SB3388 EnrolledLRB096 20594 MJR 36292 b

1    AN ACT concerning regulation.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 5. The Illinois Power Agency Act is amended by
5changing Sections 1-10 and 1-20 and by adding Sections 1-77 and
61-78 as follows:
 
7    (20 ILCS 3855/1-10)
8    Sec. 1-10. Definitions.
9    "Agency" means the Illinois Power Agency.
10    "Agency loan agreement" means any agreement pursuant to
11which the Illinois Finance Authority agrees to loan the
12proceeds of revenue bonds issued with respect to a project to
13the Agency upon terms providing for loan repayment installments
14at least sufficient to pay when due all principal of, interest
15and premium, if any, on those revenue bonds, and providing for
16maintenance, insurance, and other matters in respect of the
17project.
18    "Authority" means the Illinois Finance Authority.
19    "Clean coal facility" means an electric generating
20facility that uses primarily coal as a feedstock and that
21captures and sequesters carbon dioxide emissions at the
22following levels: at least 50% of the total carbon dioxide
23emissions that the facility would otherwise emit if, at the

 

 

SB3388 Enrolled- 2 -LRB096 20594 MJR 36292 b

1time construction commences, the facility is scheduled to
2commence operation before 2016, at least 70% of the total
3carbon dioxide emissions that the facility would otherwise emit
4if, at the time construction commences, the facility is
5scheduled to commence operation during 2016 or 2017, and at
6least 90% of the total carbon dioxide emissions that the
7facility would otherwise emit if, at the time construction
8commences, the facility is scheduled to commence operation
9after 2017. The power block of the clean coal facility shall
10not exceed allowable emission rates for sulfur dioxide,
11nitrogen oxides, carbon monoxide, particulates and mercury for
12a natural gas-fired combined-cycle facility the same size as
13and in the same location as the clean coal facility at the time
14the clean coal facility obtains an approved air permit. All
15coal used by a clean coal facility shall have high volatile
16bituminous rank and greater than 1.7 pounds of sulfur per
17million btu content, unless the clean coal facility does not
18use gasification technology and was operating as a conventional
19coal-fired electric generating facility on June 1, 2009 (the
20effective date of Public Act 95-1027).
21    "Clean coal SNG brownfield facility" means a facility that
22(1) has commenced construction by July 1, 2014 on an urban
23brownfield site in a municipality with at least 1,000,000
24residents; (2) uses a gasification process to produce
25substitute natural gas; (3) uses coal as at least 50% of the
26total feedstock over the term of any sourcing agreement with a

 

 

SB3388 Enrolled- 3 -LRB096 20594 MJR 36292 b

1utility and the remainder of the feedstock may be either
2petroleum coke or coal, with all such coal having a high
3bituminous rank and greater than 1.7 pounds of sulfur per
4million Btu content; and (4) captures and sequesters at least
585% of the total carbon dioxide emissions that the facility
6would otherwise emit.
7    "Clean coal SNG facility" means a facility that uses a
8gasification process to produce substitute natural gas, that
9sequesters at least 90% of the total carbon dioxide emissions
10that the facility would otherwise emit and that uses petroleum
11coke or coal as a feedstock, with all such coal having a high
12bituminous rank and greater than 1.7 pounds of sulfur per
13million btu content; provided, however, a clean coal SNG
14brownfield facility shall not be a clean coal SNG facility.
15    "Commission" means the Illinois Commerce Commission.
16    "Costs incurred in connection with the development and
17construction of a facility" means:
18        (1) the cost of acquisition of all real property,
19    fixtures, and improvements in connection therewith and
20    equipment, personal property, and other property, rights,
21    and easements acquired that are deemed necessary for the
22    operation and maintenance of the facility;
23        (2) financing costs with respect to bonds, notes, and
24    other evidences of indebtedness of the Agency;
25        (3) all origination, commitment, utilization,
26    facility, placement, underwriting, syndication, credit

 

 

SB3388 Enrolled- 4 -LRB096 20594 MJR 36292 b

1    enhancement, and rating agency fees;
2        (4) engineering, design, procurement, consulting,
3    legal, accounting, title insurance, survey, appraisal,
4    escrow, trustee, collateral agency, interest rate hedging,
5    interest rate swap, capitalized interest, contingency, as
6    required by lenders, and other financing costs, and other
7    expenses for professional services; and
8        (5) the costs of plans, specifications, site study and
9    investigation, installation, surveys, other Agency costs
10    and estimates of costs, and other expenses necessary or
11    incidental to determining the feasibility of any project,
12    together with such other expenses as may be necessary or
13    incidental to the financing, insuring, acquisition, and
14    construction of a specific project and starting up,
15    commissioning, and placing that project in operation.
16    "Department" means the Department of Commerce and Economic
17Opportunity.
18    "Director" means the Director of the Illinois Power Agency.
19    "Demand-response" means measures that decrease peak
20electricity demand or shift demand from peak to off-peak
21periods.
22    "Energy efficiency" means measures that reduce the amount
23of electricity or natural gas required to achieve a given end
24use.
25    "Electric utility" has the same definition as found in
26Section 16-102 of the Public Utilities Act.

 

 

SB3388 Enrolled- 5 -LRB096 20594 MJR 36292 b

1    "Facility" means an electric generating unit or a
2co-generating unit that produces electricity along with
3related equipment necessary to connect the facility to an
4electric transmission or distribution system.
5    "Governmental aggregator" means one or more units of local
6government that individually or collectively procure
7electricity to serve residential retail electrical loads
8located within its or their jurisdiction.
9    "Local government" means a unit of local government as
10defined in Article VII of Section 1 of the Illinois
11Constitution.
12    "Municipality" means a city, village, or incorporated
13town.
14    "Person" means any natural person, firm, partnership,
15corporation, either domestic or foreign, company, association,
16limited liability company, joint stock company, or association
17and includes any trustee, receiver, assignee, or personal
18representative thereof.
19    "Project" means the planning, bidding, and construction of
20a facility.
21    "Public utility" has the same definition as found in
22Section 3-105 of the Public Utilities Act.
23    "Real property" means any interest in land together with
24all structures, fixtures, and improvements thereon, including
25lands under water and riparian rights, any easements,
26covenants, licenses, leases, rights-of-way, uses, and other

 

 

SB3388 Enrolled- 6 -LRB096 20594 MJR 36292 b

1interests, together with any liens, judgments, mortgages, or
2other claims or security interests related to real property.
3    "Renewable energy credit" means a tradable credit that
4represents the environmental attributes of a certain amount of
5energy produced from a renewable energy resource.
6    "Renewable energy resources" includes energy and its
7associated renewable energy credit or renewable energy credits
8from wind, solar thermal energy, photovoltaic cells and panels,
9biodiesel, crops and untreated and unadulterated organic waste
10biomass, tree waste, hydropower that does not involve new
11construction or significant expansion of hydropower dams, and
12other alternative sources of environmentally preferable
13energy. For purposes of this Act, landfill gas produced in the
14State is considered a renewable energy resource. "Renewable
15energy resources" does not include the incineration or burning
16of tires, garbage, general household, institutional, and
17commercial waste, industrial lunchroom or office waste,
18landscape waste other than tree waste, railroad crossties,
19utility poles, or construction or demolition debris, other than
20untreated and unadulterated waste wood.
21    "Revenue bond" means any bond, note, or other evidence of
22indebtedness issued by the Authority, the principal and
23interest of which is payable solely from revenues or income
24derived from any project or activity of the Agency.
25    "Sequester" means permanent storage of carbon dioxide by
26injecting it into a saline aquifer, a depleted gas reservoir,

 

 

SB3388 Enrolled- 7 -LRB096 20594 MJR 36292 b

1or an oil reservoir, directly or through an enhanced oil
2recovery process that may involve intermediate storage,
3regardless of whether these activities are conducted by a clean
4coal facility, clean coal SNG facility, clean coal SNG
5brownfield facility, or a party with which a clean coal
6facility, clean coal SNG facility, or clean coal SNG brownfield
7facility has contracted for such purposes in a salt dome.
8    "Sourcing Servicing agreement" means (i) in the case of an
9electric utility, an agreement between the owner of a clean
10coal facility and such electric utility, which agreement shall
11have terms and conditions meeting the requirements of paragraph
12(3) of subsection (d) of Section 1-75, and (ii) in the case of
13an alternative retail electric supplier, an agreement between
14the owner of a clean coal facility and such alternative retail
15electric supplier, which agreement shall have terms and
16conditions meeting the requirements of Section 16-115(d)(5) of
17the Public Utilities Act, and (iii) in case of a gas utility,
18an agreement between the owner of a clean coal SNG brownfield
19facility and the gas utility, which agreement shall have the
20terms and conditions meeting the requirements of subsection
21(h-1) of Section 9-220 of the Public Utilities Act.
22    "Substitute natural gas" or "SNG" means a gas manufactured
23by gasification of hydrocarbon feedstock, which is
24substantially interchangeable in use and distribution with
25conventional natural gas.
26    "Total resource cost test" or "TRC test" means a standard

 

 

SB3388 Enrolled- 8 -LRB096 20594 MJR 36292 b

1that is met if, for an investment in energy efficiency or
2demand-response measures, the benefit-cost ratio is greater
3than one. The benefit-cost ratio is the ratio of the net
4present value of the total benefits of the program to the net
5present value of the total costs as calculated over the
6lifetime of the measures. A total resource cost test compares
7the sum of avoided electric utility costs, representing the
8benefits that accrue to the system and the participant in the
9delivery of those efficiency measures, as well as other
10quantifiable societal benefits, including avoided natural gas
11utility costs, to the sum of all incremental costs of end-use
12measures that are implemented due to the program (including
13both utility and participant contributions), plus costs to
14administer, deliver, and evaluate each demand-side program, to
15quantify the net savings obtained by substituting the
16demand-side program for supply resources. In calculating
17avoided costs of power and energy that an electric utility
18would otherwise have had to acquire, reasonable estimates shall
19be included of financial costs likely to be imposed by future
20regulations and legislation on emissions of greenhouse gases.
21(Source: P.A. 95-481, eff. 8-28-07; 95-913, eff. 1-1-09;
2295-1027, eff. 6-1-09; 96-33, eff. 7-10-09; 96-159, eff.
238-10-09; 96-784, eff. 8-28-09; 96-1000, eff. 7-2-10.)
 
