share for additional planning
18      and construction of an armory ................        7,940
19                              STATEWIDE
20    For replacement of roofs at the
21      following locations at the
22      approximate costs set forth below: ...........      293,250
23        Joliet Armory ........................52,000
24        Litchfield Armory ...................142,425
25        Springfield Military Academy .........98,825
26    For replacement of roofs at the following
27      locations at the approximate costs set
28      forth below ..................................      119,886
29          Camp Lincoln - AGO Building .......115,420
30          Mt. Vernon Armory ...................4,466
31    For installation of kitchens and renovation
32      of the interiors at the following locations
33      at the approximate costs set forth below: ....      167,750
34          Carbondale Armory ..................10,000
                            -81-                BOB-CAPITAL99
 1          Dixon Armory ......................151,750
 2          Elgin Armory ........................6,000 ____________
 3        Total, Section 9                              $10,677,951
 4        Section 9.1.  The following named  amounts,  or  so  much
 5    thereof  as  may  be  necessary  and remain unexpended at the
 6    close of business on June 30, 1998, from  appropriations  and
 7    reappropriations heretofore made for such purposes in Article
 8    93,  Section 6a of Public Act 90-0010 and Article 94, Section
 9    10.1 of Public  Act  90-0010,  are  reappropriated  from  the
10    General Revenue Fund to the Capital Development Board for the
11    Department  of  Military Affairs for the projects hereinafter
12    enumerated:
13    (From Article 93, Section 6a of Public Act 90-0010)
14                        LAWRENCEVILLE ARMORY
15    For renovating interior ........................ $    180,000
16    (From Article 94, Section 10.1 of Public Act 90-0010)
17                              STATEWIDE
18    For the following projects at the approximate
19      costs set forth below: .......................       86,000
20        Broadway Armory - Chicago
21          For repair of the heating
22          system .............................50,000
23        Freeport Armory
24          For renovation of the armory
25          and parking area, including
26          installation of a security
27          fence ..............................36,000 ____________
28        Total, Section 9.1                               $266,000
29        Section 10.  The following  named  amounts,  or  so  much
30    thereof  as  may  be  necessary  and remain unexpended at the
31    close of business on June 30, 1998, from  appropriations  and
32    reappropriations   heretofore   made  for  such  purposes  in
                            -82-                BOB-CAPITAL99
 1    Section 59 of Public Act 90-0550, and Article 94, Sections 12
 2    and 12A of Public Act 90-0010, are  reappropriated  from  the
 3    Capital Development Fund to the Capital Development Board for
 4    the   Department  of  Revenue  for  the  project  hereinafter
 5    enumerated:
 6    (From Section 59 of Public Act 90-0550)
 7                 WILLARD ICE BUILDING - SPRINGFIELD
 8    For upgrading the uninterruptible power
 9      system, in addition to funds previously
10      appropriated ................................. $  1,200,000
11    For replacing the halon fire suppression
12      system .......................................      344,000
13    (From Article 94, Section 12a of Public Act 90-0010)
14    For completion of the replacement of the
15      fire alarm and security system ...............       70,000
16    For upgrade of the uninterruptible
17      power system .................................    1,284,152
18    For completion of the renovation of
19      the atrium landscaping .......................      100,000
20    (From Article 94, Section 12 of Public Act 90-0010)
21    For planning for UPS upgrade and for renovation
22      of an interior landscape structure ...........        3,917
23        Total, Section 10                              $3,002,069
24        Section 11.  The  following  named  amount,  or  so  much
25    thereof  as  may  be  necessary and remains unexpended at the
26    close of business on June 30, 1998,  from  a  reappropriation
27    heretofore  made  for such purposes in Article 94, Section 13
28    of Public Act 90-0010, is  reappropriated  from  the  Capital
29    Development  Fund  to  the  Capital Development Board for the
30    Secretary of State for the project hereinafter enumerated:
31                    SPRINGFIELD - RECORDS CENTER
32    For correcting water infiltration in the
33      basement ..................................... $      7,012
                            -83-                BOB-CAPITAL99
 1        Total, Section 11                                  $7,012
 2        Section 12.  The following  named  amounts,  or  so  much
 3    thereof  as  may  be  necessary  and remain unexpended at the
 4    close of business on June 30, 1998, from  appropriations  and
 5    reappropriations heretofore made for such purposes in Section
 6    60  of  Public  Act 90-0550;  Article 93, Section 9 of Public
 7    Act 90-0010; and Article 94, Section 14 and 14A of Public Act
 8    90-0010, are reappropriated from the Capital Development Fund
 9    to the Capital Development Board for the Department of  State
10    Police for the projects hereinafter enumerated:
11    (From Article 94, Section 14 of Public Act 90-0010)
12                     CAIRO (ULLIN) - DISTRICT 22
13    For construction of a firing range and radio
14      tower ........................................ $    537,480
15                  CARMI - DISTRICT 19 HEADQUARTERS
16    For rehabilitation of headquarters
17      facilities ...................................      109,345
18    For planning rehabilitation of
19      Headquarters facilities ......................       60,000
20                    CHICAGO FORENSIC LABORATORY
21    For construction of a laboratory and
22      parking facilities ...........................      273,885
23                       DU QUOIN - DISTRICT 13
24    For planning the rehabilitation of the
25      headquarters, including the parking
26      lot and range ................................       15,569
27                      EAST MOLINE - DISTRICT 7
28    For rehabilitation of the headquarters
29      facilities and replacement of the
30      radio garage .................................       70,726
31                LITCHFIELD - DISTRICT 18 HEADQUARTERS
32    (From Article 94, Section 14A of Public Act 90-0010)
33    For rehabilitation of headquarters facilities ..      253,492
                            -84-                BOB-CAPITAL99
 1    (From Article 94, Section 14 of Public Act 90-0010)
 2    For planning rehabilitation of
 3      Headquarters facilities ......................       27,078
 4             SPRINGFIELD - STATE POLICE TRAINING ACADEMY
 5    For rehabilitation of the facility, including
 6      replacement of the HVAC system and
 7      installation of an elevator ..................      243,427
 8                        STERLING - DISTRICT 1
 9    For planning, construction, reconstruction,
10      demolition of existing buildings, and
11      all costs related to the relocation of
12      the headquarters, in addition to funds
13      previously appropriated ......................    1,817,398
14    For land acquisition, planning, construction,
15      reconstruction, demolition of existing
16      buildings, and all costs related to the
17      relocation of the District 1 Police
18      Headquarters in Sterling .....................      138,905
19                              STATEWIDE
20    (From Section 60 of Public Act 90-0550)
21    For replacing radio communication
22      towers and equipment buildings and
23      installing emergency power
24      generators at Andover, Eaton,
25      Pecatonia, and Cypress .......................    1,150,000
26    (From Article 93, Section 9 of Public Act 90-0010)
27    For replacing the roofs and roof
28      drainage systems at various locations,
29      at the approximate costs set forth below: ....      182,000
30       DuQuoin, District #13 .................85,000
31       Springfield, District #9 and
32        Supply Building ......................97,000
33    (From Article 94, Section 14A of Public Act 90-0010)
34    For replacing radio communication
                            -85-                BOB-CAPITAL99
 1      towers, equipment, buildings and
 2      installing emergency power
 3      generators at various locations ..............    1,109,000
 4       District #22, Effingham (Mason site)
 5       District #10, Pesotum
 6       District #21, Askum
 7       District #6, Pontiac
 8    (From Article 94, Section 14 of Public Act 90-0010)
 9    For replacing the roofing and roof
10      drainage systems at various facilities
11      at the approximate costs set forth
12      below ........................................       52,616
13       District #8, Metamora .................50,000
14       District #10, Pesotum ..................2,616 ____________
15        Total, Section 12                              $6,040,921
16        Section  13.  The  following  named  amounts,  or so much
17    thereof as may be necessary  and  remain  unexpended  at  the
18    close  of  business on June 30, 1998, from appropriations and
19    reappropriations  heretofore  made  for  such   purposes   in
20    Article 93, Section 10 of Public Act 90-0010, and Article 94,
21    Sections   15   and   15A   of   Public   Act   90-0010,  are
22    reappropriated from  the  Capital  Development  Fund  to  the
23    Capital  Development  Board  for  the Department of Veterans'
24    Affairs for the projects hereinafter enumerated:
25    (From Article 94, Section 15 of Public Act 90-0010)
26                             ANNA CENTER
27    For purchasing equipment, in addition to funds
28      previously appropriated ...................... $     24,480
29                   LASALLE VETERANS CARE FACILITY
30    For construction of a storage building  ........      178,380
31    For installation of a medical gas system
32      and for additional funding for a
33      Special Care Unit ............................        8,366
                            -86-                BOB-CAPITAL99
 1    For installation of door alarm systems .........       25,439
 2                  ILLINOIS VETERANS' HOME - MANTENO
 3    (From Article 94, Section 15A of Public Act 90-0010)
 4    For construction of a special care facility ....   $5,550,000
 5    (From Article 94, Section 15 of Public Act 90-0010)
 6    For planning the construction of a special
 7      care facility ................................       72,352
 8    For replacement of roofs and upgrade
 9      of sewer system, in addition to funds
10      previously appropriated ......................      404,509
11    For reinforcement and sealing off of sections
12      of utility tunnels ...........................       26,512
13    For air conditioning the interconnects .........       41,964
14    For replacement of the roof on Kilbourne,
15      Meyers and Billings and upgrade
16      of sewer system, in addition to
17      funds previously appropriated ................       88,363
18                  ILLINOIS VETERANS' HOME - QUINCY
19    (From Article 93, Section 10 of Public Act 90-0010)
20    For renovating Lippincott Hall .................      215,000
21    (From Article 94, Section 15A of Public Act 90-0010)
22    For upgrading HVAC system ......................      236,070
23    For replacing steam lines ......................       83,000
24    For replacing the domestic hot water loop ......      305,000
25    For renovating the elevator ....................      195,350
26    (From Article 94, Section 15 of Public Act 90-0010)
27    For renovation and replacement of power plant
28      equipment ....................................      133,637
29    For construction of a Therapy Building and
30      renovation of the Kent Building entrance,
31      in addition to funds previously
32      appropriated .................................       13,117
33        Total, Section 13                              $7,601,539
                            -87-                BOB-CAPITAL99
 1        Section 13.1.  The following named amounts,  or  so  much
 2    thereof  as  may  be  necessary  and remain unexpended at the
 3    close of business on June 30, 1998, from  appropriations  and
 4    reappropriations heretofore made for such purposes in Article
 5    93,  Section  10a  of  Public  Act  90-0010,  and Article 94,
 6    Section 15.1 of Public Act 90-0010, are  reappropriated  from
 7    the General Revenue Fund to the Capital Development Board for
 8    the   Department   of  Veterans'  Affairs  for  the  projects
 9    hereinafter enumerated:
10                  ILLINOIS VETERANS' HOME - LASALLE
11    (From Article 93, Section 10A of Public Act 90-0010)
12    For relocating security alarm
13      system ....................................... $     37,800
14    For installing an exit door
15      alarm system .................................       52,500
16                  ILLINOIS VETERANS' HOME - MANTENO
17    For replacing wiring in light poles ............      153,900
18    For replacing exterior doors and frames ........      200,000
19    (From Article 94, Section 15.1 of Public Act 90-0010)
20    For stabilization of the Billings, Kilbourne,
21      and Meyers Buildings and upgrade of
22      sewer system, in addition to funds
23      previously appropriated ......................       37,069
24    For replacement of sewer lines, repair and
25      replacement of bar screens, and
26      rehabilitation of the water tower and
27      reservoir ....................................      234,861
28        Total, Section 13.1                              $716,130
29        Section 14.  The following  named  amounts,  or  so  much
30    thereof  as  may  be  necessary  and remain unexpended at the
31    close of business on June 30, 1998, from  appropriations  and
32    reappropriations   heretofore   made  for  such  purposes  in
33    Sections 62  and  63  of  Public  Act  90-0550;  Article  93,
                            -88-                BOB-CAPITAL99
 1    Sections  11.02  and 11.03 of Public Act 90-0010; and Article
 2    94,  Sections  16  and  16A  of  Public  Act   90-0010,   are
 3    reappropriated  from  the  Capital  Development  Fund  to the
 4    Capital  Development  Board  for  the  projects   hereinafter
 5    enumerated:
 6    (From Article 94, Section 16 of Public Act 90-0010)
 7              ATTORNEY GENERAL BUILDING - SPRINGFIELD
 8    For planning energy improvements and upgrading
 9      HVAC and electrical systems .................. $      9,299
10                 MT. VERNON APPELLATE COURT BUILDING
11    For installation of a security system ..........       20,021
12                SPRINGFIELD - SUPREME COURT BUILDING
13    For replacement of side walls and steps, in addition
14      to funds previously appropriated .............       82,574
15                    SPRINGFIELD - CAPITOL COMPLEX
16    (From Section 63 of Public Act 90-0550):
17    For installing fire/security alarm
18      system .......................................    1,100,000
19    (From Article 93, Section 11.02 of Public Act 90-0010)
20    For stabilizing the parking ramp ...............    3,000,000
21    (From Article 94, Section 16A of Public Act 90-0010)
22    For energy improvements and upgrading the
23      HVAC, security and electrical systems,
24      in addition to funds previously
25      appropriated - Attorney General's
26      Building .....................................      216,450
27    To renovate the interior, exterior and
28      site improvements, in addition to
29      funds previously appropriated -
30      Executive Mansion ............................       91,306
31    For upgrading environmental equipment
32      and HVAC, in addition to funds previously
33      appropriated - Archives Building .............    2,150,000
34    For planning and beginning the rehabilitation
                            -89-                BOB-CAPITAL99
 1      of the Power Plant ...........................    3,805,000
 2    For upgrading sewer system - Capitol Complex,
 3      in addition to funds previously
 4      appropriated .................................    2,023,683
 5    For renovation of the lower level and
 6      ground floor, in addition to funds
 7      previously appropriated - Old Power Plant ....    1,747,101
 8    (From Article 94, Section 16 of Public Act 90-0010)
 9    For upgrading the life/safety and security
10      systems - Capitol Building ...................    2,116,800
11    For upgrading the refrigeration equipment -
12      Capitol Complex ..............................    3,466,000
13    For renovating mechanical system -
14      Capitol Complex, in addition to funds
15      previously appropriated ......................    3,322,326
16    For planning the upgrade of environmental
17      equipment and HVAC ...........................       57,619
18    For renovation of mechanical systems, in
19      addition to funds previously appropriated ....      528,808
20    For upgrading the elevators ....................       59,396
21    For planning and beginning sewer
22      rehabilitation ...............................       34,625
23    For renovation of the second floor of the
24      Old Powerhouse for the Emergency Manage-
25      ment Agency ..................................       22,131
26    For providing a parking facility for the
27      Bloom and Harris Buildings, including
28      land acquisition .............................      249,824
29    For all costs associated with the design
30      and planning for asbestos abatement,
31      window replacement, energy conservation
32      improvements, replacement of carpeting and
33      ceiling tiles, handicap accessibility
34      improvements, and rehabilitation of the
                            -90-                BOB-CAPITAL99
 1      water and air distribution systems in the
 2      Stratton Office Building .....................    1,636,429
 3    For planning and design of the rehabilitation
 4      of the Springfield Armory ....................      656,425
 5    For renovation of the Waterways Building for
 6      the Fourth District of the Appellate Court ...    3,701,859
 7             SPRINGFIELD - SIU CONSOLIDATED LABORATORIES
 8    For construction of an addition to the
 9      laboratory facility for Southern Illinois
10      University, Environmental Protection Agency
11      and Department of Public Health ..............      727,459
12                       STATE CAPITOL BUILDING
13    (From Section 63 of Public Act 90-0550)
14    For upgrading the life/safety and
15      security systems, in addition to
16      funds previously appropriated ................    2,600,000
17               STRATTON OFFICE BUILDING - SPRINGFIELD
18    (From Section 63 of Public Act 90-0550)
19    For installing fire alarm system ...............      400,000
20                              STATEWIDE
21    (From Section 62 of Public Act 90-0550):
22    For surveys and modifications to
23      buildings to meet requirements of the
24      federal Americans with Disabilities Act ......    5,000,000
25    (From Article 93, Section 11.03 of Public Act 90-0010)
26    For abatement of hazardous materials ...........    5,000,000
27    For upgrading/retrofitting mechanized
28      refrigeration equipment (CFC's) ..............    5,000,000
29    For upgrade and remediation of underground
30      storage tanks ................................    5,000,000
31    (From Article 94, Section 16A of Public Act 90-0010)
32    For renovation to meet the requirements
33      of the Americans with Disabilities Act .......    3,000,000
34    (From Article 94, Section 16 of Public Act 90-0010)
