1 | AN ACT concerning safety.
| ||||||||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||||||||||||||||||||
3 | represented in the General Assembly:
| ||||||||||||||||||||||||
4 | Section 5. The Environmental Protection Act is amended by | ||||||||||||||||||||||||
5 | changing Section 39.14 as follows: | ||||||||||||||||||||||||
6 | (415 ILCS 5/39.14) | ||||||||||||||||||||||||
7 | Sec. 39.14. Expedited review of permits. | ||||||||||||||||||||||||
8 | (a) It is the intent of this Section to promote an | ||||||||||||||||||||||||
9 | expedited permit review process for any permit required under | ||||||||||||||||||||||||
10 | this Act. | ||||||||||||||||||||||||
11 | (b) Any applicant for a permit under this Act may request | ||||||||||||||||||||||||
12 | in writing from the Agency an expedited review of the | ||||||||||||||||||||||||
13 | application for a permit. Within a reasonable time, the Agency | ||||||||||||||||||||||||
14 | shall respond in writing, indicating whether the Agency will | ||||||||||||||||||||||||
15 | perform an expedited review. | ||||||||||||||||||||||||
16 | (c) In addition to any other fees required by this Act or | ||||||||||||||||||||||||
17 | Board regulations, an applicant requesting expedited review | ||||||||||||||||||||||||
18 | under this Section shall pay to the Agency an expedited permit | ||||||||||||||||||||||||
19 | fee. The amount of the expedited permit fee shall be 4 times | ||||||||||||||||||||||||
20 | the standard permit fee required for the requested permit under | ||||||||||||||||||||||||
21 | this Act or Board regulations; provided that the expedited | ||||||||||||||||||||||||
22 | permit fee shall not exceed $100,000. For recurring permit | ||||||||||||||||||||||||
23 | fees, such as annual fees, operating fees, or discharge fees, |
| |||||||
| |||||||
1 | the expedited permit fee shall be 4 times the amount of the | ||||||
2 | recurring fee on a one-time basis for each expedited permitting | ||||||
3 | action. If an owner or operator is not required to pay a | ||||||
4 | standard permit fee for the requested permit, the amount of the | ||||||
5 | expedited permit fee shall be mutually agreed upon by the | ||||||
6 | Agency and the applicant. Prior to any Agency review, the | ||||||
7 | applicant shall make full payment of the expedited permit fee | ||||||
8 | to the Agency. All amounts paid to the Agency pursuant to this | ||||||
9 | Section shall be deposited into the Environmental Protection | ||||||
10 | Permit and Inspection Fund. The applicant shall also pay all | ||||||
11 | standard permit fees in accordance with the applicable fee | ||||||
12 | provisions of this Act or Board regulations. | ||||||
13 | (d) The Agency's expedited review under this Section shall | ||||||
14 | include the usual and customary review by the Agency as | ||||||
15 | necessary for processing any similar application. | ||||||
16 | (e) "Expedited review" means, for the purposes of this | ||||||
17 | Section, the Agency taking action on a permit application | ||||||
18 | within a period of time mutually agreed upon by the Agency and | ||||||
19 | the applicant; provided, however, that the agreed-upon period | ||||||
20 | of time shall be tolled during any times the Agency is waiting | ||||||
21 | for the applicant or another party to provide information | ||||||
22 | necessary for the Agency to complete its expedited review. | ||||||
23 | (f) If the Agency fails to complete an expedited review | ||||||
24 | within the period of time agreed upon by the Agency and the | ||||||
25 | applicant, taking into account the tolling provided under | ||||||
26 | subsection (e) of this Section, the applicant shall be entitled |
| |||||||
| |||||||
1 | to a refund of the expedited permit fee paid under this | ||||||
2 | Section, on a prorated basis, as mutually agreed upon by the | ||||||
3 | Agency and the applicant. | ||||||
4 | (g) This Section shall not apply to applications related to | ||||||
5 | emergency events necessitating immediate action by the Agency | ||||||
6 | on permit applications. | ||||||
7 | (h) The Agency may adopt rules for the implementation of | ||||||
8 | this Section.
| ||||||
9 | (i) Upon the Agency taking action on a permit application | ||||||
10 | pursuant to this Section, the Agency shall provide the | ||||||
11 | applicant with an invoice setting forth the total fee paid | ||||||
12 | pursuant to this Section, as well as the number of overtime | ||||||
13 | hours that were expended by Agency staff in the expedited | ||||||
14 | review. | ||||||
15 | (Source: P.A. 97-95, eff. 7-12-11.)
| ||||||
16 | Section 99. Effective date. This Act takes effect upon | ||||||
17 | becoming law.
|