24    (20 ILCS 3855/1-20)
25    Sec. 1-20. General powers of the Agency.

 

 

SB3388 Enrolled- 9 -LRB096 20594 MJR 36292 b

1    (a) The Agency is authorized to do each of the following:
2        (1) Develop electricity procurement plans to ensure
3    adequate, reliable, affordable, efficient, and
4    environmentally sustainable electric service at the lowest
5    total cost over time, taking into account any benefits of
6    price stability, for electric utilities that on December
7    31, 2005 provided electric service to at least 100,000
8    customers in Illinois. The procurement plans shall be
9    updated on an annual basis and shall include electricity
10    generated from renewable resources sufficient to achieve
11    the standards specified in this Act.
12        (2) Conduct competitive procurement processes to
13    procure the supply resources identified in the procurement
14    plan, pursuant to Section 16-111.5 of the Public Utilities
15    Act.
16        (3) Develop electric generation and co-generation
17    facilities that use indigenous coal or renewable
18    resources, or both, financed with bonds issued by the
19    Illinois Finance Authority.
20        (4) Supply electricity from the Agency's facilities at
21    cost to one or more of the following: municipal electric
22    systems, governmental aggregators, or rural electric
23    cooperatives in Illinois.
24    (b) Except as otherwise limited by this Act, the Agency has
25all of the powers necessary or convenient to carry out the
26purposes and provisions of this Act, including without

 

 

SB3388 Enrolled- 10 -LRB096 20594 MJR 36292 b

1limitation, each of the following:
2        (1) To have a corporate seal, and to alter that seal at
3    pleasure, and to use it by causing it or a facsimile to be
4    affixed or impressed or reproduced in any other manner.
5        (2) To use the services of the Illinois Finance
6    Authority necessary to carry out the Agency's purposes.
7        (3) To negotiate and enter into loan agreements and
8    other agreements with the Illinois Finance Authority.
9        (4) To obtain and employ personnel and hire consultants
10    that are necessary to fulfill the Agency's purposes, and to
11    make expenditures for that purpose within the
12    appropriations for that purpose.
13        (5) To purchase, receive, take by grant, gift, devise,
14    bequest, or otherwise, lease, or otherwise acquire, own,
15    hold, improve, employ, use, and otherwise deal in and with,
16    real or personal property whether tangible or intangible,
17    or any interest therein, within the State.
18        (6) To acquire real or personal property, whether
19    tangible or intangible, including without limitation
20    property rights, interests in property, franchises,
21    obligations, contracts, and debt and equity securities,
22    and to do so by the exercise of the power of eminent domain
23    in accordance with Section 1-21; except that any real
24    property acquired by the exercise of the power of eminent
25    domain must be located within the State.
26        (7) To sell, convey, lease, exchange, transfer,

 

 

SB3388 Enrolled- 11 -LRB096 20594 MJR 36292 b

1    abandon, or otherwise dispose of, or mortgage, pledge, or
2    create a security interest in, any of its assets,
3    properties, or any interest therein, wherever situated.
4        (8) To purchase, take, receive, subscribe for, or
5    otherwise acquire, hold, make a tender offer for, vote,
6    employ, sell, lend, lease, exchange, transfer, or
7    otherwise dispose of, mortgage, pledge, or grant a security
8    interest in, use, and otherwise deal in and with, bonds and
9    other obligations, shares, or other securities (or
10    interests therein) issued by others, whether engaged in a
11    similar or different business or activity.
12        (9) To make and execute agreements, contracts, and
13    other instruments necessary or convenient in the exercise
14    of the powers and functions of the Agency under this Act,
15    including contracts with any person, local government,
16    State agency, or other entity; and all State agencies and
17    all local governments are authorized to enter into and do
18    all things necessary to perform any such agreement,
19    contract, or other instrument with the Agency. No such
20    agreement, contract, or other instrument shall exceed 40
21    years.
22        (10) To lend money, invest and reinvest its funds in
23    accordance with the Public Funds Investment Act, and take
24    and hold real and personal property as security for the
25    payment of funds loaned or invested.
26        (11) To borrow money at such rate or rates of interest

 

 

SB3388 Enrolled- 12 -LRB096 20594 MJR 36292 b

1    as the Agency may determine, issue its notes, bonds, or
2    other obligations to evidence that indebtedness, and
3    secure any of its obligations by mortgage or pledge of its
4    real or personal property, machinery, equipment,
5    structures, fixtures, inventories, revenues, grants, and
6    other funds as provided or any interest therein, wherever
7    situated.
8        (12) To enter into agreements with the Illinois Finance
9    Authority to issue bonds whether or not the income
10    therefrom is exempt from federal taxation.
11        (13) To procure insurance against any loss in
12    connection with its properties or operations in such amount
13    or amounts and from such insurers, including the federal
14    government, as it may deem necessary or desirable, and to
15    pay any premiums therefor.
16        (14) To negotiate and enter into agreements with
17    trustees or receivers appointed by United States
18    bankruptcy courts or federal district courts or in other
19    proceedings involving adjustment of debts and authorize
20    proceedings involving adjustment of debts and authorize
21    legal counsel for the Agency to appear in any such
22    proceedings.
23        (15) To file a petition under Chapter 9 of Title 11 of
24    the United States Bankruptcy Code or take other similar
25    action for the adjustment of its debts.
26        (16) To enter into management agreements for the

 

 

SB3388 Enrolled- 13 -LRB096 20594 MJR 36292 b

1    operation of any of the property or facilities owned by the
2    Agency.
3        (17) To enter into an agreement to transfer and to
4    transfer any land, facilities, fixtures, or equipment of
5    the Agency to one or more municipal electric systems,
6    governmental aggregators, or rural electric agencies or
7    cooperatives, for such consideration and upon such terms as
8    the Agency may determine to be in the best interest of the
9    citizens of Illinois.
10        (18) To enter upon any lands and within any building
11    whenever in its judgment it may be necessary for the
12    purpose of making surveys and examinations to accomplish
13    any purpose authorized by this Act.
14        (19) To maintain an office or offices at such place or
15    places in the State as it may determine.
16        (20) To request information, and to make any inquiry,
17    investigation, survey, or study that the Agency may deem
18    necessary to enable it effectively to carry out the
19    provisions of this Act.
20        (21) To accept and expend appropriations.
21        (22) To engage in any activity or operation that is
22    incidental to and in furtherance of efficient operation to
23    accomplish the Agency's purposes.
24        (23) To adopt, revise, amend, and repeal rules with
25    respect to its operations, properties, and facilities as
26    may be necessary or convenient to carry out the purposes of

 

 

SB3388 Enrolled- 14 -LRB096 20594 MJR 36292 b

1    this Act, subject to the provisions of the Illinois
2    Administrative Procedure Act and Sections 1-22 and 1-35 of
3    this Act.
4        (24) To establish and collect charges and fees as
5    described in this Act.
6        (25) To conduct competitive gasification feedstock
7    procurement processes to procure the feedstocks for the
8    clean coal SNG brownfield facility in accordance with the
9    requirements of Section 1-78 of this Act To manage
10    procurement of substitute natural gas from a facility that
11    meets the criteria specified in subsection (a) of Section
12    1-58 of this Act, on terms and conditions that may be
13    approved by the Agency pursuant to subsection (d) of
14    Section 1-58 of this Act, to support the operations of
15    State agencies and local governments that agree to such
16    terms and conditions. This procurement process is not
17    subject to the Procurement Code.
18        (26) To review, revise, and approve sourcing
19    agreements and mediate and resolve disputes between gas
20    utilities and the clean coal SNG brownfield facility
21    pursuant to subsection (h-1) of Section 9-220 of the Public
22    Utilities Act.
23(Source: P.A. 95-481, eff. 8-28-07; 96-784, eff. 8-28-09;
2496-1000, eff. 7-2-10.)
 