                            -91-                BOB-CAPITAL99
 1    For abatement of hazardous materials ...........    4,967,927
 2    For upgrade and remediation of
 3      underground storage tanks ....................    5,000,000
 4    For survey for and abatement of
 5      asbestos-containing materials ................    2,000,000
 6    For upgrade/retrofit of mechanized
 7      refrigeration equipment (CFC's) ..............    6,832,397
 8    For abatement of hazardous conditions,
 9      including underground storage tanks,
10      in addition to funds previously
11      appropriated .................................    1,421,091
12    For surveys and modifications to buildings
13      to meet requirements of the federal
14      Americans with Disabilities Act ..............   30,871,012
15    For demolition of buildings ....................    4,108,754
16    For retrofitting/upgrading mechanical
17      refrigeration equipment ......................    1,277,506
18    For planning quick chill food factories ........      133,946
19                STATEWIDE - UNDERGROUND STORAGE TANKS
20    For abating hazardous conditions, including
21      underground storage tanks, in addition to
22      funds previously appropriated ................      151,622
23    For the planning, upgrade and replacement of
24      potentially hazardous underground storage
25      tanks ........................................      878,720
26                     STATEWIDE - ASBESTOS SURVEY
27    For surveys and abatement of asbestos-
28      containing materials .........................    1,386,058
29                   STATEWIDE - ASBESTOS ABATEMENT
30    For asbestos abatement located during
31      Asbestos Abatement Authority and other
32      surveys to eliminate significant health
33      hazards ......................................      367,424
34    For planning and abatement of asbestos, and
                            -92-                BOB-CAPITAL99
 1      replenishment of initial project
 2      construction costs in bondable projects
 3      at various state owned facilities ............      460,290
 4        Total, Section 14                            $116,681,882
 5        Section  14.1.  The amount of $51,193, or so much thereof
 6    as may be necessary and remains unexpended at  the  close  of
 7    business  on June 30, 1998, from a reappropriation heretofore
 8    made for such purpose in Article 94, Section 16.2  of  Public
 9    Act  90-0010,  is reappropriated from the Capital Development
10    Fund  to  the  Capital  Development   Board   for   planning,
11    construction  and  equipment  for a joint laboratory facility
12    for  the  Illinois  Environmental  Protection   Agency,   the
13    Department  of  Public  Health,  and  the  Southern  Illinois
14    University  School of Medicine at the SIU Medical Facility in
15    Springfield.
16        Section 14.2.  The sum of $825,000, or so much thereof as
17    may be necessary and remains unexpended  on  June  30,  1998,
18    from  a  reappropriation heretofore made for such purposes in
19    Article  94,  Section  17.7  of  Public   Act   90-0010,   is
20    reappropriated  from  the  Capital  Development  Fund  to the
21    Capital Development Board for the Secretary of  State  for  a
22    grant  to the Edgebrook Library for all costs associated with
23    the miscellaneous costs incurred for  construction  or  other
24    purposes.
25        Section 14.3.  The sum of $400,000, or so much thereof as
26    may  be  necessary  and  remains  unexpended  at the close of
27    business on June 30, 1998, from an  appropriation  heretofore
28    made  for  such  purposes  in  Article  93, Section 11.03b of
29    Public  Act  90-0010,  is  reappropriated  from  the  Capital
30    Development Fund to the Capital  Development  Board  for  the
31    Secretary  of  State  for a grant to the Wilmette Library for
                            -93-                BOB-CAPITAL99
 1    all   costs   associated   with    planning,    construction,
 2    reconstruction, and rehabilitation or other purposes.
 3        Section  15.  The  following  named  amounts,  or so much
 4    thereof as may be necessary  and  remain  unexpended  at  the
 5    close  of  business on June 30, 1998, from appropriations and
 6    reappropriations heretofore made for such purposes in Article
 7    93, Section 11.03b of Public Act  90-0010,  and  Article  94,
 8    Section  17  of  Public Act 90-0010,  are reappropriated from
 9    the General Revenue Fund to the Capital Development Board for
10    the projects hereinafter enumerated:
11                              STATEWIDE
12    (From Article 93, Section 11.03a of Public Act 90-0010):
13    For repair of minor problems and
14      emergencies .................................. $  3,614,300
15    For construction site archeological
16      studies ......................................      200,000
17    For surveys for and abatement of
18      asbestos-containing material .................    1,000,000
19    For demolition of buildings ....................    5,000,000
20    (From Article 94, Section 17 of Public Act 90-0010)
21    For repair of minor problems and
22      emergencies ..................................    1,501,903
23    For tuckpointing and exterior repair
24      of state buildings ...........................      613,000
25    For surveys for asbestos containing
26      material .....................................      285,488
27    For construction site archaeological
28      studies ......................................       90,413
29    For survey of asbestos-containing
30      materials ....................................      237,636
31    For repairing minor problems and for
32      emergencies, in addition to funds
33      previously appropriated ......................       57,371
                            -94-                BOB-CAPITAL99
 1    For repairing minor problems and emergencies
 2      for agencies .................................      233,756
 3    For the planning and abatement of asbestos
 4      hazards, and replenishment of initial
 5      project construction costs in
 6      non-bondable projects at various
 7      state owned facilities .......................      197,110
 8        Total, Section 15                             $13,030,977
 9        Section 15.1.  The sum of $14,400, or so much thereof  as
10    may  be  necessary  and  remains  unexpended  at the close of
11    business on June 30, 1998, from an  appropriation  heretofore
12    made  for  such purposes in Section 46 of Public Act 90-0550,
13    is reappropriated  from  the  General  Revenue  Fund  to  the
14    Capital  Development Board for a grant to Charleston Township
15    for all costs associated with meeting the requirements of the
16    Americans with Disabilities Act.
17        Section 15.2.  The sum of $250,000, or so much thereof as
18    may be necessary and  remains  unexpended  at  the  close  of
19    business  on  June 30, 1998, from an appropriation heretofore
20    made for such purposes in Article 93, Section  17  of  Public
21    Act  90-0010,  as amended by Section 7 of Public Act 90-0550,
22    is reappropriated  from  the  General  Revenue  Fund  to  the
23    Capital  Development  Board  for  a  grant to the Lake Zurich
24    Rural Fire Protection District for all costs associated  with
25    planning, construction, reconstruction, and rehabilitation or
26    other firehouse purposes.
27        Section 15.3.  The sum of $400,000, or so much thereof as
28    may  be  necessary  and  remains  unexpended  at the close of
29    business on June 30, 1998 from  an  appropriation  heretofore
30    made  for  such  purposes in Article 93, Section 23 of Public
31    Act 90-0010, is reappropriated from the General Revenue  Fund
                            -95-                BOB-CAPITAL99
 1    to  the  Capital Development Board for a grant to the City of
 2    Danville for all costs associated with the construction of  a
 3    new  firehouse  and  the  conversion  of  the  library  to  a
 4    children's museum.
 5        Section 15.4.  The sum of $300,000, or so much thereof as
 6    may  be  necessary  and  remains  unexpended  at the close of
 7    business on June 30, 1998, from an  appropriation  heretofore
 8    made  for  such  purposes in Article 93, Section 30 of Public
 9    Act 90-0010, is reappropriated from the General Revenue  Fund
10    to  the Capital Development Board for a grant to Lincoln Land
11    Community  College  for  all  costs   associated   with   the
12    remodeling of Cass Gymnasium.
13        Section  15.5.  The sum of $1,500,000, or so much thereof
14    as may be necessary and remains unexpended at  the  close  of
15    business  on  June 30, 1998, from an appropriation heretofore
16    made for such purposes in Article 93, Section  31  of  Public
17    Act  90-0010, is reappropriated from the General Revenue Fund
18    to the Capital Development Board for a grant to Lincoln  Land
19    Community   College   for   all  costs  associated  with  the
20    construction of a new Rural Education and Technology Center.
21        Section 15.6.  The sum of $236,088, or so  much  of  that
22    amount  as  may  be  necessary  and remains unexpended at the
23    close of business on June 30, 1998,  from  a  reappropriation
24    heretofore made for such purposes in Article 94, Section 17.4
25    of  Public  Act  90-0010,  is  reappropriated  to the Capital
26    Development Board from  the  General  Revenue  Fund  for  the
27    planning  and  construction of the Anna Veterans Home Visitor
28    Center.
29        Section 15.7.  The amount of $538,151, or so much thereof
30    as may be necessary and remains unexpended at  the  close  of
                            -96-                BOB-CAPITAL99
 1    business  on  June 30, 1998, from an appropriation heretofore
 2    made for such purposes in Article 94, Section 17.5 of  Public
 3    Act  90-0010, is reappropriated from the General Revenue Fund
 4    to  the  Capital  Development  Board  for  planning,  design,
 5    construction, renovation, and all other necessary  costs  for
 6    the Market House in Galena.
 7        Section 15.8.  The sum of $976,000, or so much thereof as
 8    may  be  necessary  and  remains unexpended on June 30, 1998,
 9    from an appropriation heretofore made for  such  purposes  in
10    Article   94,   Section   17.6  of  Public  Act  90-0010,  is
11    reappropriated from the General Revenue Fund to  the  Capital
12    Development  Board  for  planning  and renovation of Founders
13    Memorial Library at Northern Illinois University.
14        Section  16.  The  amount  of  $30,000,000,  or  so  much
15    thereof as may be necessary and  remains  unexpended  at  the
16    close  of  business  on  June 30, 1998, from an appropriation
17    heretofore made for such purposes in Section  51c  of  Public
18    Act 90-0550, is reappropriated from the School Infrastructure
19    Fund to the Capital Development Board for school construction
20    project grants pursuant to the School Construction Law.