25    (20 ILCS 3855/1-77 new)

 

 

SB3388 Enrolled- 15 -LRB096 20594 MJR 36292 b

1    Sec. 1-77. The Planning and Procurement Bureau; feedstock
2procurement administrator; qualified expert or expert
3consulting firm.
4    (a) The Planning and Procurement Bureau shall at least
5every 5 years beginning in 2015 develop feedstock procurement
6plans and conduct competitive feedstock procurement processes
7in accordance with the requirements of Section 1-78 of this
8Act.
9        (1) The Agency shall at least every 5 years beginning
10    in 2015 issue a request for qualifications for experts or
11    expert consulting firms to develop the feedstock
12    procurement plans in accordance with Section 1-78 of this
13    Act. In order to qualify, an expert or expert consulting
14    firm must have:
15            (A) direct previous experience assembling large
16        scale feedstock supply plans or portfolios for
17        industrial customers;
18            (B) an advanced degree in economics, mathematics,
19        engineering, risk management, or a related area of
20        study;
21            (C) ten years of experience in the energy sector,
22        including managing supply risk;
23            (D) expertise in wholesale feedstock markets,
24        which may be particularized to the specific type of
25        feedstock to be purchased in that procurement event;
26            (E) expertise in credit protocols and familiarity

 

 

SB3388 Enrolled- 16 -LRB096 20594 MJR 36292 b

1        with contract protocols;
2            (F) adequate resources to perform and fulfill the
3        required functions and responsibilities; and
4            (G) the absence of a conflict of interest and
5        inappropriate bias for or against potential bidders or
6        the affected clean coal SNG brownfield facility.
7        (2) The Agency shall at least every 5 years beginning
8    in 2015 issue a request for qualifications for a feedstock
9    procurement administrator to conduct the competitive
10    feedstock procurement processes in accordance with Section
11    1-78 of this Act. In order to qualify, an expert or expert
12    consulting firm must have:
13            (A) direct previous experience administering a
14        large scale competitive feedstock procurement process;
15            (B) an advanced degree in economics, mathematics,
16        engineering, or a related area of study;
17            (C) ten years of experience in the energy sector,
18        including risk management experience;
19            (D) expertise in wholesale feedstock market rules,
20        which may be particularized to the specific type of
21        feedstock to be purchased in that procurement event;
22            (E) expertise in credit and contract protocols;
23            (F) adequate resources to perform and fulfill the
24        required functions and responsibilities; and
25            (G) the absence of a conflict of interest and
26        inappropriate bias for or against potential bidders or

 

 

SB3388 Enrolled- 17 -LRB096 20594 MJR 36292 b

1        the affected clean coal SNG brownfield facility.
2        (3) The Agency shall provide the clean coal SNG
3    brownfield facility and other interested parties with the
4    lists of qualified experts or expert consulting firms
5    identified through the request for qualifications
6    processes that are under consideration to develop the
7    feedstock procurement plans and to serve as the feedstock
8    procurement administrator. The Agency shall also provide
9    the clean coal SNG brownfield facility and other interested
10    parties with each qualified expert's or expert consulting
11    firm's response to the request for qualifications. All
12    information provided under this subparagraph (3) shall
13    also be provided to the Commission. The Agency may provide
14    by rule for fees associated with supplying the information
15    to the clean coal SNG brownfield facility and other
16    interested parties. The clean coal SNG brownfield facility
17    and other interested parties must, within 5 business days
18    after receiving the lists and information, notify the
19    Agency in writing if they object to any experts or expert
20    consulting firms on the lists. Objections shall be based
21    on:
22            (A) failure to satisfy qualification criteria;
23            (B) identification of a conflict of interest; or
24            (C) evidence of inappropriate bias for or against
25        potential bidders or the clean coal SNG brownfield
26        facility.

 

 

SB3388 Enrolled- 18 -LRB096 20594 MJR 36292 b

1        The Agency shall remove an expert or expert consulting
2    firm from the list within 10 days if there is a reasonable
3    basis for an objection and provide the updated list to the
4    clean coal SNG brownfield facility and other interested
5    parties. If the Agency fails to remove an expert or expert
6    consulting firm from a list, then an objecting party may
7    seek review by the Commission within 5 days thereafter by
8    filing a petition, and the Commission shall render a ruling
9    on the petition within 10 days after the filing. There is
10    no right of appeal of the Commission's ruling.
11        (4) The Agency shall, as needed, issue requests for
12    proposals to the qualified experts or expert consulting
13    firms to develop a feedstock procurement plan for the clean
14    coal SNG brownfield facility and to serve as feedstock
15    procurement administrator.
16        (5) The Agency shall select an expert or expert
17    consulting firm to develop feedstock procurement plans
18    based on the proposals submitted and shall award one-year
19    contracts to those selected with an option for the Agency
20    for a one-year renewal.
21        (6) The Agency shall select, with the approval of the
22    Commission, an expert or expert consulting firm to serve as
23    feedstock procurement administrator based on the proposals
24    submitted. If the Commission rejects the Agency's
25    selection within 5 days after being notified of the
26    Agency's selection, then the Agency shall submit another

 

 

SB3388 Enrolled- 19 -LRB096 20594 MJR 36292 b

1    recommendation within 3 days after the Commission's
2    rejection based on the proposals submitted. The Agency
3    shall award at least a one-year contract to the expert or
4    expert consulting firm selected with the Commission's
5    approval with an option for the Agency for renewal for a
6    term equal to the term of the contract.
7    (b) The experts or expert consulting firms retained by the
8Agency shall, as appropriate, prepare feedstock procurement
9plans and conduct a competitive feedstock procurement process
10as prescribed in Section 1-78 of this Act to ensure adequate,
11reliable, affordable feedstocks, taking into account any
12benefits of price stability, for the clean coal SNG brownfield
13facility.
14    (c) The draft procurement plans are subject to public
15comment pursuant to Section 1-78 of this Act.
16    (d) The Agency shall assess fees to each bidder to recover
17the costs incurred in connection with the competitive
18procurement process.
 
19    (20 ILCS 3855/1-78 new)
20    Sec. 1-78. Feedstock procurement plan; feedstock
21procurement process.
22    (a) A feedstock procurement plan shall at least every 5
23years beginning in 2015 be prepared for the clean coal SNG
24brownfield facility based on the clean coal SNG brownfield
25facility's projection of feedstock usage and ratios, and

 

 

SB3388 Enrolled- 20 -LRB096 20594 MJR 36292 b

1consistent with the applicable requirements of the Public
2Utilities Act and this Act. The plan shall specifically
3identify the wholesale feedstock products to be procured
4following plan approval and shall follow all the requirements
5set forth in this Act, the Public Utilities Act, and all
6applicable State and federal laws, statutes, rules, or
7regulations, as well as Commission orders. Nothing in this
8Section precludes consideration of contracts longer than 5
9years and related forecast data. Any feedstock procurement
10occurring in accordance with this plan shall be competitively
11bid through a request for proposals process. Approval and
12implementation of the feedstock procurement plan shall be
13subject to review and approval by the Commission according to
14the provisions set forth in this Section. A feedstock
15procurement plan shall include each of the following
16components:
17        (1) Daily load analysis. This analysis shall include:
18            (A) multi-year historical analysis of hourly
19        loads; and
20            (B) known or projected changes to future loads.
21        (2) Determination of the fuel specifications required
22    for the clean coal SNG brownfield facility, including:
23            (A) coal and petroleum coke mix, as set by the
24        clean coal SNG brownfield facility with coal
25        comprising at least 50% of the total feedstock over the
26        term of any sourcing agreement;

 

 

SB3388 Enrolled- 21 -LRB096 20594 MJR 36292 b

1            (B) volume of each feedstock required;
2            (C) quality standards of each feedstock;
3            (D) delivery requirements, including cost
4        implications; and
5            (E) technical specifications of the clean coal SNG
6        brownfield facility for its feedstocks.
7    (b) The feedstock procurement process shall be
8administered by a feedstock procurement administrator and
9monitored by a feedstock procurement monitor.
10        (1) The feedstock procurement administrator shall:
11            (A) design the final feedstock procurement process
12        in accordance with subsection (d) of this Section
13        following Commission approval of the feedstock
14        procurement plan;
15            (B) develop feedstock benchmarks in accordance
16        with subsection (d)(3) to be used to evaluate bids;
17        these benchmarks shall be submitted to the Commission
18        for review and approval on a confidential basis prior
19        to the feedstock procurement event;
20            (C) serve as the interface between the clean coal
21        SNG brownfield facility and coal and petroleum coke
22        suppliers;
23            (D) manage the bidder prequalification and
24        registration process;
25            (E) obtain the facility's agreement to the final
26        form of all supply contracts and credit collateral

 

 

SB3388 Enrolled- 22 -LRB096 20594 MJR 36292 b

1        agreements;
2            (F) administer the request for feedstock proposals
3        process;
4            (G) have the discretion to negotiate to determine
5        whether bidders are willing to lower the price of bids
6        that meet the benchmarks approved by the Commission;
7        any post-bid negotiations with bidders shall be
8        limited to price only and shall be completed within 24
9        hours after opening the sealed bids and shall be
10        conducted in a fair and unbiased manner; in conducting
11        the negotiations, there shall be no disclosure of any
12        information derived from proposals submitted by
13        competing bidders; if information is disclosed to any
14        bidder, it shall be provided to all competing bidders;
15            (H) maintain confidentiality of supplier and
16        bidding information in a manner consistent with all
17        applicable laws, rules, regulations, and tariffs;
18            (I) submit a confidential report to the Commission
19        recommending acceptance or rejection of bids;
20            (J) notify the facility of contract counterparties
21        and contract specifics; and
22            (K) administer related contingency feedstock
23        procurement events.
24        (2) The feedstock procurement monitor, who shall be
25    retained by the Commission, shall:
26            (A) monitor interactions among the feedstock