21        Section  17.  The  sum of $272,189, or so much thereof as
22    may be necessary and  remains  unexpended  at  the  close  of
23    business  on June 30, 1998, from a reappropriation heretofore
24    made for such purposes in Article 94, Section  19  of  Public
25    Act  90-0010,  is  reappropriated from the Asbestos Abatement
26    Fund to the Capital Development Board for asbestos surveys in
27    relation to the  asbestos  abatement  of  State  Governmental
28    Buildings.
29        Section  18.  The  following  named  amounts,  or so much
30    thereof as may be necessary  and  remain  unexpended  at  the
                            -97-                BOB-CAPITAL99
 1    close  of  business  on  June 30, 1998, from reappropriations
 2    heretofore made for such purposes in Article 94, Sections  20
 3    and  22A  of  Public Act 90-0010, are reappropriated from the
 4    Capital Development Fund to the Capital Development Board for
 5    the Board of Higher Education for  the  projects  hereinafter
 6    enumerated:
 7          ILLINOIS MATHEMATICS AND SCIENCE ACADEMY - AURORA
 8    (From Article 94, Section 22A of Public Act 90-0010)
 9    For replacing air conditioning units,
10      controls and upgrading the energy
11      management system ............................ $  2,370,000
12    (From Article 94, Section 20 of Public Act 90-0010)
13    For remodeling the Information Resource
14      Technology Center ............................       96,336
15    For renovation of the laboratory areas,
16      including a greenhouse .......................       87,700
17    For the purchase, renovation and improvement
18      of the North Campus High School site of
19      the Aurora West School District 129,
20      including construction of four dormitories,
21      equipment purchases and other expenses for
22      use by the Illinois Mathematics and Science
23      Academy ......................................    2,271,053
24        Total, Section 18                              $4,825,089
25        Section  19.  The  following  named  amounts,  or so much
26    thereof as may be necessary  and  remain  unexpended  at  the
27    close  of  business on June 30, 1998, from appropriations and
28    reappropriations heretofore made for such purposes in Section
29    64 of Public Act 90-0550, and Article 94, Sections 21 and 21A
30    of Public Act 90-0010, are reappropriated  from  the  Capital
31    Development  Fund  to  the  Capital Development Board for the
32    Illinois Community College Board for the projects hereinafter
33    enumerated:
                            -98-                BOB-CAPITAL99
 1                       BELLEVILLE AREA COLLEGE
 2    (From Article 94, Section 21A of Public Act 90-0010)
 3    For constructing a building, additions
 4      and site improvements at the
 5      Belleville and Red Bud campuses,
 6      in addition to funds previously
 7      appropriated ................................. $ 10,797,100
 8    (From Article 94, Section 21 of Public Act 90-0010)
 9    For planning buildings, additions and
10      site improvements ............................    1,451,210
11            DANVILLE COMMUNITY COLLEGE - VERMILION COUNTY
12    (From Article 94, Section 21A of Public Act 90-0010)
13    To rehabilitate infrastructure,
14      construct a classroom facility
15      and a day care center, in addition
16      to funds previously appropriated .............    4,140,932
17    (From Article 94, Section 21 of Public Act 90-0010)
18    For rehabilitation of infrastructure
19      and beginning construction of a
20      classroom facility ...........................    1,753,743
21    For rehabilitation of the infrastructure and
22      planning campus buildings ....................      885,648
23                          COLLEGE OF DUPAGE
24    For completing the addition to
25      the Student Resource Center ..................      168,024
26                       ELGIN COMMUNITY COLLEGE
27    For construction of addition, site improvements,
28      remodeling and purchasing equipment ..........    1,052,361
29    For planning, design, site improvements, utility
30      adjustments, and any other costs associated
31      with construction of a new Instructional
32      Building at Elgin Community College ..........      135,999
33              HEARTLAND COMMUNITY COLLEGE - BLOOMINGTON
34    (From Section 64 of Public Act 90-0550)
                            -99-                BOB-CAPITAL99
 1    For constructing buildings and making
 2      site improvements, including equipment .......   21,015,900
 3    (From Article 94, Section 21A of Public Act 90-0010)
 4    For planning buildings, parking areas,
 5      utilities, and site development and
 6      preliminary site preparation
 7      required to establish permanent
 8      campus facilities ............................    2,173,805
 9                   JOHN A. LOGAN COMMUNITY COLLEGE
10    (From Article 94, Section 21A of Public Act 90-0010)
11    For constructing additions and site
12      improvements, in addition to funds
13      previously appropriated ......................   12,136,568
14    (From Article 94, Section 21 of Public Act 90-0010)
15    For construction of classroom facility,
16      and remodeling the existing facility,
17      including utilities and site improvements ....       33,745
18                     JOHN WOOD COMMUNITY COLLEGE
19    For construction of a science and technology
20      center and access road .......................       58,276
21                        JOLIET JUNIOR COLLEGE
22    For construction of a business and technology
23      center and remodeling the main campus
24      building .....................................      619,182
25    For planning, design and site preparation of
26      a Business Technology Center .................       10,338
27                       COLLEGE OF LAKE COUNTY
28    For construction of a multi-use Instructional
29      Center, including acquisition of equipment
30      and remodeling of existing facilities ........       77,973
31    For initial costs associated with planning,
32      design, construction, site improvements,
33      utilities, remodeling and equipment for
34      a multi-use instructional facility ...........       20,171
                            -100-               BOB-CAPITAL99
 1                  LEWIS AND CLARK COMMUNITY COLLEGE
 2    For renovation of buildings, construction of an
 3      addition and site improvements ...............      216,805
 4    For construction of health, mathematics and
 5      science laboratory facilities and
 6      remodeling Fobes Hall ........................      378,484
 7    For renovation of the main complex .............       14,925
 8    For planning, design, and site preparation,
 9      and construction of a multi-purpose
10      building .....................................       22,932
11                       MCHENRY COUNTY COLLEGE
12    For construction of an addition, including
13      equipment, a parking area and
14      site improvements ............................       19,993
15                  MORAINE VALLEY COMMUNITY COLLEGE
16    For planning and constructing a new classroom
17      facility .....................................      362,212
18    For providing for an architectural engineering
19      study, renovations, construction,
20      reconstruction and remodeling of Buildings
21      A, B and L ...................................      417,365
22                   PRAIRIE STATE COMMUNITY COLLEGE
23    For construction of a Learning Resource
24      Center addition ..............................       39,959
25                          REND LAKE COLLEGE
26    For construction of an aquatic and
27      rehabilitation center ........................       55,125
28                  SHAWNEE COMMUNITY COLLEGE - ULLIN
29    (From Section 64 of Public Act 90-0550)
30    For constructing additions, parking
31      facilities, and renovating buildings,
32      including equipment ..........................    7,403,200
33    (From Article 94, Section 21A of Public Act 90-0010)
34    For planning additions to the main
                            -101-               BOB-CAPITAL99
 1      building, parking areas, site
 2      improvements and roofing
 3      replacements .................................      310,000
 4    (From Article 94, Section 21 of Public Act 90-0010)
 5                    SOUTHEASTERN ILLINOIS COLLEGE
 6    For construction of humanities,
 7      administration, and child care facilities
 8      and remodeling campus buildings ..............       87,849
 9               TRITON COMMUNITY COLLEGE - RIVER GROVE
10    For planning, site improvements, construction
11      and other expenses necessary for the
12      construction of an addition to the Learning
13      Resource Center ..............................      122,078
14         WILLIAM RAINEY HARPER COMMUNITY COLLEGE - PALATINE
15    (From Section 64 of Public Act 90-0550)
16    For constructing a Multi-purpose
17      Instructional Center and renovating
18      Building A Cafeteria .........................    6,823,200
19    (From Article 94, Section 21 of Public Act 90-0010)
20    For planning, developing, and designing a
21      multi-purpose telecommunications
22      instructional delivery center ................      114,792
23                  STATEWIDE - CONSTRUCTION DEFECTS
24    For planning, construction and renovation
25      to correct defectively designed or
26      constructed community college facilities,
27      provided that monies recovered based upon
28      claims arising out of such defective design
29      or construction shall be paid to the state
30      as required by Section 105.12 of the Public
31      Community College Act as reimbursement for
32      monies expended pursuant to this
33      appropriation ................................    1,529,813
34        Total, Section 19                             $74,449,707
                            -102-               BOB-CAPITAL99
 1        Section 19A.  The sum of $5,008,000, or so  much  thereof
 2    as  may  be  necessary and remains unexpended at the close of
 3    business on June 30, 1998, from an  appropriation  heretofore
 4    made  for  such purposes in Section 67 of Public Act 90-0550,
 5    is reappropriated from the Capital Development  Fund  to  the
 6    Capital  Development Board for the Illinois Community College
 7    Board  for  miscellaneous  capital   improvements   including
 8    construction, reconstruction, remodeling, improvement, repair
 9    and  installation  of  capital  facilities, cost of planning,
10    supplies,  equipment,  materials,  services  and  all   other
11    expenses  required  to  complete  the  work  at  the  various
12    community  colleges.  This appropriation shall be in addition
13    to any other appropriated amounts which can be  expended  for
14    these purposes.
15        Section  19B.  The  sum of $8,608,805, or so much thereof
16    as may be necessary and remains unexpended at  the  close  of
17    business  on  June 30, 1998, from an appropriation heretofore
18    made for such purposes in Article 94, Section 21B  of  Public
19    Act  90-0010,  is reappropriated from the Capital Development
20    Fund to  the  Capital  Development  Board  for  the  Illinois
21    Community    College    Board   for   miscellaneous   capital
22    improvements    including    construction,    reconstruction,
23    remodeling, improvement, repair and installation  of  capital
24    facilities, cost of planning, supplies, equipment, materials,
25    services and all other expenses required to complete the work
26    at  the various community colleges.  This appropriation shall
27    be in addition to any other appropriated amounts which can be
28    expended for these purposes.
29        Section 19C.  The sum of $2,919,369, or so  much  thereof
30    as  may  be  necessary and remains unexpended at the close of
31    business on June 30, 1998, from  reappropriations  heretofore
32    made for such purposes in  Article 94, Section 21.1 of Public
                            -103-               BOB-CAPITAL99
 1    Act  90-0010,  is reappropriated from the Capital Development
 2    Fund to  the  Capital  Development  Board  for  the  Illinois
 3    Community  College Board for grants to community colleges for
 4    miscellaneous capital  improvements  including  construction,
 5    reconstruction,    remodeling,   improvements,   repair   and
 6    installation  of  capital  facilities,  cost   of   planning,
 7    supplies,  equipment,  materials,  services,  and  all  other
 8    expenses  required  to  complete the work. This appropriation
 9    shall be in addition to any other appropriated amounts  which
10    can be expended for these purposes.
11        Section  20.  The  following  named  amounts,  or so much
12    thereof as may be necessary  and  remain  unexpended  at  the
13    close  of  business on June 30, 1998, from appropriations and
14    reappropriations heretofore made for such purposes in Section
15    65 of Public Act 90-0550, and Article 94, Sections 22 and 22A
16    of Public Act 90-0010, are reappropriated  from  the  Capital
17    Development  Fund  to  the  Capital Development Board for the
18    Board  of  Higher  Education  for  the  projects  hereinafter
19    enumerated:
20                      CHICAGO STATE UNIVERSITY
21    (From Section 65 of Public Act 90-0550)
22    For renovating buildings and upgrading
23      mechanical systems ...........................  $ 3,300,000
24    (From Article 94, Section 22A of Public Act 90-0010)
25    For renovating campus buildings and
26      upgrading mechanical systems .................    2,432,200
27    (From Article 94, Section 22 of Public Act 90-0010)
28    For providing campus health and safety
29      improvements .................................      133,815
30    For remodeling the Cook Administration
31      Building .....................................       12,128
32                     EASTERN ILLINOIS UNIVERSITY
33    (From Section 65 of Public Act 90-0550)
                            -104-               BOB-CAPITAL99
 1    For constructing an addition and
 2      renovating Booth Library .....................   16,764,500
 3    (From Article 94, Section 22A of Public Act 90-0010)
 4    For planning an addition and renovation
 5      of Booth Library .............................    1,000,000
 6    (From Article 94, Section 22 of Public Act 90-0010)
 7    For construction of an addition and
 8      remodeling Buzzard Building ..................      495,433
 9    For upgrading the energy management system
10      and HVAC systems and installation of a chilled
11      water loop between various buildings .........      623,355
12    For completing conversion to a coal-fired
13      power plant ..................................       79,503
14    For completion of the construction and
15      renovation of the heating system .............       37,703
16    For planning, equipment, site improvements,
17      construction and renovation of the heating
18      system to restore coal burning capability ....       30,429
19              GOVERNORS STATE UNIVERSITY - PARK FOREST
20    (From Article 94, Section 22A of Public Act 90-0010)
21    For upgrading and replacing cooling
22      and refrigeration systems and
23      equipment ....................................    2,299,400
24    (From Article 94, Section 22 of Public Act 90-0010)
25    For renovation of the main building ............      422,825
26    For remodeling Main Building ...................      346,063
27    For replacement of the main building roof
28      and renovation of the interior of the
29      main building ................................      541,923
30    For renovation of the main building ............      237,761
31    For remodeling the main building ...............      175,007
32             NORTHEASTERN ILLINOIS UNIVERSITY - CHICAGO
33    (From Section 65 of Public Act 90-0550)
34    For renovating the auditorium in
                            -105-               BOB-CAPITAL99
 1      Building E ...................................    7,156,700
 2    (From Article 94, Section 22 of Public Act 90-0010)
 3    For upgrading the boilers and related
 4      control systems ..............................       82,232
 5    For fire safety modifications at the
 6      facility .....................................    1,349,273
 7    For renovation of Buildings E, F, and
 8      the auditorium, and demolition and
 9      replacement of Buildings G, J and M,
10      in addition to amounts previously
11      appropriated .................................    8,532,437
12    For remodeling the library .....................      171,978
13                NORTHERN ILLINOIS UNIVERSITY - DEKALB
14    (From Section 65 of Public Act 90-0550)
15    For renovating Altgeld Hall and
16      purchasing equipment .........................   19,150,400
17              SOUTHERN ILLINOIS UNIVERSITY - CARBONDALE
18    (From Article 94, Section 22A of Public Act 90-0010)
19    For site improvements and purchasing
20      equipment for the Engineering and
21      Technology Building ..........................      757,426
22    For planning addition, remodeling and
23      upgrading the HVAC system in Altgeld Hall ....      574,000
24             SOUTHERN ILLINOIS UNIVERSITY - EDWARDSVILLE
25    For construction of the Engineering Facility
26      building and related site improvements .......   21,161,358
27                UNIVERSITY OF ILLINOIS - SPRINGFIELD
28    For completion of access road improvements,
29      including all costs associated with
30      a connection to 11th Street ..................      451,600
31                  UNIVERSITY OF ILLINOIS - CHICAGO
32    For the renovation of the court area and
33      Lecture Center, in addition to funds
34      previously appropriated ......................    5,887,400
                            -106-               BOB-CAPITAL99
 1                 UNIVERSITY OF ILLINOIS - CHAMPAIGN
 2    (From Section 65 of Public Act 90-0550)
 3    For constructing an Agricultural
 4      Library ......................................    9,500,000
 5    (From Article 94, Section 22A of Public Act 90-0010)
 6    For completion of campus flood control .........    6,000,000
 7                WESTERN ILLINOIS UNIVERSITY - MACOMB
 8    For remodeling Horrabin Hall and
 9      beginning to convert Simpkins Hall
10      gymnasium and adjacent areas into
11      a performing arts facility ...................    2,309,300
12    (From Article 94, Section 22 of Public Act 90-0010)
13    For renovation of Knoblauch Hall ...............      115,195
14    For construction of a steam and electrical
15      utility tunnel ...............................      212,459
16          WESTERN ILLINOIS UNIVERSITY - ROCK ISLAND COUNTY
17    For purchasing land and a building and
18      converting to an educational center ..........      216,284
19        Total, Section 20                            $112,560,087
20        Section 20.1.  The sum of $780,729, or so much thereof as
21    may be necessary and  remains  unexpended  at  the  close  of
22    business  on June 30, 1998, from a reappropriation heretofore
23    made for such purposes in  Article 94, Section 22.1 of Public
24    Act 90-0010, is reappropriated from the  Capital  Development
25    Fund to the Capital Development Board for the Board of Higher
26    Education  for  miscellaneous  capital improvements including
27    construction, reconstruction, remodeling, improvement, repair
28    and installation of capital  facilities,  cost  of  planning,
29    supplies,   equipment,  materials,  services  and  all  other
30    expenses required for completing the the work at the colleges
31    and universities.  This appropriation shall be in addition to
32    any other appropriated amounts  which  can  be  expended  for
33    these purposes.
                            -107-               BOB-CAPITAL99
 1        Section  20.2.  The  following  named amounts, or so much
 2    thereof as may be necessary  and  remain  unexpended  at  the
 3    close  of  business  on  June 30, 1998, from reappropriations
 4    heretofore made for such purposes in Article 94, Section 22.2
 5    of Public Act 90-0010, are reappropriated  from  the  Capital
 6    Development  Fund  to  the  Capital Development Board for the
 7    Board  of  Higher   Education   for   miscellaneous   capital
 8    improvements    including    construction,    reconstruction,
 9    remodeling,  improvement,  repair and installation of capital
10    facilities, cost of planning, supplies, equipment, materials,
11    services and all other expenses required to complete the work
12    at the colleges and universities hereinafter enumerated. This
13    appropriation shall be in addition to any other  appropriated
14    amounts which can be expended for these purposes:
15      Eastern Illinois University .................. $     24,385
16      Northeastern Illinois University .............      342,532
17      Western Illinois University ..................      487,936
18        Total, Section 20.2                              $854,853
19        Section 20.3.  The sum of $14,992,000, or so much thereof
20    as  may  be  necessary and remains unexpended at the close of
21    business on June 30, 1998, from an  appropriation  heretofore
22    made  for  such purposes in Section 66 of Public Act 90-0550,
23    is reappropriated from the Capital Development  Fund  to  the
24    Capital  Development  Board for the Board of Higher Education
25    for    miscellaneous    capital    improvements,    including
26    construction, reconstruction, remodeling, improvement, repair
27    and installation of capital  facilities,  cost  of  planning,
28    supplies,   equipment,  materials,  services  and  all  other
29    expenses  required  to  complete  the  work  at  the  various
30    universities set forth below.  This appropriation shall be in
31    addition to any  other  appropriated  amounts  which  can  be
32    expended for these purposes.