 

 

SB3388 Enrolled- 23 -LRB096 20594 MJR 36292 b

1        procurement administrator, suppliers, and the
2        facility;
3            (B) monitor and report to the Commission on the
4        progress of the feedstock procurement process;
5            (C) provide an independent, confidential report to
6        the Commission regarding the results of the feedstock
7        procurement event;
8            (D) preserve the confidentiality of supplier and
9        bidding information in a manner consistent with all
10        applicable laws, rules, regulations, and tariffs;
11            (E) provide expert advice to the Commission and
12        consult with the feedstock procurement administrator
13        regarding issues related to feedstock procurement
14        process design, rules, protocols, and policy-related
15        matters;
16            (F) consult with the feedstock procurement
17        administrator regarding the development and use of
18        benchmark criteria, standard form contracts, credit
19        policies, and bid documents; and
20            (G) assess compliance with the procurement plans
21        approved by the Commission.
22    (c) The feedstock planning process shall be conducted as
23follows:
24        (1) Beginning in 2015, the clean coal SNG brownfield
25    facility shall annually provide a range of feedstock
26    requirement forecasts to the Agency by May 15 of each year,

 

 

SB3388 Enrolled- 24 -LRB096 20594 MJR 36292 b

1    or such other date as may be required by the Commission or
2    Agency. The feedstock requirement forecasts shall cover
3    the 5-year feedstock procurement planning period for the
4    next feedstock procurement plan, or such other longer
5    period that the Agency or the Commission may require and
6    shall include daily data representing a high-load,
7    low-load, and expected-load scenario for the load of the
8    utilities required to enter into sourcing agreements with
9    the clean coal SNG brownfield facility. The utility shall
10    provide supporting data and assumptions for each of the
11    scenarios.
12        (2) Beginning in 2015, the Agency shall at least every
13    5 years prepare a feedstock procurement plan by June 15, or
14    such other date as may be required by the Commission. The
15    feedstock procurement plan shall identify the portfolio of
16    feedstocks to be procured. Copies of the feedstock
17    procurement plan shall be posted and made publicly
18    available on the Agency's and Commission's websites, and
19    copies shall also be provided to the clean coal SNG
20    brownfield facility. The clean coal SNG brownfield
21    facility shall have 30 days following the date of posting
22    to provide comment to the Agency on the feedstock
23    procurement plan. Other interested entities also may
24    comment on the feedstock procurement plan. All comments
25    submitted to the Agency shall be specific, supported by
26    data or other detailed analyses, and, if objecting to all

 

 

SB3388 Enrolled- 25 -LRB096 20594 MJR 36292 b

1    or a portion of the feedstock procurement plan, accompanied
2    by specific alternative wording or proposals. All comments
3    shall be posted on the Agency's and Commission's websites.
4    During this 30-day comment period, the Agency shall hold at
5    least one public hearing for the purpose of receiving
6    public comment on the procurement plan. Within 14 days
7    following the end of the 30-day comment period, the Agency
8    shall revise the feedstock procurement plan as necessary
9    based on the comments received, file the feedstock
10    procurement plan with the Commission, and post the
11    feedstock procurement plan on the websites.
12        (3) Within 5 days after the filing of the feedstock
13    procurement plan, any person objecting to the feedstock
14    procurement plan shall file an objection with the
15    Commission. Within 10 days after the filing, the Commission
16    shall determine whether a hearing is necessary. The
17    Commission shall enter its order confirming or modifying
18    the feedstock procurement plan within 90 days after the
19    filing of the feedstock procurement plan by the Agency.
20        (4) The Commission shall approve the feedstock
21    procurement plan, including expressly the forecast used in
22    the feedstock procurement plan, if the Commission
23    determines that it will ensure adequate, reliable, and
24    affordable feedstocks to the clean coal SNG brownfield
25    facility at the lowest total cost over time, taking into
26    account any benefits of price stability.

 

 

SB3388 Enrolled- 26 -LRB096 20594 MJR 36292 b

1    (d) The feedstock procurement process shall include each of
2the following components:
3        (1) Solicitation, prequalification, and registration
4    of bidders. The feedstock procurement administrator shall
5    disseminate information to potential bidders to promote a
6    feedstock procurement event, notify potential bidders that
7    the feedstock procurement administrator may enter into a
8    post-bid price negotiation with bidders that meet the
9    applicable benchmarks, provide supply requirements, and
10    otherwise explain the competitive feedstock procurement
11    process. In addition to such other publication as the
12    feedstock procurement administrator determines is
13    appropriate, this information shall be posted on the
14    Agency's and the Commission's websites. The feedstock
15    procurement administrator shall also administer the
16    prequalification process, including evaluation of credit
17    worthiness, compliance with feedstock procurement rules,
18    and agreement to the standard form contract developed
19    pursuant to paragraph (2) of this subsection (d). The
20    feedstock procurement administrator shall then identify
21    and register bidders to participate in the feedstock
22    procurement event.
23        (2) Standard contract forms and credit terms and
24    instruments. The feedstock procurement administrator, in
25    consultation with the clean coal SNG brownfield facility,
26    gas utilities, the Commission, and other interested

 

 

SB3388 Enrolled- 27 -LRB096 20594 MJR 36292 b

1    parties and subject to Commission oversight, shall develop
2    and provide standard contract forms for the supplier
3    contracts that meet generally accepted industry practices.
4    Standard credit terms and instruments that meet generally
5    accepted industry practices shall be similarly developed.
6    The feedstock procurement administrator shall make
7    available to the Commission all written comments it
8    receives on the contract forms, credit terms, or
9    instruments. If the feedstock procurement administrator
10    cannot reach agreement with the applicable clean coal SNG
11    brownfield facility as to the contract terms and
12    conditions, then the feedstock procurement administrator
13    must notify the Commission of any disputed terms and the
14    Commission shall resolve the dispute. The terms of the
15    contracts shall not be subject to negotiation by winning
16    bidders and the bidders must agree to the terms of the
17    contract in advance so that winning bids are selected
18    solely on the basis of price.
19        (3) Establishment of a market-based price benchmark.
20    As part of the development of the feedstock procurement
21    process, the feedstock procurement administrator, in
22    consultation with the Commission staff, Agency staff, and
23    the feedstock procurement monitor, shall establish
24    benchmarks for evaluating the final prices in the contracts
25    for each of the feedstocks that will be procured through
26    the feedstock procurement process. The benchmarks shall be

 

 

SB3388 Enrolled- 28 -LRB096 20594 MJR 36292 b

1    based on price data for similar feedstocks for the same
2    delivery period and same delivery hub or other delivery
3    hubs after adjusting for that difference. The price
4    benchmarks may also be adjusted to take into account
5    differences between the information reflected in the
6    underlying data sources and the specific feedstocks and
7    gasification feedstock procurement process being used to
8    procure for the clean coal SNG brownfield facility. The
9    benchmarks shall be confidential but shall be provided to,
10    and shall be subject to, the Commission's review and
11    approval prior to a feedstock procurement event.
12        (4) Request for proposals. The feedstock procurement
13    administrator shall design and issue a request for
14    proposals to supply coal or petroleum coke in accordance
15    with the clean coal SNG brownfield facility's usage plan,
16    as approved by the Commission. The request for proposals
17    shall set forth a procedure for sealed, binding commitment
18    bidding with pay-as-bid settlement, and provision for
19    selection of bids on the basis of price.
20        (5) A plan for implementing contingencies in the event
21    of supplier default or failure of the feedstock procurement
22    process to fully meet the expected feedstock requirement
23    due to insufficient supplier participation, Commission
24    rejection of results, or any other cause. The plan must be
25    specific to the clean coal SNG brownfield facility's
26    feedstock specifications and requirements.

 

 

SB3388 Enrolled- 29 -LRB096 20594 MJR 36292 b

1    The feedstock procurement process described in this
2subsection (d) is exempt from the requirements of the Illinois
3Procurement Code, pursuant to Section 20-10 of that Code.
4    (e) Within 2 business days after opening the sealed bids,
5the feedstock procurement administrator shall submit a
6confidential report to the Commission. The report shall contain
7the results of the bidding for each of the feedstock types
8along with the feedstock procurement administrator's
9recommendation for the acceptance and rejection of bids based
10on the price benchmark criteria and other factors observed in
11the process. The feedstock procurement monitor also shall
12submit a confidential report to the Commission within 2
13business days after opening the sealed bids. The report shall
14contain the feedstock procurement monitor's assessment of
15bidder behavior in the process, as well as an assessment of the
16feedstock procurement administrator's compliance with the
17feedstock procurement process and rules. The Commission shall
18review the confidential reports submitted by the feedstock
19procurement administrator and feedstock procurement monitor
20and shall accept or reject the recommendations of the feedstock
21procurement administrator within 2 business days after receipt
22of the reports.
23    (f) Within 3 business days after the Commission decision
24approving the results of a feedstock procurement event, the
25clean coal SNG brownfield facility shall enter into binding
26contractual arrangements with the winning suppliers using

 

 