33      For Chicago State University ......... 301,400
                            -108-               BOB-CAPITAL99
 1      For Eastern Illinois University ...... 564,100
 2      For Governors State University ....... 181,600
 3      For Illinois State University ...... 1,150,600
 4      For Northeastern Illinois University . 423,700
 5      For Northern Illinois University ... 1,287,700
 6      For Western Illinois University ...... 862,400
 7      For Southern Illinois University -
 8       Carbondale ........................ 1,991,500
 9      For Southern Illinois University -
10       Edwardsville ........................ 751,500
11      For University of Illinois -
12       Chicago ........................... 3,280,400
13      For University of Illinois -
14       Springfield ......................... 216,800
15      For University of Illinois -
16       Urbana-Champaign .................. 3,980,300
17        Section  21.  The  following  named  amounts,  or so much
18    thereof as may be necessary  and  remain  unexpended  at  the
19    close  of  business  on  June 30, 1998, from reappropriations
20    heretofore made for such purposes in  Article 94, Section  23
21    of  Public  Act  90-0010, are reappropriated from the Capital
22    Development Fund to the Capital  Development  Board  for  the
23    Board  of  Higher  Education  for  the  projects  hereinafter
24    enumerated:
25                 ILLINOIS STATE UNIVERSITY - NORMAL
26    For construction of science laboratory
27      facilities ................................... $    661,772
28                    NORTHERN ILLINOIS UNIVERSITY
29    For upgrading the storm waterway controls
30      and campus drives ............................    1,030,289
31    For construction of tunnels and installation
32      of utility piping ............................       47,604
33    For renovation of heating plants and the
                            -109-               BOB-CAPITAL99
 1      HVAC system ..................................      145,230
 2               NORTHERN ILLINOIS UNIVERSITY - ROCKFORD
 3    For construction of the Rockford Center
 4      facilities ...................................       35,982
 5        Total, Section 21                              $1,920,877
 6        Section  21.1.  The sum of $2,289,030, or so much thereof
 7    as may be necessary and remains unexpended at  the  close  of
 8    business  on June 30, 1998, from a reappropriation heretofore
 9    made for such purposes in  Article 94, Section 23.1 of Public
10    Act 90-0010, is reappropriated from the  Capital  Development
11    Fund to the Capital Development Board for the Board of Higher
12    Education  for  miscellaneous capital improvements, including
13    construction, reconstruction, remodeling, improvement, repair
14    and installation of capital  facilities,  cost  of  planning,
15    supplies,   equipment,  materials,  services  and  all  other
16    expenses required for completing the the work at the colleges
17    and universities.  This appropriation shall be in addition to
18    any other appropriated amounts  which  can  be  expended  for
19    these purposes.
20        Section  21.2.  The  following  named amounts, or so much
21    thereof as may be necessary  and  remain  unexpended  at  the
22    close  of  business  on  June 30, 1998, from reappropriations
23    heretofore made for such purposes in Article 94, Section 23.2
24    of Public Act 90-0010, are reappropriated  from  the  Capital
25    Development  Fund  to  the  Capital Development Board for the
26    Board  of  Higher   Education   for   miscellaneous   capital
27    improvements,    including    construction,   reconstruction,
28    remodeling, improvements, repair and installation of  capital
29    facilities, cost of planning, supplies, equipment, materials,
30    services,  and  all  other  expenses required to complete the
31    work at the colleges and universities hereinafter enumerated.
32    This  appropriation  shall  be  in  addition  to  any   other
                            -110-               BOB-CAPITAL99
 1    appropriated   amounts   which  can  be  expended  for  these
 2    purposes:
 3    Illinois State University ...................... $     87,560
 4    Northern Illinois University ...................    1,230,379
 5        Total, Section 21.2                            $1,317,939
 6        Section 21.3.  The sum of $21,156, or so much thereof  as
 7    may  be  necessary  and  remains  unexpended  at the close of
 8    business on June 30, 1998, from a reappropriation  heretofore
 9    made  for such purposes in Article 94, Section 23.3 of Public
10    Act 90-0010, is reappropriated from the  Capital  Development
11    Fund to the Capital Development Board for the Board of Higher
12    Education for Northern Illinois University, for the planning,
13    architectural  engineering,  purchase,  site improvements and
14    construction or remodeling of a site in Rockford for use as a
15    campus.
16        Section 21.4.  The following named amounts,  or  so  much
17    thereof  as  may  be  necessary, and remain unexpended at the
18    close of business  on  June  30,  1998,  from  appropriations
19    heretofore made for such purposes in Article 94, Section 23.4
20    of  Public  Act  90-0010, are reappropriated from the Capital
21    Development Fund to the Capital  Development  Board  for  the
22    Board   of   Higher   Education   for  miscellaneous  capital
23    improvements    including    construction,    reconstruction,
24    remodeling, improvement, repair and installation  of  capital
25    facilities, cost of planning, supplies, equipment, materials,
26    services and all other expenses required to complete the work
27    at   the   various   universities   set  forth  below.   This
28    appropriation shall be in addition to any other  appropriated
29    amounts which can be expended for these purposes.
30      For Chicago State University ................. $    525,000
31      For Eastern Illinois University ..............      980,000
32      For Governors State University ...............      315,000
                            -111-               BOB-CAPITAL99
 1      For Illinois State University ................    2,030,000
 2      For Northeastern Illinois University .........      735,000
 3      For Northern Illinois University .............    2,240,000
 4      For Southern Illinois University .............    4,081,014
 5      For University of Illinois ...................   10,931,488
 6      For Western Illinois University ..............    1,505,000
 7        Total, Section 21.4                           $23,342,502
 8        Section  22.  The  following  named  amounts,  or so much
 9    thereof as may be necessary  and  remain  unexpended  at  the
10    close  of  business  on  June 30, 1998, from reappropriations
11    heretofore made for such purposes in  Article 94, Section  24
12    of  Public  Act  90-0010, are reappropriated from the Capital
13    Development Fund to the Capital  Development  Board  for  the
14    Board  of  Trustees  of  Southern Illinois University for the
15    projects hereinafter enumerated:
16                          CARBONDALE CAMPUS
17    For construction of an engineering building
18      annex ........................................ $    109,585
19    For construction of an environmental control
20      and hazardous waste management facility ......       52,426
21    For remodeling the Communications Building .....       16,901
22                         EDWARDSVILLE CAMPUS
23    For replacement of the high temperature water
24      distribution system ..........................      188,842
25    For infrastructure, site development, and
26      other necessary costs associated with
27      the development of University Park ...........       10,044
28    For costs associated with the consolidation
29      of the music facilities ......................       25,010
30    For planning and construction of an Art and
31      Design Facility ..............................       25,089
32        Total, Section 22                                $427,897
                            -112-               BOB-CAPITAL99
 1        Section 22.1.  The sum of $1,559,919, or so much  thereof
 2    as  may  be  necessary and remains unexpended at the close of
 3    business on June 30, 1998, from a reappropriation  heretofore
 4    made for such purposes in  Article 94, Section 24.1 of Public
 5    Act  90-0010,  is reappropriated from the Capital Development
 6    Fund to the Capital Development Board for  Southern  Illinois
 7    University  for  miscellaneous capital improvements including
 8    construction,   reconstruction,   remodeling,   improvements,
 9    repair  and  installation  of  capital  facilities,  cost  of
10    planning, supplies, equipment, materials, services,  and  all
11    other   expenses   required   to  complete  the  work.   This
12    appropriation shall be in addition to any other  appropriated
13    amounts which can be expended for these purposes.
14        Section  23.  The  following  named  amounts,  or so much
15    thereof as may be necessary  and  remain  unexpended  at  the
16    close  of  business  on  June 30, 1998, from reappropriations
17    heretofore made for such purposes in  Article 94, Section  25
18    of  Public  Act  90-0010, are reappropriated from the Capital
19    Development Fund to the Capital  Development  Board  for  the
20    Board  of  Trustees  of  the  University  of Illinois for the
21    projects hereinafter enumerated:
22                    UNIVERSITY CENTER - CHICAGO
23    For construction and all other costs
24      necessary for site development and
25      utilities systems extensions, upgrades and
26      modifications for a new Molecular Biology
27      Building in addition to any other amounts
28      previously appropriated ...................... $     11,654
29    For remodeling Alumni Hall, Phase II,
30      including utilities ..........................      560,186
31    For construction of an instruction and
32      research facility for the College of
33      Engineering ..................................       21,270
                            -113-               BOB-CAPITAL99
 1                        HEALTH SCIENCE CENTER
 2    For remodeling the Neuropsychiatric
 3      Institute ....................................    1,353,712
 4    For planning the upgrade of the ventilating
 5      and air conditioning systems in the
 6      Pharmacy Building ............................       23,605
 7                       URBANA-CHAMPAIGN CAMPUS
 8    For initiating a campus flood
 9      control project ..............................    1,867,692
10    For construction of a special materials
11      storage facility, including equipment ........       73,272
12        Total, Section 23                              $3,911,391
13        Section 23.1.  The sum of $6,276,708, or so much  thereof
14    as  may  be  necessary and remains unexpended at the close of
15    business on June 30, 1998, from a reappropriation  heretofore
16    made for such purposes in  Article 94, Section 25.1 of Public
17    Act  90-0010,  is reappropriated from the Capital Development
18    Fund to the  Capital  Development  Board  for  the  Board  of
19    Trustees  of  the  University  of  Illinois for miscellaneous
20    capital improvements including construction,  reconstruction,
21    remodeling,  improvement,  repair and installation of capital
22    facilities, cost of planning, supplies, equipment, materials,
23    services and all other expenses required for  completing  the
24    work  at  the  colleges and universities.  This appropriation
25    shall be in addition to any other appropriated amounts  which
26    can be expended for these purposes.
27        Section  23.2.  The  following  named  amount, or so much
28    thereof as may be necessary and  remains  unexpended  at  the
29    close  of  business  on June 30, 1998, from a reappropriation
30    heretofore made for such purposes in Article 94, Section 25.2
31    of Public Act 90-0010, is  reappropriated  from  the  General
32    Revenue  Fund  to the Capital Development Board for the Board
                            -114-               BOB-CAPITAL99
 1    of Trustees of the University of  Illinois  for  the  project
 2    hereinafter enumerated:
 3                   HEALTH SCIENCE CENTER - CHICAGO
 4    For energy conservation improvements at
 5      Taylor Street Hospital, the College of
 6      Pharmacy Building, and the Clinical
 7      Science Building ............................. $     24,780
 8        Total, Section 23.2                               $24,780
 9        Section  23.3.  The sum of $4,500,000, or so much thereof
10    as may be necessary and remains unexpended at  the  close  of
11    business  on June 30, 1998, from a reappropriation heretofore
12    made for such purposes in Article 94, Section 9 of Public Act
13    90-0010, is reappropriated from the Capital Development  Fund
14    to the Capital Development Board for the Board of Trustees of
15    the  University  of  Illinois (formerly for the Department of
16    Human Services) for renovation of the ISPI building.
17        Section 24.  The following  named  amounts,  or  so  much
18    thereof  as  may  be  necessary, and remain unexpended at the
19    close of business on June 30, 1998,  from  appropriation  and
20    reappropriations heretofore made for such purposes in Article
21    94, Sections 22A, 22.3, 24.2, and 25.3 of Public Act 90-0010,
22    are  reappropriated  from the Capital Development Fund to the
23    following Universities (formerly to the  Capital  Development
24    Board  for  the  Universities)  for  the projects hereinafter
25    enumerated:
26    (From Article 94, Section 22.3 of Public Act 90-0010)
27                     EASTERN ILLINOIS UNIVERSITY
28    For purchasing Buzzard Building equipment ......       37,854
29    (From Article 94, Section 22A of Public Act 90-0010)
30                 ILLINOIS STATE UNIVERSITY - NORMAL
31    For purchasing equipment for
32      the Science Laboratory building ..............    1,534,723
                            -115-               BOB-CAPITAL99
 1    (From Article 94, Section 22A of Public Act 90-0010)
 2             NORTHEASTERN ILLINOIS UNIVERSITY - CHICAGO
 3    For purchasing equipment
 4      for the Fine Arts Complex ....................    4,000,000
 5    (From Article 94, Section 22.3 of Public Act 90-0010)
 6                    NORTHERN ILLINOIS UNIVERSITY
 7    For purchasing Engineering
 8      Building equipment ...........................       65,525
 9    (From Article 94, Section 24.2 of Public Act 90-0010)
10              SOUTHERN ILLINOIS UNIVERSITY - CARBONDALE
11    For purchasing Bio-Science building
12      equipment ....................................       38,836
13    (From Article 94, Section 25.3 of Public Act 90-0010)
14              UNIVERSITY OF ILLINOIS - URBANA-CHAMPAIGN
15    For purchasing equipment for Temple
16      Hoyne Buell Hall .............................      154,413
17        Total, Section 24                              $5,831,351
18        Section  25.  In  addition  to  any  amounts   heretofore
19    appropriated for such purposes, the sum of $4,576, or so much
20    thereof  as  may  be  necessary and remains unexpended at the
21    close of business on June 30, 1998,  from  a  reappropriation
22    heretofore  made  for such purposes in Article 94, Section 26
23    of Public Act 90-0010, is  reappropriated  from  the  Capital
24    Development  Fund  to  the  Secretary  of State for planning,
25    remodeling, relocation, permanent equipment,  and  any  other
26    related  expenses,  including  architectural  and engineering
27    fees associated with construction and  remodeling  of  office
28    space  and  other support areas under the jurisdiction of the
29    House of Representatives, and to various legislative services
30    agencies in both the Capitol and Stratton Office Buildings.
31        Section  26.  In  addition  to  any  amounts   heretofore
32    appropriated for such purposes, the sum of $4,802, or so much
                            -116-               BOB-CAPITAL99
 1    thereof  as  may  be  necessary and remains unexpended at the
 2    close of business on June 30,  1998  from  a  reappropriation
 3    heretofore  made  for such purposes in Article 94, Section 27
 4    of Public Act 90-0010, is  reappropriated  from  the  Capital
 5    Development  Fund to the Space Needs Commission for planning,
 6    remodeling, relocation, permanent equipment,  and  any  other
 7    related  expenses,  including  architectural  and engineering
 8    fees  associated  with  construction   of   a   non-sectarian
 9    meditation room in the Capitol Office Building.
10        Section   27.  No  contract  shall  be  entered  into  or
11    obligation incurred for any expenditures from  appropriations
12    made  in  this  Article  until after the purposes and amounts
13    have been approved in writing by the Governor.