SB3388 Enrolled- 30 -LRB096 20594 MJR 36292 b

1standard form contracts.
2    (g) The names of the successful bidders and the amount of
3feedstock to be delivered for each contract type and for each
4contract term shall be made available to the public at the time
5of Commission approval of a feedstock procurement event. The
6Commission, the procurement monitor, the feedstock procurement
7administrator, the Agency, and all participants in the
8feedstock procurement process shall maintain the
9confidentiality of all other supplier and bidding information
10in a manner consistent with all applicable laws, rules,
11regulations, and tariffs. Confidential information, including
12the confidential reports submitted by the feedstock
13procurement administrator and feedstock procurement monitor
14pursuant to subsection (e) of this Section, shall not be
15publicly available or discoverable by any party in any
16proceeding absent a compelling demonstration of need. The
17reports shall not be admissible in any proceeding other than
18one for law enforcement purposes.
19    (h) Within 2 business days after a Commission decision
20approving the results of a feedstock procurement event or such
21other date as may be required by the Commission from time to
22time, the clean coal SNG brownfield facility shall file for
23informational purposes with the Commission its actual or
24estimated feedstock costs by utility customer reflecting the
25costs associated with the feedstock procurement.
26    (i) The clean coal SNG brownfield facility shall pay for

 

 

SB3388 Enrolled- 31 -LRB096 20594 MJR 36292 b

1reasonable costs incurred by the Agency in administering the
2feedstock procurement events, which costs shall be included in
3the actual delivered fuel costs of the clean coal SNG
4brownfield facility. The Agency shall determine the amount owed
5for each feedstock procurement event, and the clean coal SNG
6brownfield facility shall pay that amount to the Agency within
730 days after being informed by the Agency of the amount owed.
8Those funds shall be deposited into the Illinois Power Agency
9Operations Fund, pursuant to Section 1-55 of this Act, to be
10used to reimburse expenses related to the feedstock
11procurement.
12    (j) The Commission has the authority to adopt rules to
13carry out the provisions of this Section. For the public
14interest, safety, and welfare, the Commission also has the
15authority to adopt rules to carry out the provisions of this
16Section on an emergency basis.
17    (k) On or before April 1 of each year, the Commission may
18hold an informal hearing for the purpose of receiving comments
19on the prior year's feedstock procurement process and any
20recommendations for change.
 
21    Section 7. The Illinois Procurement Code is amended by
22changing Sections 1-10 and 20-10 as follows:
 
23    (30 ILCS 500/1-10)
24    Sec. 1-10. Application.

 

 

SB3388 Enrolled- 32 -LRB096 20594 MJR 36292 b

1    (a) This Code applies only to procurements for which
2contractors were first solicited on or after July 1, 1998. This
3Code shall not be construed to affect or impair any contract,
4or any provision of a contract, entered into based on a
5solicitation prior to the implementation date of this Code as
6described in Article 99, including but not limited to any
7covenant entered into with respect to any revenue bonds or
8similar instruments. All procurements for which contracts are
9solicited between the effective date of Articles 50 and 99 and
10July 1, 1998 shall be substantially in accordance with this
11Code and its intent.
12    (b) This Code shall apply regardless of the source of the
13funds with which the contracts are paid, including federal
14assistance moneys. This Code shall not apply to:
15        (1) Contracts between the State and its political
16    subdivisions or other governments, or between State
17    governmental bodies except as specifically provided in
18    this Code.
19        (2) Grants, except for the filing requirements of
20    Section 20-80.
21        (3) Purchase of care.
22        (4) Hiring of an individual as employee and not as an
23    independent contractor, whether pursuant to an employment
24    code or policy or by contract directly with that
25    individual.
26        (5) Collective bargaining contracts.

 

 

SB3388 Enrolled- 33 -LRB096 20594 MJR 36292 b

1        (6) Purchase of real estate, except that notice of this
2    type of contract with a value of more than $25,000 must be
3    published in the Procurement Bulletin within 7 days after
4    the deed is recorded in the county of jurisdiction. The
5    notice shall identify the real estate purchased, the names
6    of all parties to the contract, the value of the contract,
7    and the effective date of the contract.
8        (7) Contracts necessary to prepare for anticipated
9    litigation, enforcement actions, or investigations,
10    provided that the chief legal counsel to the Governor shall
11    give his or her prior approval when the procuring agency is
12    one subject to the jurisdiction of the Governor, and
13    provided that the chief legal counsel of any other
14    procuring entity subject to this Code shall give his or her
15    prior approval when the procuring entity is not one subject
16    to the jurisdiction of the Governor.
17        (8) Contracts for services to Northern Illinois
18    University by a person, acting as an independent
19    contractor, who is qualified by education, experience, and
20    technical ability and is selected by negotiation for the
21    purpose of providing non-credit educational service
22    activities or products by means of specialized programs
23    offered by the university.
24        (9) Procurement expenditures by the Illinois
25    Conservation Foundation when only private funds are used.
26        (10) Procurement expenditures by the Illinois Health

 

 

SB3388 Enrolled- 34 -LRB096 20594 MJR 36292 b

1    Information Exchange Authority involving private funds
2    from the Health Information Exchange Fund. "Private funds"
3    means gifts, donations, and private grants.
4    (c) This Code does not apply to the electric power
5procurement process provided for under Section 1-75 of the
6Illinois Power Agency Act and Section 16-111.5 of the Public
7Utilities Act.
8    (d) Except for Section 20-160 and Article 50 of this Code,
9and as expressly required by Section 9.1 of the Illinois
10Lottery Law, the provisions of this Code do not apply to the
11procurement process provided for under Section 9.1 of the
12Illinois Lottery Law.
13    (e) This Code does not apply to the process used by the
14Capital Development Board to retain a person or entity to
15assist the Capital Development Board with its duties related to
16the determination of costs of a clean coal SNG brownfield
17facility, as defined by Section 1-10 of the Illinois Power
18Agency Act, as required in subsection (h-3) of Section 9-220 of
19the Public Utilities Act, including calculating the range of
20capital costs, the range of operating and maintenance costs, or
21the sequestration costs or monitoring the construction of clean
22coal SNG brownfield facility for the full duration of
23construction.
24    (f) This Code does not apply to the process used by the
25Illinois Power Agency to retain a mediator to mediate sourcing
26agreement disputes between gas utilities and the clean coal SNG

 

 

SB3388 Enrolled- 35 -LRB096 20594 MJR 36292 b

1brownfield facility, as defined in Section 1-10 of the Illinois
2Power Agency Act, as required under subsection (h-1) of Section
39-220 of the Public Utilities Act.
4(Source: P.A. 95-481, eff. 8-28-07; 95-615, eff. 9-11-07;
595-876, eff. 8-21-08; 96-840, eff. 12-23-09; 96-1331, eff.
67-27-10.)
 
7    (30 ILCS 500/20-10)
8    (Text of Section from P.A. 96-159 and 96-588)
9    Sec. 20-10. Competitive sealed bidding; reverse auction.
10    (a) Conditions for use. All contracts shall be awarded by
11competitive sealed bidding except as otherwise provided in
12Section 20-5.
13    (b) Invitation for bids. An invitation for bids shall be
14issued and shall include a purchase description and the
15material contractual terms and conditions applicable to the
16procurement.
17    (c) Public notice. Public notice of the invitation for bids
18shall be published in the Illinois Procurement Bulletin at
19least 14 days before the date set in the invitation for the
20opening of bids.
21    (d) Bid opening. Bids shall be opened publicly in the
22presence of one or more witnesses at the time and place
23designated in the invitation for bids. The name of each bidder,
24the amount of each bid, and other relevant information as may
25be specified by rule shall be recorded. After the award of the

 

 

SB3388 Enrolled- 36 -LRB096 20594 MJR 36292 b

1contract, the winning bid and the record of each unsuccessful
2bid shall be open to public inspection.
3    (e) Bid acceptance and bid evaluation. Bids shall be
4unconditionally accepted without alteration or correction,
5except as authorized in this Code. Bids shall be evaluated
6based on the requirements set forth in the invitation for bids,
7which may include criteria to determine acceptability such as
8inspection, testing, quality, workmanship, delivery, and
9suitability for a particular purpose. Those criteria that will
10affect the bid price and be considered in evaluation for award,
11such as discounts, transportation costs, and total or life
12cycle costs, shall be objectively measurable. The invitation
13for bids shall set forth the evaluation criteria to be used.
14    (f) Correction or withdrawal of bids. Correction or
15withdrawal of inadvertently erroneous bids before or after
16award, or cancellation of awards of contracts based on bid
17mistakes, shall be permitted in accordance with rules. After
18bid opening, no changes in bid prices or other provisions of
19bids prejudicial to the interest of the State or fair
20competition shall be permitted. All decisions to permit the
21correction or withdrawal of bids based on bid mistakes shall be
22supported by written determination made by a State purchasing
23officer.
24    (g) Award. The contract shall be awarded with reasonable
25promptness by written notice to the lowest responsible and
26responsive bidder whose bid meets the requirements and criteria

 

 