14                              ARTICLE 3
15        Division  A.  The  reappropriations  in   this   Division
16    continue certain appropriations initially made for the fiscal
17    year  beginning  July  1, 1996, for the purposes of the Build
18    Illinois Program as set forth below.
19        Section 5.  The sum of $1,000,000, or so much thereof  as
20    may  be  necessary  and  remains unexpended on June 30, 1998,
21    from appropriations heretofore  made  for  such  purposes  in
22    Section   5   of   Public   Act   90-0010,   Article  95,  is
23    reappropriated to the Department of  Natural  Resources  from
24    the  Build Illinois Bond Fund for expenditure by the Division
25    of Water Resources for  infrastructure  improvements  to  the
26    Wood Dale/Itasca Reservoir.
27        Section  7.  The  sum  of $406,824, or so much thereof as
28    may be necessary and remains unexpended on June 30, 1998 from
29    appropriations made for such purposes in Section 7 of  Public
                            -117-               BOB-CAPITAL99
 1    Act  90-0010, Article 95, is reappropriated to the Department
 2    of Natural Resources from the Build Illinois  Bond  Fund  for
 3    expenditure   by   the   Division   of  Water  Resources  for
 4    infrastructure  repairs  of  the  Batavia  Dam  in   Batavia,
 5    Illinois.
 6        Section  8.  The  sum  of $250,000, or so much thereof as
 7    may be necessary and remains unexpended  on  June  30,  1998,
 8    from  appropriations  heretofore  made  for  such purposes in
 9    Section  8  of   Public   Act   90-0010,   Article   95,   is
10    reappropriated   to   the   Illinois  Department  of  Natural
11    Resources from the Build Illinois Bond Fund for  access  road
12    improvements at Eagle Creek State Park.
13        Section  14.  The  sum  of $60,000, or so much thereof as
14    may be necessary and remains unexpended  on  June  30,  1998,
15    from  appropriations  heretofore  made  for  such purposes in
16    Section  14  of  Public   Act   90-0010,   Article   95,   is
17    reappropriated  to  the  Environmental Protection Agency from
18    the Build Illinois Bond Fund for a grant to  the  Village  of
19    Pecatonica for a water tower.
20        Section  15.  The  sum of $379,384, or so much thereof as
21    may be necessary and remains unexpended  on  June  30,  1998,
22    from  appropriations  heretofore  made  for  such purposes in
23    Section  15  of  Public   Act   90-0010,   Article   95,   is
24    reappropriated  to  the  Environmental Protection Agency from
25    the Build Illinois Bond Fund for a grant to  the  Village  of
26    Maple Park for infrastructure improvements.
27        Section  16.  The  sum of $200,000, or so much thereof as
28    may be necessary and remains unexpended  on  June  30,  1998,
29    from  the appropriations heretofore made for such purposes in
30    Section  16  of  Public   Act   90-0010,   Article   95,   is
                            -118-               BOB-CAPITAL99
 1    reappropriated  to  the  Environmental Protection Agency from
 2    the Build Illinois Bond Fund for a grant to  the  Village  of
 3    Homer for infrastructure improvements.
 4        Section  21.  The  sum of $250,000, or so much thereof as
 5    may be necessary and remains unexpended  on  June  30,  1998,
 6    from  appropriations  heretofore  made  for  such purposes in
 7    Section  21  of  Public   Act   90-0010,   Article   95,   is
 8    reappropriated  from  the  Build  Illinois  Bond  Fund to the
 9    Department of Natural Resources  for  rehabilitation  of  the
10    concession  building  and  other park improvements at Johnson
11    Sauk Trail State Park in Henry County.
12        Section 32.  The sum of $1,500,000, or so much thereof as
13    may be necessary and remains unexpended  on  June  30,  1998,
14    from  appropriations  heretofore  made  for  such purposes in
15    Section  32  of  Public   Act   90-0010,   Article   95,   is
16    reappropriated  from  the  Build  Illinois  Bond  Fund to the
17    Department of Natural Resources for all costs associated with
18    flood control projects for the DuPage County Forest  Preserve
19    District.
20        Section 33.  The sum of $1,000,000, or so much thereof as
21    may  be  necessary  and  remains unexpended on June 30, 1998,
22    from appropriations heretofore  made  for  such  purposes  in
23    Section   33   of   Public   Act   90-0010,  Article  95,  is
24    reappropriated from the  Build  Illinois  Bond  Fund  to  the
25    Capital  Development  Board  for the state match for planning
26    for construction of the  Ag  Library  at  the  University  of
27    Illinois.
28        Section  34.  The  sum of $150,000, or so much thereof as
29    may be necessary and remains unexpended  on  June  30,  1998,
30    from  appropriations  heretofore  made  for  such purposes in
                            -119-               BOB-CAPITAL99
 1    Section  34  of  Public   Act   90-0010,   Article   95,   is
 2    reappropriated  from  the  Build  Illinois  Bond  Fund to the
 3    Illinois  Environmental  Protection  Agency  for  all   costs
 4    associated  with  waste  water  and  drinking  water  systems
 5    development and improvements in the Village of LaGrange Park.
 6        Section 36.  The sum of $1,100,000, or so much thereof as
 7    may  be  necessary  and  remains unexpended on June 30, 1998,
 8    from appropriations heretofore  made  for  such  purposes  in
 9    Section   36   of   Public   Act   90-0010,  Article  95,  is
10    reappropriated from the  Build  Illinois  Bond  Fund  to  the
11    Illinois  Environmental  Protection Agency for a grant to the
12    Fox River Water Reclamation District for improvements for the
13    South Plant, the Skyline  Treatment  Plant  and  the  Skyline
14    Water Plant.
15        Division   B.  The   reappropriation   in  this  Division
16    continues an appropriation initially made for the fiscal year
17    beginning July 1, 1997, for the purpose of the Build Illinois
18    Program as set forth below:
19        Section 32.  The sum of $2,000,000, or so much thereof as
20    may be necessary and remains unexpended  on  June  30,  1998,
21    from  an  appropriation  heretofore  made for such purpose in
22    Section 32 of Public Act 90-0550, is  reappropriated  to  the
23    Capital  Development  Board from the Build Illinois Bond Fund
24    to plan for a medical school replacement at the University of
25    Illinois at Chicago.
26        Division  II.  The  reappropriations  in  this   Division
27    continue certain appropriations initially made for the fiscal
28    year  beginning  July  1,  1995, for the purpose of the Build
29    Illinois program set forth below.
                            -120-               BOB-CAPITAL99
 1        Section 1-2.  The amount of $450,000, or so much  thereof
 2    as  may be necessary and remains unexpended on June 30, 1998,
 3    from appropriations heretofore  made  for  such  purposes  in
 4    Article   95,   Section   1-2   of  Public  Act  90-0010,  is
 5    reappropriated from the  Build  Illinois  Bond  Fund  to  the
 6    Department  of  Natural  Resources  for a grant to the DuPage
 7    County Forest Preserve District for dredging the  Salt  Creek
 8    at the Fullersburg Dam.
 9        Section  1-9.  The amount of $500,000, or so much thereof
10    as may be necessary and remains unexpended on June 30,  1998,
11    from  appropriations  heretofore  made  for  such purposes in
12    Article  95,  Section  1-9  of   Public   Act   90-0010,   is
13    reappropriated  from  the  Build  Illinois  Bond  Fund to the
14    Environmental Protection Agency for a grant to the Fox  River
15    Water  Reclamation  District  for  improvements for the South
16    Plant, the Skyline Treatment  Plant  and  the  Skyline  Water
17    Plant.
18        Section 1-10.  The amount of $500,000, or so much thereof
19    as  may be necessary and remains unexpended on June 30, 1998,
20    from appropriations heretofore  made  for  such  purposes  in
21    Article   95,   Section   1-10  of  Public  Act  90-0010,  is
22    reappropriated from the  Build  Illinois  Bond  Fund  to  the
23    Department of Natural Resources for phase one construction of
24    a  Visitors'  Center at Kline Creek Farms in conjunction with
25    the DuPage County Forest Preserve District
26        Division  III.  The  reappropriations  in  this  Division
27    continue certain appropriations initially made for the fiscal
28    year beginning July 1, 1990, for the purposes  of  the  Build
29    Illinois Program as set forth below.
30        Section  2-6.  The  following  named  amounts, or so much
                            -121-               BOB-CAPITAL99
 1    thereof as may be necessary, and remain  unexpended  on  June
 2    30,   1998  from  appropriations  heretofore  made  for  such
 3    purposes in Article 95, Section 2-6 of  Public  Act  90-0010,
 4    are  reappropriated  from the Build Illinois Bond Fund to the
 5    Capital Development Board for the Board of  Higher  Education
 6    for the projects hereinafter enumerated:
 7                NORTHERN ILLINOIS UNIVERSITY - DEKALB
 8    To construct and equip the Engineering
 9      Building ..................................... $    149,355
10    To purchase equipment and complete
11      construction for Faraday Hall Addition .......      190,678
12        Total, Build Illinois Bond Fund                  $340,033
13        Section  2-7.  The  following  named  amounts, or so much
14    thereof as may be necessary, and remain  unexpended  on  June
15    30,   1998  from  appropriations  heretofore  made  for  such
16    purposes in Article 95, Section 2-7 of  Public  Act  90-0010,
17    are  reappropriated  from the Build Illinois Bond Fund to the
18    Capital Development Board for  Southern  Illinois  University
19    for the projects hereinafter enumerated:
20              SOUTHERN ILLINOIS UNIVERSITY - CARBONDALE
21    To construct an addition and remodel the
22      existing Steam Plant ......................... $    262,345
23    To construct and equip the Biological
24      Sciences Facilities ..........................      849,444
25        Total, Build Illinois Bond Fund                $1,111,789
26        Section  2-8.  The  following  named  amounts, or so much
27    thereof as may be necessary, and remain  unexpended  on  June
28    30,   1998  from  appropriations  heretofore  made  for  such
29    purposes in Article 95, Section 2-8 of  Public  Act  90-0010,
30    are  reappropriated  from the Build Illinois Bond Fund to the
31    Capital Development Board for the University of Illinois  for
32    the projects hereinafter enumerated:
                            -122-               BOB-CAPITAL99
 1               UNIVERSITY OF ILLINOIS URBANA-CHAMPAIGN
 2    To construct and equip the Chemical and Life
 3      Sciences Building ............................$     252,522
 4        Section  2-19B.  The  following  named amount, or so much
 5    thereof as may be necessary and remain unexpended on June 30,
 6    1998 from appropriations heretofore made for such purposes in
 7    Article  95,  Section  2-19B  of  Public  Act   90-0010,   is
 8    reappropriated  from  the  Build  Illinois  Bond  Fund to the
 9    Capital Development Board for the Board of  Higher  Education
10    for the project hereinafter enumerated:
11             NORTHEASTERN ILLINOIS UNIVERSITY - CHICAGO
12    For repair of exterior masonry walls
13      and replacement of the roof on the
14      Science Building ..............................$    286,004
15        Section  2-20.1.  The following named amounts, or so much
16    thereof as may be necessary, and remain  unexpended  on  June
17    30,   1998  from  appropriations  heretofore  made  for  such
18    purposes in Article 95, Section 2-20.1 of Public Act 90-0010,
19    are reappropriated from the Build Illinois Bond Fund  to  the
20    Capital  Development  Board for the Board of Higher Education
21    for the projects hereinafter enumerated:
22               NORTHERN ILLINOIS UNIVERSITY - DE KALB
23    For construction of the Engineering Building
24      including extension of utilities, in
25      addition to funds previously appropriated
26      for such purpose ...............................$    86,716
27        Section 2-21A.  The following named amounts, or  so  much
28    thereof  as  may  be necessary, and remain unexpended on June
29    30,  1998  from  appropriations  heretofore  made  for   such
30    purposes  in Article 95, Section 2-21A of Public Act 90-0010,
31    are reappropriated from the Build Illinois Bond Fund  to  the
                            -123-               BOB-CAPITAL99
 1    Capital  Development  Board  for Southern Illinois University
 2    for the projects hereinafter enumerated:
 3              SOUTHERN ILLINOIS UNIVERSITY - CARBONDALE
 4    For construction and all other costs
 5      necessary for an addition and remodeling
 6      of the existing steam plant, in addition to
 7      funds previously appropriated for such
 8      purpose .......................................$    245,423
 9        Division  IV.  The  reappropriations  in  this   Division
10    continue certain appropriations initially made for the fiscal
11    year  beginning  July  1,  1989, for the purpose of the Build
12    Illinois Program set forth below.
13        Section 3-1.2a.  The amount of  $1,000,000,  or  so  much
14    thereof  as  may  be necessary and remains unexpended on June
15    30,  1998,  from  appropriations  heretofore  made  for  such
16    purposes in Article 95, Section 3-1.2a of Public Act 90-0010,
17    is reappropriated from the Build Illinois  Purposes  Fund  to
18    the  Department  of  Commerce and Community Affairs for loans
19    and grants to units of local  government  for  infrastructure
20    improvements.
21        Section  3-1.3.  The  following named amounts, or so much
22    thereof as may be necessary and remain unexpended on June 30,
23    1998, from appropriations heretofore made for  such  purposes
24    in  Article  95,  Section  3-1.3  of  Public Act 90-0010, are
25    reappropriated from the  Build  Illinois  Bond  Fund  to  the
26    Department    of   Transportation   for   land   acquisition,
27    engineering,   and   contract   costs    for    construction,
28    reconstruction, extension, and improvement of State highways.
29        FAP 412 (U.S. 51)............................$    389,507
30        Section 3-1.12b.  The following named amounts, or so much
                            -124-               BOB-CAPITAL99
 1    thereof  as  may  be necessary, and remain unexpended on June
 2    30,  1998  from  appropriations  heretofore  made  for   such
 3    purposes  in  Article  95,  Section  3-1.12b  of  Public  Act
 4    90-0010, are reappropriated from the Build Illinois Bond Fund
 5    to  the  Capital  Development  Board  for the Board of Higher
 6    Education for the projects hereinafter enumerated:
 7               NORTHERN ILLINOIS UNIVERSITY - DE KALB
 8    To construct an addition to Faraday Hall ........$    757,625
 9        Section 3-1.13.  The following named amounts, or so  much
10    thereof  as  may  be necessary, and remain unexpended on June
11    30,  1998  from  appropriations  heretofore  made  for   such
12    purposes in Article 95, Section 3-1.13 of Public Act 90-0010,
13    are  reappropriated  from the Build Illinois Bond Fund to the
14    Capital Development Board for University of Illinois for  the
15    project hereinafter enumerated:
16                   UNIVERSITY OF ILLINOIS - URBANA
17    To remodel Noyes Laboratory ......................$    43,853
18        Section  3-6.2a.  The  amount  of  $500,000,  or  so much
19    thereof as may be necessary and remains  unexpended  on  June
20    30,  1998,  from  appropriations  heretofore  made  for  such
21    purposes in Section 3-6.2a of Public Act 90-0010, Article 95,
22    is  reappropriated  from  the Build Illinois Purposes Fund to
23    the Department of Commerce and Community Affairs for a  grant
24    to  the  City  of Chicago for infrastructure improvements and
25    large equipment purchase  at  the  Crawford  Industrial  Park
26    located at 47th Street and Pulaski Road.