SB3388 Enrolled- 37 -LRB096 20594 MJR 36292 b

1set forth in the invitation for bids, except when a State
2purchasing officer determines it is not in the best interest of
3the State and by written explanation determines another bidder
4shall receive the award. The explanation shall appear in the
5appropriate volume of the Illinois Procurement Bulletin.
6    (h) Multi-step sealed bidding. When it is considered
7impracticable to initially prepare a purchase description to
8support an award based on price, an invitation for bids may be
9issued requesting the submission of unpriced offers to be
10followed by an invitation for bids limited to those bidders
11whose offers have been qualified under the criteria set forth
12in the first solicitation.
13    (i) Alternative procedures. Notwithstanding any other
14provision of this Act to the contrary, the Director of the
15Illinois Power Agency may create alternative bidding
16procedures to be used in procuring professional services under
17subsection (a) of Section 1-75 and subsection (d) of Section
181-78 1-75(a) of the Illinois Power Agency Act and Section
1916-111.5(c) of the Public Utilities Act and to procure
20renewable energy resources under Section 1-56 of the Illinois
21Power Agency Act. These alternative procedures shall be set
22forth together with the other criteria contained in the
23invitation for bids, and shall appear in the appropriate volume
24of the Illinois Procurement Bulletin.
25    (j) Reverse auction. Notwithstanding any other provision
26of this Section and in accordance with rules adopted by the

 

 

SB3388 Enrolled- 38 -LRB096 20594 MJR 36292 b

1Director of Central Management Services as chief procurement
2officer, a State purchasing officer under that chief
3procurement officer's jurisdiction may procure supplies or
4services through a competitive electronic auction bidding
5process after the purchasing officer explains in writing to the
6chief procurement officer his or her determination that the use
7of such a process will be in the best interest of the State.
8The chief procurement officer shall publish that determination
9in his or her next volume of the Illinois Procurement Bulletin.
10    An invitation for bids shall be issued and shall include
11(i) a procurement description, (ii) all contractual terms,
12whenever practical, and (iii) conditions applicable to the
13procurement, including a notice that bids will be received in
14an electronic auction manner.
15    Public notice of the invitation for bids shall be given in
16the same manner as provided in subsection (c).
17    Bids shall be accepted electronically at the time and in
18the manner designated in the invitation for bids. During the
19auction, a bidder's price shall be disclosed to other bidders.
20Bidders shall have the opportunity to reduce their bid prices
21during the auction. At the conclusion of the auction, the
22record of the bid prices received and the name of each bidder
23shall be open to public inspection.
24    After the auction period has terminated, withdrawal of bids
25shall be permitted as provided in subsection (f).
26    The contract shall be awarded within 60 days after the

 

 

SB3388 Enrolled- 39 -LRB096 20594 MJR 36292 b

1auction by written notice to the lowest responsible bidder, or
2all bids shall be rejected except as otherwise provided in this
3Code. Extensions of the date for the award may be made by
4mutual written consent of the State purchasing officer and the
5lowest responsible bidder.
6    This subsection does not apply to (i) procurements of
7professional and artistic services, including but not limited
8to telecommunications services, communications services,
9Internet services, and information services, and (ii)
10contracts for construction projects.
11(Source: P.A. 95-481, eff. 8-28-07; 96-159, eff. 8-10-09;
1296-588, eff. 8-18-09; revised 10-5-10.)
 
13    (Text of Section from P.A. 96-159 and 96-795)
14    Sec. 20-10. Competitive sealed bidding; reverse auction.
15    (a) Conditions for use. All contracts shall be awarded by
16competitive sealed bidding except as otherwise provided in
17Section 20-5.
18    (b) Invitation for bids. An invitation for bids shall be
19issued and shall include a purchase description and the
20material contractual terms and conditions applicable to the
21procurement.
22    (c) Public notice. Public notice of the invitation for bids
23shall be published in the Illinois Procurement Bulletin at
24least 14 days before the date set in the invitation for the
25opening of bids.

 

 

SB3388 Enrolled- 40 -LRB096 20594 MJR 36292 b

1    (d) Bid opening. Bids shall be opened publicly in the
2presence of one or more witnesses at the time and place
3designated in the invitation for bids. The name of each bidder,
4the amount of each bid, and other relevant information as may
5be specified by rule shall be recorded. After the award of the
6contract, the winning bid and the record of each unsuccessful
7bid shall be open to public inspection.
8    (e) Bid acceptance and bid evaluation. Bids shall be
9unconditionally accepted without alteration or correction,
10except as authorized in this Code. Bids shall be evaluated
11based on the requirements set forth in the invitation for bids,
12which may include criteria to determine acceptability such as
13inspection, testing, quality, workmanship, delivery, and
14suitability for a particular purpose. Those criteria that will
15affect the bid price and be considered in evaluation for award,
16such as discounts, transportation costs, and total or life
17cycle costs, shall be objectively measurable. The invitation
18for bids shall set forth the evaluation criteria to be used.
19    (f) Correction or withdrawal of bids. Correction or
20withdrawal of inadvertently erroneous bids before or after
21award, or cancellation of awards of contracts based on bid
22mistakes, shall be permitted in accordance with rules. After
23bid opening, no changes in bid prices or other provisions of
24bids prejudicial to the interest of the State or fair
25competition shall be permitted. All decisions to permit the
26correction or withdrawal of bids based on bid mistakes shall be

 

 

SB3388 Enrolled- 41 -LRB096 20594 MJR 36292 b

1supported by written determination made by a State purchasing
2officer.
3    (g) Award. The contract shall be awarded with reasonable
4promptness by written notice to the lowest responsible and
5responsive bidder whose bid meets the requirements and criteria
6set forth in the invitation for bids, except when a State
7purchasing officer determines it is not in the best interest of
8the State and by written explanation determines another bidder
9shall receive the award. The explanation shall appear in the
10appropriate volume of the Illinois Procurement Bulletin. The
11written explanation must include:
12        (1) a description of the agency's needs;
13        (2) a determination that the anticipated cost will be
14    fair and reasonable;
15        (3) a listing of all responsible and responsive
16    bidders; and
17        (4) the name of the bidder selected, pricing, and the
18    reasons for selecting that bidder.
19    Each chief procurement officer may adopt guidelines to
20implement the requirements of this subsection (g).
21    The written explanation shall be filed with the Legislative
22Audit Commission and the Procurement Policy Board and be made
23available for inspection by the public within 30 days after the
24agency's decision to award the contract.
25    (h) Multi-step sealed bidding. When it is considered
26impracticable to initially prepare a purchase description to

 

 

SB3388 Enrolled- 42 -LRB096 20594 MJR 36292 b

1support an award based on price, an invitation for bids may be
2issued requesting the submission of unpriced offers to be
3followed by an invitation for bids limited to those bidders
4whose offers have been qualified under the criteria set forth
5in the first solicitation.
6    (i) Alternative procedures. Notwithstanding any other
7provision of this Act to the contrary, the Director of the
8Illinois Power Agency may create alternative bidding
9procedures to be used in procuring professional services under
10subsection (a) of Section 1-75 and subsection (d) of Section
111-78 1-75(a) of the Illinois Power Agency Act and Section
1216-111.5(c) of the Public Utilities Act and to procure
13renewable energy resources under Section 1-56 of the Illinois
14Power Agency Act. These alternative procedures shall be set
15forth together with the other criteria contained in the
16invitation for bids, and shall appear in the appropriate volume
17of the Illinois Procurement Bulletin.
18    (j) Reverse auction. Notwithstanding any other provision
19of this Section and in accordance with rules adopted by the
20chief procurement officer, that chief procurement officer may
21procure supplies or services through a competitive electronic
22auction bidding process after the chief procurement officer
23determines that the use of such a process will be in the best
24interest of the State. The chief procurement officer shall
25publish that determination in his or her next volume of the
26Illinois Procurement Bulletin.

 

 

SB3388 Enrolled- 43 -LRB096 20594 MJR 36292 b

1    An invitation for bids shall be issued and shall include
2(i) a procurement description, (ii) all contractual terms,
3whenever practical, and (iii) conditions applicable to the
4procurement, including a notice that bids will be received in
5an electronic auction manner.
6    Public notice of the invitation for bids shall be given in
7the same manner as provided in subsection (c).
8    Bids shall be accepted electronically at the time and in
9the manner designated in the invitation for bids. During the
10auction, a bidder's price shall be disclosed to other bidders.
11Bidders shall have the opportunity to reduce their bid prices
12during the auction. At the conclusion of the auction, the
13record of the bid prices received and the name of each bidder
14shall be open to public inspection.
15    After the auction period has terminated, withdrawal of bids
16shall be permitted as provided in subsection (f).
17    The contract shall be awarded within 60 days after the
18auction by written notice to the lowest responsible bidder, or
19all bids shall be rejected except as otherwise provided in this
20Code. Extensions of the date for the award may be made by
21mutual written consent of the State purchasing officer and the
22lowest responsible bidder.
23    This subsection does not apply to (i) procurements of
24professional and artistic services, (ii) telecommunications
25services, communication services, and information services,
26and (iii) contracts for construction projects.

 

 

SB3388 Enrolled- 44 -LRB096 20594 MJR 36292 b

1(Source: P.A. 95-481, eff. 8-28-07; 96-159, eff. 8-10-09;
296-795, eff. 7-1-10 (see Section 5 of P.A. 96-793 for the
3effective date of changes made by P.A. 96-795); revised
410-5-10.)
 
5    Section 10. The Public Utilities Act is amended by changing
6Sections 3-101 and 9-220 and by adding Section 3-123 as
7follows:
 
8    (220 ILCS 5/3-101)  (from Ch. 111 2/3, par. 3-101)
9    Sec. 3-101. Definitions. Unless otherwise specified, the
10terms set forth in Sections 3-102 through 3-123 3-121 are used
11in this Act as therein defined.
12(Source: P.A. 84-617; 84-1118.)
 