27        Section  3-6.2e.  The  amount  of  $20,400,  or  so  much
28    thereof  as  may  be necessary and remains unexpended on June
29    30,  1998,  from  appropriations  heretofore  made  for  such
30    purposes in Section 3-6.2e of Public Act 90-0010, Article 95,
31    is reappropriated from the Build Illinois Bond  Fund  to  the
                            -125-               BOB-CAPITAL99
 1    Secretary  of  State for making grants to the City of Chicago
 2    for planning, construction,  reconstruction,  rehabilitation,
 3    and  all  necessary  costs  for the following branches of the
 4    Chicago Public Library at the  approximate  costs  set  forth
 5    below:
 6        North Austin Branch Library ................  $ 1,150,025
 7        Legler Library .............................       26,886
 8        Auburn/Hamilton Park Library ...............      879,056
 9        Near West Side Branch Library ..............    1,136,419
10        Carter G. Woodson Regional Library .........       68,696
11        Clearing Branch Library ....................      258,398
12        McKinley Park Branch Library ...............      829,124
13        South Chicago Branch Library ...............      551,657
14        North Pulaski/Humboldt Library .............    2,753,474
15        Roosevelt Branch ...........................      204,000
16        Rockwell Gardens Reading &
17          Study Center .............................            0
18        Pullman Branch Library .....................      632,063
19        Total                                          $8,489,798
20        Section  3-6.2h.  The  amount  of  $63,340,  or  so  much
21    thereof  as  may  be necessary and remains unexpended on June
22    30,  1998,  from  appropriations  heretofore  made  for  such
23    purposes in Section 3-6.2h of Public Act 90-0010, Article 95,
24    is reappropriated from the Build Illinois Bond  Fund  to  the
25    Department  of Natural Resources for grants to units of local
26    governments as provided in the "Open Space Lands  Acquisition
27    and Development Act."
28        Division   V.  The   reappropriations  in  this  Division
29    continue certain appropriations initially made for the fiscal
30    year beginning July 1, 1988, for the purposes  of  the  Build
31    Illinois Program set forth below.
                            -126-               BOB-CAPITAL99
 1        Section  4-1.4.  The  amount  of  $104,000,  or  so  much
 2    thereof  as  may  be necessary and remains unexpended on June
 3    30,  1998,  from  appropriations  heretofore  made  for  such
 4    purposes in Section 4-1.4 of Public Act 90-0010, Article  95,
 5    is  reappropriated  from  the Build Illinois Purposes Fund to
 6    the Department of Commerce and Community  Affairs  for  loans
 7    and  grants  to  units of local government for infrastructure
 8    improvements.
 9        Section 4-1.11.  The following named amounts, or so  much
10    thereof as may be necessary and remain unexpended on June 30,
11    1998,  from  appropriations heretofore made for such purposes
12    in Section 4-1.11 of Public  Act  90-0010,  Article  95,  are
13    reappropriated  from  the  Build  Illinois  Bond  Fund to the
14    Department   of   Transportation   for   land    acquisition,
15    engineering,    and    contract   costs   for   construction,
16    reconstruction, extension, and improvement of State highways,
17    including  bridges,  structures   separating   highways   and
18    railroads,  rest areas, interchanges, and access roads to and
19    from any State or local highway and such other  necessary  or
20    appropriate  purposes  as  provided  by the "Illinois Highway
21    Code" as follows:
22        FAP 412 (U.S. 51)........................... $    170,839
23        Access roads and interchanges ..............    1,093,282
24        Total                                          $1,264,121
25        Section 4-1.13.  The  amount  of  $617,613,  or  so  much
26    thereof  as  may  be necessary and remains unexpended on June
27    30,  1998,  from  appropriations  heretofore  made  for  such
28    purposes in Section 4-1.13 of Public Act 90-0010, Article 95,
29    is reappropriated from the Build Illinois Bond  Fund  to  the
30    Department of Natural Resources for the following projects at
31    the approximate costs set forth below:
32    Des   Plaines   Watershed  Mitigation  -  Cook,
                            -127-               BOB-CAPITAL99
 1        DuPage,   and   Lake   Counties    -    For
 2        implementation  of  flood hazard mitigation
 3        plans, developed in cooperation with  units
 4        of  local  government  in  the  Des Plaines
 5        Watershed, filed in accordance with Section
 6        5 of the Flood  Control  Act  of  1945,  as
 7        amended  (Ill.  Rev.  Stat.,  Ch.  19, par.
 8        126e) .....................................  $    100,000
 9    Indian Creek - Kane County - For implementation
10        of the Indian Creek flood  control  project
11        in Kane County in cooperation with the City
12        of Aurora .................................        48,089
13    Midlothian Creek - Cook County - Improvement of
14        Midlothian  Creek  channel to provide flood
15        damage reduction for Fernway Subdivision in
16        cooperation with  the  Villages  of  Orland
17        Park and Tinley Park ......................       469,524
18        Total                                            $617,613
19        Division   VI.  The  reappropriations  in  this  Division
20    continue certain appropriations initially made for the fiscal
21    year beginning July 1, 1987, for the purposes  of  the  Build
22    Illinois Program set forth below.
23        Section  5-1.10.  The  amount  of  $90,789,  or  so  much
24    thereof  as  may  be necessary and remains unexpended on June
25    30,  1998,  from  appropriations  heretofore  made  for  such
26    purposes in Section 5-1.10 of Public Act 90-0010, Article 95,
27    is reappropriated from the Build Illinois  Purposes  Fund  to
28    the  Department  of  Commerce and Community Affairs for loans
29    and grants to units of local  government  for  infrastructure
30    improvements.
31        Section  5-1.11.  The  amount  of  $116,044,  or  so much
                            -128-               BOB-CAPITAL99
 1    thereof as may be necessary and remains  unexpended  on  June
 2    30,  1998,  from  appropriations  heretofore  made  for  such
 3    purposes in Section 5-1.11 of Public Act 90-0010, Article 95,
 4    is  reappropriated  from  the Build Illinois Purposes Fund to
 5    the Department of Commerce and Community Affairs  for  grants
 6    and  loans to establish and operate small business incubators
 7    under the Small Business Incubator Program.
 8        Section 5-1.16.  The following named amounts, or so  much
 9    thereof as may be necessary and remain unexpended on June 30,
10    1998,  from  appropriations heretofore made for such purposes
11    in Section 5-1.16 of Public  Act  90-0010,  Article  95,  are
12    reappropriated  from  the  Build  Illinois  Bond  Fund to the
13    Department   of   Transportation   for   land    acquisition,
14    engineering    and    contract    costs   for   construction,
15    reconstruction, extension and improvement of state  highways,
16    including   bridges,   structures   separating  highways  and
17    railroads, rest areas, interchanges, and access roads to  and
18    from  any  state or local highway and such other necessary or
19    appropriate purposes as provided  by  the  "Illinois  Highway
20    Code" as follows:
21        Access roads, interchanges, and
22          rest areas....................................$ 426,953
23        Division  VII.  The  Reappropriations  in  this  Division
24    continue certain appropriations initially made for the fiscal
25    year  beginning  July  1, 1986, for the purposes of the Build
26    Illinois Program set forth below.
27        Section 6-1.13.  The  amount  of  $144,887,  or  so  much
28    thereof  as  may  be necessary and remains unexpended on June
29    30,  1998,  from  appropriations  heretofore  made  for  such
30    purposes in Section 6-1.13 of Public Act 90-0010, Article 95,
31    is reappropriated from the Build Illinois Bond  Fund  to  the
                            -129-               BOB-CAPITAL99
 1    Environmental Protection Agency for making grants to units of
 2    local  government  for  the  planning,  design, construction,
 3    rehabilitation and any other necessary costs  for  wastewater
 4    treatment  facilities  and  for plans, construction, repairs,
 5    improvements and any other  necessary  costs  for  sewer  and
 6    water supply systems.
 7        Section  6-1.16.  The following named amounts, or so much
 8    thereof as may be necessary and remain unexpended on June 30,
 9    1998, from appropriations heretofore made for  such  purposes
10    in  Section  6-1.16  of  Public  Act 90-0010, Article 95, are
11    reappropriated from the  Build  Illinois  Bond  Fund  to  the
12    Department    of   Transportation   for   land   acquisition,
13    engineering   and   contract    costs    for    construction,
14    reconstruction,  extension and improvement of state highways,
15    including  bridges,  structures   separating   highways   and
16    railroads,  rest areas, interchanges, and access roads to and
17    from any state or local highway and such other  necessary  or
18    appropriate  purposes  as  provided  by the "Illinois Highway
19    Code" as follows:
20        FAP 412 (U.S. 51) ...........................$    293,775
21        Section  6-1.21.  The  amount  of  $20,058,  or  so  much
22    thereof as may be necessary and remains  unexpended  on  June
23    30,  1998,  from  appropriations  heretofore  made  for  such
24    purposes in Section 6-1.21 of Public Act 90-0010, Article 95,
25    is  reappropriated  from  the Build Illinois Bond Fund to the
26    Department of Natural Resources  for  costs  associated  with
27    drainage, flood control and related improvements.
28        Section  6-2.7.  The  amount  of  $425,000,  or  so  much
29    thereof  as  may  be necessary and remains unexpended on June
30    30,  1998,  from  appropriations  heretofore  made  for  such
31    purposes in Section 6-2.7 of Public Act 90-0010, Article  95,
                            -130-               BOB-CAPITAL99
 1    is  reappropriated  from  the Build Illinois Bond Fund to the
 2    Environmental  Protection  Agency  for   the   planning   and
 3    improvement of a water system in Edinburg.
 4        Section 6-2.8.  The amount of $50,000, or so much thereof
 5    as  may be necessary and remains unexpended on June 30, 1998,
 6    from appropriations heretofore  made  for  such  purposes  in
 7    Section   6-2.8   of  Public  Act  90-0010,  Article  95,  is
 8    reappropriated from the  Build  Illinois  Bond  Fund  to  the
 9    Environmental   Protection   Agency   for  the  planning  and
10    construction of a waterworks components system in the Village
11    of Elburn.
12        Section 6-2.14.  The  amount  of  $100,000,  or  so  much
13    thereof  as  may  be necessary and remains unexpended on June
14    30,  1998,  from  appropriations  heretofore  made  for  such
15    purposes in Section 6-2.14 of Public Act 90-0010, Article 95,
16    is reappropriated from the Build Illinois Bond  Fund  to  the
17    Environmental  Protection  Agency  for  planning,  design and
18    construction of Crystal Lake sewer.
19        Section 6-2.25.  The  amount  of  $310,000,  or  so  much
20    thereof  as  may  be necessary and remains unexpended on June
21    30,  1998,  from  appropriations  heretofore  made  for  such
22    purposes in Section 6-2.25 of Public Act 90-0010, Article 95,
23    is reappropriated from the Build Illinois Bond  Fund  to  the
24    Environmental   Protection   Agency   for   a  grant  to  the
25    Brookfield-North  Riverside  Water  Commission,  serving  the
26    towns of Brookfield, North Riverside, La Grange  Park,  Lyons
27    and Riverside for water supply system improvements.
28        Section  6-2.27.  The  amount  of  $136,000,  or  so much
29    thereof as may be necessary and remains  unexpended  on  June
30    30,  1998,  from  appropriations  heretofore  made  for  such
                            -131-               BOB-CAPITAL99
 1    purposes in Section 6-2.27 of Public Act 90-0010, Article 95,
 2    is  reappropriated  from  the Build Illinois Bond Fund to the
 3    Department of Natural Resources for the design,  construction
 4    and  land  acquisition  of  a retention basin in East Chicago
 5    Heights.
 6        Section  6-3.22.  The  amount  of  $50,000,  or  so  much
 7    thereof as may be necessary and remains  unexpended  on  June
 8    30,  1998,  from  appropriations  heretofore  made  for  such
 9    purposes in Section 6-3.22 of Public Act 90-0010, Article 95,
10    is  reappropriated  from  the Build Illinois Bond Fund to the
11    Department of Natural Resources for the purpose of a grant to
12    the  Rockford  Park  District  for   land   acquisition   and
13    development  of  a park near the Illinois Central train depot
14    in downtown Rockford.
15        Section 6-3.32.  The  amount  of  $140,000,  or  so  much
16    thereof  as  may  be necessary and remains unexpended on June
17    30,  1998,  from  appropriations  heretofore  made  for  such
18    purposes in Section 6-3.32 of Public Act 90-0010, Article 95,
19    is reappropriated from the Build Illinois Bond  Fund  to  the
20    Department  of Commerce and Community Affairs for the purpose
21    of a grant to the City of Elgin for extension of sewer  lines
22    to the Northeast Subarea.
23        Section  6-4.3.  The  amount  of  $175,000,  or  so  much
24    thereof  as  may  be necessary and remains unexpended on June
25    30,  1998,  from  appropriations  heretofore  made  for  such
26    purposes in Section 6-4.3 of Public Act 90-0010, Article  95,
27    is  reappropriated  from  the Build Illinois Bond Fund to the
28    Department of Commerce and Community Affairs  for  grants  to
29    local   governments   for   use   in   economic  development,
30    revitalization and community development at  the  approximate
31    costs as set forth below:
                            -132-               BOB-CAPITAL99
 1        Melrose..................................... $     50,000
 2        Franklin Park...............................       50,000
 3        Hillside....................................       75,000
 4        Total                                            $175,000
 5        Section 6-4.4.  The amount of $49,500, or so much thereof
 6    as  may be necessary and remains unexpended on June 30, 1998,
 7    from appropriations heretofore  made  for  such  purposes  in
 8    Section   6-4.4   of  Public  Act  90-0010,  Article  95,  is
 9    reappropriated from the Build Illinois Purposes Fund  to  the
10    Department  of Transportation for a grant to Canteen Township
11    in St. Clair County for road repairs.
12        Section  6-4.8.  The  amount  of  $198,000,  or  so  much
13    thereof as may be necessary and remains  unexpended  on  June
14    30,  1998,  from  appropriations  heretofore  made  for  such
15    purposes  in Section 6-4.8 of Public Act 90-0010, Article 95,
16    is reappropriated from the Build Illinois  Purposes  Fund  to
17    the  Department  of  Natural Resources for a recreational and
18    flood control project and retention  basin  in  the  City  of
19    Sycamore.
20        Section  6-4.18.  The  amount  of  $99,000,  or  so  much
21    thereof  as  may  be necessary and remains unexpended on June
22    30,  1998,  from  appropriations  heretofore  made  for  such
23    purposes in Section 6-4.18 of Public Act 90-0010, Article 95,
24    is reappropriated from the Build Illinois  Purposes  Fund  to
25    the  Department  of Transportation for a grant to the Village
26    of Swansea to resurface local roads and  repair  and  replace
27    gutters and curbs.
28        Section  6-4.28.  The  amount  of  $49,500,  or  so  much
29    thereof  as  may  be necessary and remains unexpended on June
30    30,  1998,  from  appropriations  heretofore  made  for  such
                            -133-               BOB-CAPITAL99
 1    purposes in Section 6-4.28 of Public Act 90-0010, Article 95,
 2    is reappropriated from the Build Illinois  Purposes  Fund  to
 3    the Department of Transportation for a study to determine the
 4    feasibility of establishing an airport in Kankakee County.
 5        Section  6-4.33.  The  amount  of  $91,802,  or  so  much
 6    thereof  as  may  be necessary and remains unexpended on June
 7    30,  1998,  from  appropriations  heretofore  made  for  such
 8    purposes in Section 6-4.33 of Public Act 90-0010, Article 95,
 9    is reappropriated from the Build Illinois Bond  Fund  to  the
10    Department  of  Transportation  for the costs associated with
11    construction,  reconstruction  and  rehabilitation  of  Eagle
12    Creek Road and Findlay Road.
13        Section  6-5.24.  The  amount  of  $25,000,  or  so  much
14    thereof as may be necessary and remains  unexpended  on  June
15    30,  1998,  from  appropriations  heretofore  made  for  such
16    purposes in Section 6-5.24 of Public Act 90-0010, Article 95,
17    is  reappropriated  from  the Build Illinois Bond Fund to the
18    Department of Natural Resources for a grant to  the  City  of
19    Benld for recreation and park facilities.
20        Section  6-5.39.  The  amount  of  $127,000,  or  so much
21    thereof as may be necessary and remains  unexpended  on  June
22    30,  1998,  from  appropriations  heretofore  made  for  such
23    purposes in Section 6-5.39 of Public Act 90-0010, Article 95,
24    is  reappropriated  from  the Build Illinois Bond Fund to the
25    Department of Natural Resources for the Village of Midlothian
26    for flood control and drainage improvements.
27        Section 6-5.44a.  The  amount  of  $72,412,  or  so  much
28    thereof  as  may  be necessary and remains unexpended on June
29    30,  1998,  from  appropriations  heretofore  made  for  such
30    purposes in Section 6-5.44a of Public  Act  90-0010,  Article
                            -134-               BOB-CAPITAL99
 1    95,  is  reappropriated  from the Build Illinois Bond Fund to
 2    the Environmental Protection Agency for grants  to  units  of
 3    local  government  for  the  planning,  design, construction,
 4    rehabilitation, repair, improvement, expansion, and any other
 5    necessary costs for storm water, sewer, sewage treatment  and
 6    water  supply  systems,  at  the  approximate  cost set forth
 7    below:
 8        La Grange Highlands Sanitary District.........$    72,412
 9        Section 6-5.44b.  The  amount  of  $40,000,  or  so  much
10    thereof  as  may  be necessary and remains unexpended on June
11    30,  1998,  from  appropriations  heretofore  made  for  such
12    purposes in Section 6-5.44b of Public  Act  90-0010,  Article
13    95,  is  reappropriated  from the Build Illinois Bond Fund to
14    the Department  of  Natural  Resources  for  units  of  local
15    government  for  storm  drainage  at the approximate cost set
16    forth below:
17        Bonnie .......................................$    40,000
18        Section 6-5.44f.  The amount  of  $300,000,  or  so  much
19    thereof  as  may  be necessary and remains unexpended on June
20    30,  1998,  from  appropriations  heretofore  made  for  such
21    purposes in Section 6-5.44f of Public  Act  90-0010,  Article
22    95,  is  reappropriated  from the Build Illinois Bond Fund to
23    the Department of  Natural  Resources  for  a  grant  to  the
24    Village  of Summit for planning, design, construction and any
25    other necessary costs for flood control.
26        Section 6-6.6.  The amount  of  $3,000,000,  or  so  much
27    thereof  as  may  be necessary and remains unexpended on June
28    30,  1998,  from  appropriations  heretofore  made  for  such
29    purposes in Section 6-6.6 of Public Act 90-0010, Article  95,
30    is  reappropriated  from  the Build Illinois Purposes Fund to
31    the Illinois Community College Board for the City Colleges of
                            -135-               BOB-CAPITAL99
 1    Chicago for costs associated with planning,  utilities,  site
 2    improvements,    repairs,    renovation,    remodeling,   and
 3    construction of Job Training Centers.
 4        Section 6-6.10.  The amount of  $1,334,768,  or  so  much
 5    thereof  as  may  be necessary and remains unexpended on June
 6    30,  1998,  from  appropriations  heretofore  made  for  such
 7    purposes in Section 6-6.10 of Public Act 90-0010, Article 95,
 8    is reappropriated from the Build Illinois Bond  Fund  to  the
 9    Department  of  Transportation  for  a  grant  to the City of
10    Chicago for the viaduct and roadway improvement program.
11        Section 6-6.14.  The amount of  $1,227,028,  or  so  much
12    thereof  as  may  be necessary and remains unexpended on June
13    30,  1998,  from  appropriations  heretofore  made  for  such
14    purposes in Section 6-6.14 of Public Act 90-0010, Article 95,
15    is reappropriated to the Department  of  Transportation  from
16    the  Build  Illinois  Bond  Fund for the paving, upgrading or
17    construction:
18        (a)  of streets and  curbs  at  the  following  locations
19    within the City of Chicago:
20        1.  The 4300 block of West Wrightwood;
21        2.  The 3600 block of West Byron;
22        3.  The 3200 block of West Waveland;
23        4.  The 4200 block of North Hamlin;
24        5.  The 4200 block of West Grace;
25        6.  The 4200 block of North Springfield;
26        7.  The 3200 block of North Lawndale;
27        8.  East 117th from Avenue O to Avenue H;
28        9.  Avenue N from 131st to 132nd;
29        10.  State Line Road from 106th to 112th;
30        11.  Princeton Street from 30th Street to 31st Street;
31        12.  South Wells from 27th Street through 29th Street;
32        13.  23rd Place from Princeton to Wentworth;
                            -136-               BOB-CAPITAL99
 1        14.  Sayre Avenue between Higgins and Kennedy Expressway;
 2        15.  Keystone Avenue from North Avenue to Armitage
 3             Avenue;
 4        16.  Harding Avenue from North Avenue to Armitage Avenue;
 5        17.  Lawndale Avenue from North Avenue to Armitage
 6             Avenue; and
 7        18.  The 1300 block of Monticello Avenue.
 8        (b)  of curbs at the following locations within
 9             the City of Chicago:
10        1.  The 3000 and 3100 blocks of North Elbridge Street;
11        2.  The 2800, 2900 and 3000 blocks of West
12            Fletcher Street;
13        3.  The 2800, 2900 and 3000 blocks of West
14            Wellington Street;
15        4.  The 2800, 2900 and 3000 blocks of West
16            Nelson Street;
17        5.  The 5600 and 5700 blocks of West Henderson;
18        6.  The 5600 and 5700 blocks of West Cornelia;
19        7.  The 3300 block of North Major;
20        8.  The 3300, 3400 and 3500 blocks of North Linder;
21        9.  The 3300 and 3500 blocks of North Lockwood;
22        10.  The 2000, 2100 and 2200 blocks of Leland Avenue;
23        11.  The 2000, 2100, 2200 and 2300 blocks of Giddings;
24        12.  The 6100 block of North Artesian;
25        13.  The 4400 block of North Francisco;
26        14.  The 2500 block of West Hollywood;
27        15.  The 6100 block of North Rockwell;
28        16.  The 2400 block of West Winona;
29        17.  The 2300 block of West Superior;
30        18.  The 2000, 2100 and 2200 blocks of West Thomas;
31        19.  The 2200 block of West Cortez;
32        20.  The 2000 and 2100 blocks of West Iowa;
33        21.  The 1200 block of North Noble;
34        22.  The 700 block of North Campbell;
                            -137-               BOB-CAPITAL99
 1        23.  The 5600, 5700 and 5800 blocks of Kostner
 2             from Bryn Mawr to Rodgers;
 3        24.  North Kostner from Hollywood to Rodgers;
 4        25.  North Kedvale from Leland to Lawrence;
 5        26.  Leland from Kedvale to Kildare;
 6        27.  Leland from Kimball to Pulaski;
 7        28.  Monticello from Wilson to Lawrence;
 8        29.  St. Louis from Wilson to Lawrence;
 9        30.  Bernard from Leland to Lawrence;
10        31.  Kasson from Kennicott to Keystone;
11        32.  West Ainslie from Kimball to Bernard;
12        33.  The west side of the 1800 block of North Austin;
13        34.  The west side of the 2300 block of North Austin;
14        35.  The 3000 and 3100 blocks of North Marmora;
15        36.  The north side of the 7100 block of West Cornelia;
16        37.  The 5600 block of West Barry;
17        38.  The east side of the 3000 block of Norragansett;
18        39.  The 6100 block of Diversey;
19        40.  The west side of the 2500 block of Neva;
20        41.  The 3300 and 3400 blocks of Neva;
21        42.  The 6200 and 6300 blocks of West Barry;
22        43.  The 6600 block of West Barry;
23        44.  The west side of the 3100 block of North Mobile;
24        45.  The south side of 17th Street from Ashland to
25             Paulina;
26        46.  17th Street from Paulina to Damen;
27        47.  3600 to 3800 block of Cumberland;
28        48.  Sacramento Avenue from Addison to Cornelia;
29        49.  Cornelia Avenue from Sacramento to Albany;
30        50.  The 8300, 8400 and 8500 blocks of South
31             Francisco Avenue;
32        51.  The 8300, 8400 and 8500 blocks of South
33             Whipple Avenue;
34        52.  82nd Street from Western Avenue to California
                            -138-               BOB-CAPITAL99
 1             Avenue;
 2        53.  85th Street from Kenneth Avenue to Cicero Avenue;
 3        54.  The 8500, 8600 and 8700 blocks of South Ramsey Road;
 4        55.  The 4300, 4400, 4500, 4600 and 4700 blocks of South
 5             Normal Avenue;
 6        56.  The 3500, 3600, 3700 and 3800 blocks of South
 7            Lituanica Avenue;
 8        57.  Eleanor Street from Throop to Loomis Avenue; and
 9        58.  Pershing Road from Wentworth to Wood.
10        Section  6-6.18.  The  amount  of  $350,000,  or  so much
11    thereof as may be necessary and remains  unexpended  on  June
12    30,  1998,  from  appropriations  heretofore  made  for  such
13    purposes in Section 6-6.18 of Public Act 90-0010, Article 95,
14    is  reappropriated  from  the Build Illinois Bond Fund to the
15    Environmental Protection Agency for a grant  to  the  Central
16    Stickney Sanitary District of Cook County for improvements to
17    the sewer system and the water system.
18        Section  6-6.19.  The  amount  of  $559,250,  or  so much
19    thereof as may be necessary and remains  unexpended  on  June
20    30,  1998,  from  appropriations  heretofore  made  for  such
21    purposes in Section 6-6.19 of Public Act 90-0010, Article 95,
22    is  reappropriated  from  the Build Illinois Bond Fund to the
23    Department of Natural Resources for the Chicago Park District
24    for the reconstruction of the pier at 64th Street in  Jackson
25    Park.
26        Section  6-6.20.  The  amount  of  $250,000,  or  so much
27    thereof as may be necessary and remains  unexpended  on  June
28    30,  1998,  from  appropriations  heretofore  made  for  such
29    purposes in Section 6-6.20 of Public Act 90-0010, Article 95,
30    is  reappropriated  from  the Build Illinois Bond Fund to the
31    Department of Transportation for  a  grant  to  the  City  of
                            -139-               BOB-CAPITAL99
 1    Chicago for the preliminary engineering for road improvements
 2    on St. Louis Avenue, from 51st Street to 59th Street.
 3        Section  6-6.21.  The  amount  of  $50,000,  or  so  much
 4    thereof  as  may  be necessary and remains unexpended on June
 5    30,  1998,  from  appropriations  heretofore  made  for  such
 6    purposes in Section 6-6.21 of Public Act 90-0010, Article 95,
 7    is reappropriated from the Build Illinois Bond  Fund  to  the
 8    Department  of  Transportation  to study the straightening of
 9    Ogden Avenue, from First Street to Harlem Avenue.
10        Section 6-6.22.  The  amount  of  $500,000,  or  so  much
11    thereof  as  may  be necessary and remains unexpended on June
12    30,  1998,  from  appropriations  heretofore  made  for  such
13    purposes in Section 6-6.22 of Public Act 90-0010, Article 95,
14    is reappropriated from the Build Illinois Bond  Fund  to  the
15    Department  of  Transportation  for  a  grant  to the City of
16    Chicago for the repair and replacement of  roadway  curbs  in
17    the  area  bounded by Cicero Avenue, Central Avenue, Armitage
18    Avenue and Diversey Avenue, and the area bounded  by  Central
19    Avenue, Austin Avenue, Fullerton Avenue, and Grand Avenue.
20        Section  6-6.23.  The  amount  of  $500,000,  or  so much
21    thereof as may be necessary and remains  unexpended  on  June
22    30,  1998,  from  appropriations  heretofore  made  for  such
23    purposes in Section 6-6.23 of Public Act 90-0010, Article 95,
24    is  reappropriated  from  the Build Illinois Bond Fund to the
25    Department of Transportation for  a  grant  to  the  City  of
26    Chicago for the following roadway resurfacing improvements:
27             Francisco St. - 5100 S. to 5500 S.
28             Francisco St. - 5700 S. to 5900 S.
29             Mozart St. - 5100 S. to 5900 S.
30             54th Place - 3000 W. to 3200 W.
31             Carpenter St. - 3230 S. to 3400 S.
                            -140-               BOB-CAPITAL99
 1             Wood St. - Stevenson Expressway to 3900 S.
 2             Keeley St. - Archer Ave. to 3100 S.
 3        Section  6-6.24.  The  amount  of  $450,000,  or  so much
 4    thereof as may be necessary and remains  unexpended  on  June
 5    30,  1998,  from  appropriations  heretofore  made  for  such
 6    purposes in Section 6-6.24 of Public Act 90-0010, Article 95,
 7    is  reappropriated  from  the Build Illinois Bond Fund to the
 8    Department of Transportation for  a  grant  to  the  City  of
 9    Chicago for the following roadway resurfacing improvements:
10             For Drake Ave. - 1600 N. to 2400 N.
11             Hamlin Ave. - 2000 N. to 2200 N.
12             Dickens Ave. - 3200 W. to 4000 W.
13             Belden Ave. - 3200 W. to 3600 W.
14             Medill Ave. - 3400 W. to 3600 W.
15             Avers Ave. - 2000 N. to 2200 N.
16        Section  6-6.25.  The  amount  of  $558,719,  or  so much
17    thereof as may be necessary and remains  unexpended  on  June
18    30,  1998,  from  appropriations  heretofore  made  for  such
19    purposes in Section 6-6.25 of Public Act 90-0010, Article 95,
20    is  reappropriated  from  the Build Illinois Bond Fund to the
21    Department of Transportation for  a  grant  to  the  City  of
22    Chicago for roadway resurfacing improvements:
23             Farwell Ave. - Ridge Ave. to Western Ave.
24             Morse Ave. - Ridge Ave. to Western Ave.
25             Greenleaf Ave. - Ridge to Western Ave.
26             Estes Ave. - Ridge Ave. to Western Ave.
27             Rosemont - Western to Kedzie
28             Leavitt - Norwood to Granville
29             Granville Ave. from Western Ave. to Kedzie
30        Division  VIII.  The  reappropriations  in  this Division
31    continue  certain  appropriations  initially  made  for   the
                            -141-               BOB-CAPITAL99
 1    purpose of the renewal of the rural areas of Illinois for the
 2    fiscal year beginning July 1, 1986.