13    (220 ILCS 5/3-123 new)
14    Sec. 3-123. Clean coal SNG brownfield facility; sequester;
15SNG facility; sourcing agreement; substitute natural gas or
16SNG. As used in this Act:
17    "Clean coal SNG brownfield facility" shall have the same
18meaning as provided in Section 1-10 of the Illinois Power
19Agency Act.
20    "Sequester" shall have the same meaning as provided in
21Section 1-10 of the Illinois Power Agency Act.
22    "SNG facility" means a facility that produces substitute
23natural gas from feedstock that includes coal through a

 

 

SB3388 Enrolled- 45 -LRB096 20594 MJR 36292 b

1gasification process, including a clean coal facility, the
2clean coal SNG brownfield facility, and the facility described
3in subsection (h) of Section 9-220 of this Act.
4    "Sourcing agreement" means an agreement between the owner
5of a clean coal SNG brownfield facility and the gas utility
6that has the terms and conditions meeting the requirements of
7subsection (h-1) of Section 9-220 of this Act.
8    "Substitute natural gas" or "SNG" shall have the same
9meaning as provided in Section 1-10 of the Illinois Power
10Agency Act.
 
11    (220 ILCS 5/9-220)  (from Ch. 111 2/3, par. 9-220)
12    Sec. 9-220. Rate changes based on changes in fuel costs.
13    (a) Notwithstanding the provisions of Section 9-201, the
14Commission may authorize the increase or decrease of rates and
15charges based upon changes in the cost of fuel used in the
16generation or production of electric power, changes in the cost
17of purchased power, or changes in the cost of purchased gas
18through the application of fuel adjustment clauses or purchased
19gas adjustment clauses. The Commission may also authorize the
20increase or decrease of rates and charges based upon
21expenditures or revenues resulting from the purchase or sale of
22emission allowances created under the federal Clean Air Act
23Amendments of 1990, through such fuel adjustment clauses, as a
24cost of fuel. For the purposes of this paragraph, cost of fuel
25used in the generation or production of electric power shall

 

 

SB3388 Enrolled- 46 -LRB096 20594 MJR 36292 b

1include the amount of any fees paid by the utility for the
2implementation and operation of a process for the
3desulfurization of the flue gas when burning high sulfur coal
4at any location within the State of Illinois irrespective of
5the attainment status designation of such location; but shall
6not include transportation costs of coal (i) except to the
7extent that for contracts entered into on and after the
8effective date of this amendatory Act of 1997, the cost of the
9coal, including transportation costs, constitutes the lowest
10cost for adequate and reliable fuel supply reasonably available
11to the public utility in comparison to the cost, including
12transportation costs, of other adequate and reliable sources of
13fuel supply reasonably available to the public utility, or (ii)
14except as otherwise provided in the next 3 sentences of this
15paragraph. Such costs of fuel shall, when requested by a
16utility or at the conclusion of the utility's next general
17electric rate proceeding, whichever shall first occur, include
18transportation costs of coal purchased under existing coal
19purchase contracts. For purposes of this paragraph "existing
20coal purchase contracts" means contracts for the purchase of
21coal in effect on the effective date of this amendatory Act of
221991, as such contracts may thereafter be amended, but only to
23the extent that any such amendment does not increase the
24aggregate quantity of coal to be purchased under such contract.
25Nothing herein shall authorize an electric utility to recover
26through its fuel adjustment clause any amounts of

 

 

SB3388 Enrolled- 47 -LRB096 20594 MJR 36292 b

1transportation costs of coal that were included in the revenue
2requirement used to set base rates in its most recent general
3rate proceeding. Cost shall be based upon uniformly applied
4accounting principles. Annually, the Commission shall initiate
5public hearings to determine whether the clauses reflect actual
6costs of fuel, gas, power, or coal transportation purchased to
7determine whether such purchases were prudent, and to reconcile
8any amounts collected with the actual costs of fuel, power,
9gas, or coal transportation prudently purchased. In each such
10proceeding, the burden of proof shall be upon the utility to
11establish the prudence of its cost of fuel, power, gas, or coal
12transportation purchases and costs. The Commission shall issue
13its final order in each such annual proceeding for an electric
14utility by December 31 of the year immediately following the
15year to which the proceeding pertains, provided, that the
16Commission shall issue its final order with respect to such
17annual proceeding for the years 1996 and earlier by December
1831, 1998.
19    (b) A public utility providing electric service, other than
20a public utility described in subsections (e) or (f) of this
21Section, may at any time during the mandatory transition period
22file with the Commission proposed tariff sheets that eliminate
23the public utility's fuel adjustment clause and adjust the
24public utility's base rate tariffs by the amount necessary for
25the base fuel component of the base rates to recover the public
26utility's average fuel and power supply costs per kilowatt-hour

 

 

SB3388 Enrolled- 48 -LRB096 20594 MJR 36292 b

1for the 2 most recent years for which the Commission has issued
2final orders in annual proceedings pursuant to subsection (a),
3where the average fuel and power supply costs per kilowatt-hour
4shall be calculated as the sum of the public utility's prudent
5and allowable fuel and power supply costs as found by the
6Commission in the 2 proceedings divided by the public utility's
7actual jurisdictional kilowatt-hour sales for those 2 years.
8Notwithstanding any contrary or inconsistent provisions in
9Section 9-201 of this Act, in subsection (a) of this Section or
10in any rules or regulations promulgated by the Commission
11pursuant to subsection (g) of this Section, the Commission
12shall review and shall by order approve, or approve as
13modified, the proposed tariff sheets within 60 days after the
14date of the public utility's filing. The Commission may modify
15the public utility's proposed tariff sheets only to the extent
16the Commission finds necessary to achieve conformance to the
17requirements of this subsection (b). During the 5 years
18following the date of the Commission's order, but in any event
19no earlier than January 1, 2007, a public utility whose fuel
20adjustment clause has been eliminated pursuant to this
21subsection shall not file proposed tariff sheets seeking, or
22otherwise petition the Commission for, reinstatement of a fuel
23adjustment clause.
24    (c) Notwithstanding any contrary or inconsistent
25provisions in Section 9-201 of this Act, in subsection (a) of
26this Section or in any rules or regulations promulgated by the

 

 

SB3388 Enrolled- 49 -LRB096 20594 MJR 36292 b

1Commission pursuant to subsection (g) of this Section, a public
2utility providing electric service, other than a public utility
3described in subsection (e) or (f) of this Section, may at any
4time during the mandatory transition period file with the
5Commission proposed tariff sheets that establish the rate per
6kilowatt-hour to be applied pursuant to the public utility's
7fuel adjustment clause at the average value for such rate
8during the preceding 24 months, provided that such average rate
9results in a credit to customers' bills, without making any
10revisions to the public utility's base rate tariffs. The
11proposed tariff sheets shall establish the fuel adjustment rate
12for a specific time period of at least 3 years but not more
13than 5 years, provided that the terms and conditions for any
14reinstatement earlier than 5 years shall be set forth in the
15proposed tariff sheets and subject to modification or approval
16by the Commission. The Commission shall review and shall by
17order approve the proposed tariff sheets if it finds that the
18requirements of this subsection are met. The Commission shall
19not conduct the annual hearings specified in the last 3
20sentences of subsection (a) of this Section for the utility for
21the period that the factor established pursuant to this
22subsection is in effect.
23    (d) A public utility providing electric service, or a
24public utility providing gas service may file with the
25Commission proposed tariff sheets that eliminate the public
26utility's fuel or purchased gas adjustment clause and adjust

 

 

SB3388 Enrolled- 50 -LRB096 20594 MJR 36292 b

1the public utility's base rate tariffs to provide for recovery
2of power supply costs or gas supply costs that would have been
3recovered through such clause; provided, that the provisions of
4this subsection (d) shall not be available to a public utility
5described in subsections (e) or (f) of this Section to
6eliminate its fuel adjustment clause. Notwithstanding any
7contrary or inconsistent provisions in Section 9-201 of this
8Act, in subsection (a) of this Section, or in any rules or
9regulations promulgated by the Commission pursuant to
10subsection (g) of this Section, the Commission shall review and
11shall by order approve, or approve as modified in the
12Commission's order, the proposed tariff sheets within 240 days
13after the date of the public utility's filing. The Commission's
14order shall approve rates and charges that the Commission,
15based on information in the public utility's filing or on the
16record if a hearing is held by the Commission, finds will
17recover the reasonable, prudent and necessary jurisdictional
18power supply costs or gas supply costs incurred or to be
19incurred by the public utility during a 12 month period found
20by the Commission to be appropriate for these purposes,
21provided, that such period shall be either (i) a 12 month
22historical period occurring during the 15 months ending on the
23date of the public utility's filing, or (ii) a 12 month future
24period ending no later than 15 months following the date of the
25public utility's filing. The public utility shall include with
26its tariff filing information showing both (1) its actual

 

 