 3        Section  7-3.1a.    The  amount  of  $295,000, or so much
 4    thereof as may be necessary and remains  unexpended  on  June
 5    30,  1998,  from  appropriations  heretofore  made  for  such
 6    purposes in Section 7-3.1a of Public Act 90-0010, Article 95,
 7    is  reappropriated  from  the Build Illinois Bond Fund to the
 8    Environmental Protection Agency for making grants to units of
 9    local government  for  the  planning,  design,  construction,
10    rehabilitation  and  any other necessary costs for wastewater
11    treatment facilities and for  plans,  construction,  repairs,
12    improvements  and  any  other  necessary  costs for sewer and
13    water supply systems, at the approximate costs as  set  forth
14    below:
15        Sims..........................................$    45,000
16        New Lenox..........................................50,000
17        Fairmont City......................................75,000
18        Washington Park....................................75,000
19        Brooklyn...........................................50,000
20        Section  7-3.1b.  The  amount  of  $50,000,  or  so  much
21    thereof  as  may  be necessary and remains unexpended on June
22    30,  1998,  from  appropriations  heretofore  made  for  such
23    purposes in Section 7-3.1b of Public Act 90-0010, Article 95,
24    is reappropriated from the Build Illinois Bond  Fund  to  the
25    Department  of  Natural  Resources  for  plans, construction,
26    repairs, improvements and any other necessary costs for storm
27    drainage, at the approximate costs set forth below:
28        East Carondelet ..............................$    50,000
29        Section 6-3.110.  The  amount  of  $70,000,  or  so  much
30    thereof  as  may  be necessary and remains unexpended on June
31    30,  1998,  from  appropriations  heretofore  made  for  such
                            -142-               BOB-CAPITAL99
 1    purposes in Section 6-3.110 of Public  Act  90-0010,  Article
 2    95,  is  reappropriated  from the Build Illinois Bond Fund to
 3    the Environmental Protection Agency  for  the  purpose  of  a
 4    grant  to the City of Bloomington for extension and expansion
 5    of sewers.
 6        Division  IX.  The  reappropriations  in  this   Division
 7    continue certain appropriations initially made for the fiscal
 8    years  beginning  July  1, 1985, for the purpose of the Build
 9    Illinois Program set forth below.
10        Section 8-1.19.  The following named amounts, or so  much
11    thereof as may be necessary and remain unexpended on June 30,
12    1998,  from  appropriations heretofore made for such purposes
13    in Section 8-1.19 of Public  Act  90-0010,  Article  95,  are
14    reappropriated  from  the  Build  Illinois  Bond  Fund to the
15    Department   of   Transportation   for   land    acquisition,
16    engineering    and    contract    costs   for   construction,
17    reconstruction, extension and improvement of State  highways,
18    including   bridges,   structures   separating  highways  and
19    railroads, rest areas, interchanges, and access roads to  and
20    from  any  State or local highway and such other necessary or
21    appropriate purposes as provided  by  the  "Illinois  Highway
22    Code" as follows:
23      Access Roads, interchanges, and rest areas......$    95,191
24        Section  8-1.21.  The  amount  of  $189,520,  or  so much
25    thereof as may be necessary and remains  unexpended  on  June
26    30,  1998,  from  appropriations  heretofore  made  for  such
27    purposes in Section 8-1.21 of Public Act 90-0010, Article 95,
28    is  reappropriated  from  the Build Illinois Bond Fund to the
29    Department of Natural Resources for  the  completion  of  the
30    following projects at the approximate costs set forth below:
31    Lower Des Plaines River at Tributaries Watershed
                            -143-               BOB-CAPITAL99
 1        -   Cook   and   DuPage   Counties   -   For
 2        construction  of  drainage,  flood  control,
 3        recreation   and  related  improvements  and
 4        facilities  in   the   Lower   Des   Plaines
 5        Watershed;    and    for    necessary   land
 6        acquisition,   relocation,    and    related
 7        expenses,  all  in  general conformance with
 8        the Lower Des Plaines River and  Tributaries
 9        Watershed  Work plan in cooperation with the
10        U.S. Soil  Conservation  Service  and  local
11        governments sponsoring this Federal
12        Flood Control project .......................$    189,520
13        Section  8-1.22.  The  amount  of  $33,311,  or  so  much
14    thereof  as  may  be necessary and remains unexpended on June
15    30,  1998,  from  appropriations  heretofore  made  for  such
16    purposes in Section 8-1.22 of Public Act 90-0010, Article 95,
17    is reappropriated from the Build Illinois Bond  Fund  to  the
18    Department  of  Natural  Resources  for costs associated with
19    drainage, flood control and related improvements.
20        Section 8-2.18.  The  amount  of  $552,048,  or  so  much
21    thereof  as  may  be necessary and remains unexpended on June
22    30,  1998,  from  appropriations  heretofore  made  for  such
23    purposes in Section 8-2.18 of Public Act 90-0010, Article 95,
24    is reappropriated from the Build Illinois Bond  Fund  to  the
25    Environmental Protection Agency for the purpose of a grant to
26    the  Village  of  Palos  Park for the design, engineering and
27    construction of sewers.
28        Section 8-2.28.  The  amount  of  $500,000,  or  so  much
29    thereof  as  may  be necessary and remains unexpended on June
30    30,  1998,  from  appropriations  heretofore  made  for  such
31    purposes in Section 8-2.28 of Public Act 90-0010, Article 95,
                            -144-               BOB-CAPITAL99
 1    is reappropriated from the Build Illinois Bond  Fund  to  the
 2    Department  of  Natural  Resources  to assist in planning and
 3    construction of a water retention project on Tyler Creek.
 4        Section  8-2.33.  The  amount  of  $50,000,  or  so  much
 5    thereof as may be necessary and remains  unexpended  on  June
 6    30,  1998,  from  appropriations  heretofore  made  for  such
 7    purposes in Section 8-2.33 of Public Act 90-0010, Article 95,
 8    is  reappropriated  from  the Build Illinois Bond Fund to the
 9    Department of Natural Resources for feasibility, engineering,
10    and economic and environmental studies on  the  LaMoine  Lake
11    Project.
12        Section  8-4.5.  The  amount  of  $500,000,  or  so  much
13    thereof  as  may  be necessary and remains unexpended on June
14    30,  1998,  from  appropriations  heretofore  made  for  such
15    purposes in Section 8-4.5 of Public Act 90-0010, Article  95,
16    is  reappropriated  from  the Build Illinois Bond Fund to the
17    Department of Commerce and Community Affairs for a  grant  to
18    the  City  of North Chicago for all costs associated with the
19    planning and construction of a building and parking  facility
20    to house a Community Cultural Art Center.
21        Section  8-4.6.  The  amount  of  $100,000,  or  so  much
22    thereof  as  may  be necessary and remains unexpended on June
23    30,  1998,  from  appropriations  heretofore  made  for  such
24    purposes in Section 8-4.6 of Public Act 90-0010, Article  95,
25    is  reappropriated  from  the Build Illinois Purposes Fund to
26    the Department of Commerce and Community Affairs for a  grant
27    to  the  Metro East Solid Waste Disposal and Energy Producing
28    Service for its ordinary and contingent expenses.
29        Section 8-5.3.  The amount  of  $2,000,000,  or  so  much
30    thereof  as  may  be necessary and remains unexpended on June
                            -145-               BOB-CAPITAL99
 1    30,  1998,  from  appropriations  heretofore  made  for  such
 2    purposes in Section 8-5.3 of Public Act 90-0010, Article  95,
 3    is  reappropriated  from  the Build Illinois Bond Fund to the
 4    Illinois Community College Board for  the  City  Colleges  of
 5    Chicago  for  costs associated with planning, utilities, site
 6    improvements,   repairs,    renovation,    remodeling,    and
 7    construction of Job Training Centers.
 8        Section  8-5.6.  The  amount  of  $588,193,  or  so  much
 9    thereof  as  may  be necessary and remains unexpended on June
10    30,  1998,  from  appropriations  heretofore  made  for  such
11    purposes in Section 8-5.6 of Public Act 90-0010, Article  95,
12    is  reappropriated  from  the Build Illinois Bond Fund to the
13    Department of Transportation  as  a  grant  to  the  City  of
14    Chicago for a viaduct and roadway improvement program.
15        Division   X.  The   reappropriations  in  this  Division
16    continue certain appropriations initially made for the fiscal
17    years beginning July 1, 1985 through 1992, combined  for  the
18    purpose of the Build Illinois Program set forth below.
19        Section  10A.  The  amount  of  $9,490,071,  or  so  much
20    thereof  as  may  be necessary and remains unexpended on June
21    30,  1998,  from  appropriations  heretofore  made  for  such
22    purposes in Section 10A of Public Act 90-0010, Article 95, is
23    reappropriated from the  Build  Illinois  Bond  Fund  to  the
24    Environmental  Protection Agency for grants to units of local
25    government  for  sewer  systems  and   wastewater   treatment
26    facilities pursuant to rules and procedures established under
27    the Anti-Pollution Bond Act.
28        Section  10B.  The  amount  of  $102,236,940,  or so much
29    thereof as may be necessary, and remains unexpended  on  June
30    30,  1998,  from  appropriations  heretofore  made  for  such
                            -146-               BOB-CAPITAL99
 1    purposes in Section 10B of Public Act 90-0010, Article 95, is
 2    reappropriated  from  the  Build  Illinois  Bond  Fund to the
 3    Environmental Protection  Agency  for  wastewater  compliance
 4    grants  to  units  of  local government for sewer systems and
 5    wastewater treatment facilities pursuant  to  procedures  and
 6    rules  established  under the Anti-Pollution Bond Act.  These
 7    grants are limited to projects for which the local government
 8    provides at least 30% of  the  project  cost.   There  is  an
 9    approved project compliance plan, and there is an enforceable
10    compliance  schedule  prior  to  the  grant award.  The grant
11    award will be based on eligible project cost contained in the
12    approved compliance plan.
13        Section 10C.  The following named  amounts,  or  so  much
14    thereof  as  may  be necessary, and remain unexpended on June
15    30,  1998  from  appropriations  heretofore  made  for   such
16    purposes  in  Article  95, Section 10C of Public Act 90-0010,
17    are reappropriated from the Build Illinois Bond Fund  to  the
18    Capital  Development  Board for the Board of Higher Education
19    for    miscellaneous    capital    improvements     including
20    construction, reconstruction, remodeling, improvement, repair
21    and  installation  of  capital facilities, costs of planning,
22    supplies,  equipment,  materials,  services,  and  all  other
23    expenses required to complete the work at  the  colleges  and
24    universities hereinafter enumerated:
25    Chicago State University ....................... $     26,515
26    Eastern Illinois University ....................       92,221
27    Western Illinois University ....................       15,152
28        Total, Build Illinois Bond Fund                  $133,888
29        Section  10D.  The  following  named  amounts, or so much
30    thereof as may be necessary, and remain  unexpended  on  June
31    30,   1998  from  appropriations  heretofore  made  for  such
32    purposes in Article 95, Section 10D of  Public  Act  90-0010,
                            -147-               BOB-CAPITAL99
 1    are  reappropriated  from the Build Illinois Bond Fund to the
 2    Capital Development Board for the Board of  Higher  Education
 3    for     miscellaneous    capital    improvements    including
 4    construction, reconstruction, remodeling, improvement, repair
 5    and installation of capital facilities,  costs  of  planning,
 6    supplies,  equipment,  materials,  services,  and  all  other
 7    expenses  required  to  complete the work at the colleges and
 8    universities hereinafter enumerated:
 9    Illinois State University ...................... $    156,023
10    Northern Illinois University ...................       80,257
11        Total, Build Illinois Bond Fund                  $236,280
12        Section  10E.  The  amount  of  $1,352,223,  or  so  much
13    thereof as may be necessary, and remains unexpended  on  June
14    30,   1998  from  appropriations  heretofore  made  for  such
15    purposes in Article 95, Section 10E of Public Act 90-0010, is
16    reappropriated from the  Build  Illinois  Bond  Fund  to  the
17    Capital  Development Board for the University of Illinois for
18    miscellaneous capital  improvements  including  construction,
19    reconstruction,    remodeling,    improvement,   repair   and
20    installation  of  capital  facilities,  costs  of   planning,
21    supplies,  equipment,  materials,  services,  and  all  other
22    expenses  required  to complete the work.  This appropriation
23    shall be in addition to any other appropriated amounts  which
24    can be expended for these purposes.
25        Section  10F.  The amount of $226,138, or so much thereof
26    as may be necessary, and remains unexpended on June 30,  1998
27    from  appropriations  heretofore  made  for  such purposes in
28    Article  95,  Section  10F  of   Public   Act   90-0010,   is
29    reappropriated  from  the  Build  Illinois  Bond  Fund to the
30    Capital Development Board for  Southern  Illinois  University
31    for     miscellaneous    capital    improvements    including
32    construction, reconstruction, remodeling, improvement, repair
                            -148-               BOB-CAPITAL99
 1    and installation of capital facilities,  costs  of  planning,
 2    supplies,  equipment,  materials,  services,  and  all  other
 3    expenses  required  to complete the work.  This appropriation
 4    shall be in addition to any other appropriated amounts  which
 5    can be expended for these purposes.
 6        Section  10G.  The  amount  of  $1,541,230,  or  so  much
 7    thereof  as  may be necessary, and remains unexpended on June
 8    30,  1998  from  appropriations  heretofore  made  for   such
 9    purposes in Article 95, Section 10G of Public Act 90-0010, is
10    reappropriated  from  the  Build  Illinois  Bond  Fund to the
11    Capital Development Board for the Illinois Community  College
12    Board  for  grants  to community colleges repair, renovation,
13    and    miscellaneous    capital    improvements     including
14    construction, reconstruction, remodeling, improvement, repair
15    and  installation  of  capital facilities, costs of planning,
16    supplies,  equipment,  materials,  services,  and  all  other
17    expenses required to complete the work.   This  appropriation
18    shall  be in addition to any other appropriated amounts which
19    can be expended for these purposes.
20        Division XI.  This Division contains provisions governing
21    the expenditure of funds appropriated in this Article.
22        Section 10-1.1.  No contract shall  be  entered  into  or
23    obligation   incurred   for   any   expenditures   from   the
24    appropriations  made in this Article until after the purposes
25    and amounts have been approved in writing by the Governor.
26                              ARTICLE 4
27        Section 99.  This Act becomes effective July 1, 1998.

[ Top ]