SB3388 Enrolled- 51 -LRB096 20594 MJR 36292 b

1jurisdictional power supply costs or gas supply costs for a 12
2month historical period conforming to (i) above and (2) its
3projected jurisdictional power supply costs or gas supply costs
4for a future 12 month period conforming to (ii) above. If the
5Commission's order requires modifications in the tariff sheets
6filed by the public utility, the public utility shall have 7
7days following the date of the order to notify the Commission
8whether the public utility will implement the modified tariffs
9or elect to continue its fuel or purchased gas adjustment
10clause in force as though no order had been entered. The
11Commission's order shall provide for any reconciliation of
12power supply costs or gas supply costs, as the case may be, and
13associated revenues through the date that the public utility's
14fuel or purchased gas adjustment clause is eliminated. During
15the 5 years following the date of the Commission's order, a
16public utility whose fuel or purchased gas adjustment clause
17has been eliminated pursuant to this subsection shall not file
18proposed tariff sheets seeking, or otherwise petition the
19Commission for, reinstatement or adoption of a fuel or
20purchased gas adjustment clause. Nothing in this subsection (d)
21shall be construed as limiting the Commission's authority to
22eliminate a public utility's fuel adjustment clause or
23purchased gas adjustment clause in accordance with any other
24applicable provisions of this Act.
25    (e) Notwithstanding any contrary or inconsistent
26provisions in Section 9-201 of this Act, in subsection (a) of

 

 

SB3388 Enrolled- 52 -LRB096 20594 MJR 36292 b

1this Section, or in any rules promulgated by the Commission
2pursuant to subsection (g) of this Section, a public utility
3providing electric service to more than 1,000,000 customers in
4this State may, within the first 6 months after the effective
5date of this amendatory Act of 1997, file with the Commission
6proposed tariff sheets that eliminate, effective January 1,
71997, the public utility's fuel adjustment clause without
8adjusting its base rates, and such tariff sheets shall be
9effective upon filing. To the extent the application of the
10fuel adjustment clause had resulted in net charges to customers
11after January 1, 1997, the utility shall also file a tariff
12sheet that provides for a refund stated on a per kilowatt-hour
13basis of such charges over a period not to exceed 6 months;
14provided however, that such refund shall not include the
15proportional amounts of taxes paid under the Use Tax Act,
16Service Use Tax Act, Service Occupation Tax Act, and Retailers'
17Occupation Tax Act on fuel used in generation. The Commission
18shall issue an order within 45 days after the date of the
19public utility's filing approving or approving as modified such
20tariff sheet. If the fuel adjustment clause is eliminated
21pursuant to this subsection, the Commission shall not conduct
22the annual hearings specified in the last 3 sentences of
23subsection (a) of this Section for the utility for any period
24after December 31, 1996 and prior to any reinstatement of such
25clause. A public utility whose fuel adjustment clause has been
26eliminated pursuant to this subsection shall not file a

 

 

SB3388 Enrolled- 53 -LRB096 20594 MJR 36292 b

1proposed tariff sheet seeking, or otherwise petition the
2Commission for, reinstatement of the fuel adjustment clause
3prior to January 1, 2007.
4    (f) Notwithstanding any contrary or inconsistent
5provisions in Section 9-201 of this Act, in subsection (a) of
6this Section, or in any rules or regulations promulgated by the
7Commission pursuant to subsection (g) of this Section, a public
8utility providing electric service to more than 500,000
9customers but fewer than 1,000,000 customers in this State may,
10within the first 6 months after the effective date of this
11amendatory Act of 1997, file with the Commission proposed
12tariff sheets that eliminate, effective January 1, 1997, the
13public utility's fuel adjustment clause and adjust its base
14rates by the amount necessary for the base fuel component of
15the base rates to recover 91% of the public utility's average
16fuel and power supply costs for the 2 most recent years for
17which the Commission, as of January 1, 1997, has issued final
18orders in annual proceedings pursuant to subsection (a), where
19the average fuel and power supply costs per kilowatt-hour shall
20be calculated as the sum of the public utility's prudent and
21allowable fuel and power supply costs as found by the
22Commission in the 2 proceedings divided by the public utility's
23actual jurisdictional kilowatt-hour sales for those 2 years,
24provided, that such tariff sheets shall be effective upon
25filing. To the extent the application of the fuel adjustment
26clause had resulted in net charges to customers after January

 

 

SB3388 Enrolled- 54 -LRB096 20594 MJR 36292 b

11, 1997, the utility shall also file a tariff sheet that
2provides for a refund stated on a per kilowatt-hour basis of
3such charges over a period not to exceed 6 months. Provided
4however, that such refund shall not include the proportional
5amounts of taxes paid under the Use Tax Act, Service Use Tax
6Act, Service Occupation Tax Act, and Retailers' Occupation Tax
7Act on fuel used in generation. The Commission shall issue an
8order within 45 days after the date of the public utility's
9filing approving or approving as modified such tariff sheet. If
10the fuel adjustment clause is eliminated pursuant to this
11subsection, the Commission shall not conduct the annual
12hearings specified in the last 3 sentences of subsection (a) of
13this Section for the utility for any period after December 31,
141996 and prior to any reinstatement of such clause. A public
15utility whose fuel adjustment clause has been eliminated
16pursuant to this subsection shall not file a proposed tariff
17sheet seeking, or otherwise petition the Commission for,
18reinstatement of the fuel adjustment clause prior to January 1,
192007.
20    (g) The Commission shall have authority to promulgate rules
21and regulations to carry out the provisions of this Section.
22    (h) Any Illinois gas utility may enter into a contract on
23or before March 31, 2011 for up to 10 years of supply with any
24company for the purchase of substitute natural gas (SNG)
25produced from coal through the gasification process if the
26company has commenced construction of a coal gasification

 

 

SB3388 Enrolled- 55 -LRB096 20594 MJR 36292 b

1facility by July 1, 2012 in Jefferson County and commencement
2of construction shall mean that material physical site work has
3occurred, such as site clearing and excavation, water runoff
4prevention, water retention reservoir preparation, or
5foundation development. The contract shall contain the
6following provisions: (i) the only coal to be used in the
7gasification process has high volatile bituminous rank and
8greater than 1.7 pounds of sulfur per million Btu content; (ii)
9at the time the contract term commences, the price per million
10Btu may not exceed $7.95 in 2008 dollars, adjusted annually
11based on the change in the Annual Consumer Price Index for All
12Urban Consumers for the Midwest Region as published in April by
13the United States Department of Labor, Bureau of Labor
14Statistics (or a suitable Consumer Price Index calculation if
15this Consumer Price Index is not available) for the previous
16calendar year; provided that the price per million Btu shall
17not exceed $9.95 at any time during the contract; (iii) the
18utility's aggregate long-term supply contracts for the
19purchase of SNG does not exceed 25% of the annual system supply
20requirements of the utility as of 2008 and the quantity of SNG
21supplied to a utility may not exceed 16 million MMBtus; and
22(iv) contract costs pursuant to subsection (h-10) of this
23Section shall not include any lobbying expenses, charitable
24contributions, advertising, organizational memberships, or
25marketing expenses per year.
26    (h-1) Any Illinois gas utility may enter into a sourcing

 

 

SB3388 Enrolled- 56 -LRB096 20594 MJR 36292 b

1agreement for up to 30 years of supply with the clean coal SNG
2brownfield facility if the clean coal SNG brownfield facility
3has commenced construction. Any gas utility that is providing
4service to more than 150,000 customers on the effective date of
5this amendatory Act of the 96th General Assembly shall either
6elect to file biennial rate proceedings before the Commission
7in the years 2011, 2013, and 2015 or enter into a sourcing
8agreement or sourcing agreements with a clean coal SNG
9brownfield facility for 30 years for either (i) 43,500,000,000
10cubic feet per year times a percentage calculated by dividing
11100 by the number of utilities entering into sourcing
12agreements with the clean coal SNG brownfield facility or (ii)
13such lesser amount as may be available from the clean coal SNG
14brownfield facility.
15    Provided, however, that the Illinois Power Agency may
16allocate the purchase obligations more proportionately based
17upon total therms sold to ultimate customers, if it is
18demonstrated with certainty that such alternative allocation
19will not result in adverse consolidation, derivative, or lease
20impacts to the balance sheet or income statement of any
21purchasing utility. In any event, no utility shall be required
22to purchase more than 42% of the projected annual output of the
23clean coal SNG brownfield facility, with the remainder of such
24utility's obligation to be divided proportionately between the
25other utilities.
26    A gas utility electing to file biennial rate proceedings

 

 

SB3388 Enrolled- 57 -LRB096 20594 MJR 36292 b

1before the Commission must file a notice of its election with
2the Commission within 60 days after the effective date of this
3amendatory Act of the 96th General Assembly or its right to
4make the election is irrevocably waived. A gas utility electing
5to file biennial rate proceedings shall make such filings no
6later than August 1 of the years 2011, 2013, and 2015,
7consistent with all requirements of 83 Ill. Adm. Code 255 and
8285 as though the gas utility were filing for an increase in
9its rates, without regard to whether such filing would produce
10an increase, a decrease, or no change in the gas utility's
11rates, and the Commission shall review the gas utility's filing
12and shall issue its order in accordance with the provisions of
13Section 9-201 of this Act.
14    Within 15 days after the effective date of this amendatory
15Act of the 96th General Assembly, the owner of the clean coal
16SNG brownfield facility shall submit to the Illinois Power
17Agency and each gas utility that is providing service to more
18than 150,000 customers on the effective date of this amendatory
19Act of the 96th General Assembly a copy of a draft sourcing
20agreement. Within 45 days after receipt of the draft sourcing
21agreement, each such gas utility shall provide the Illinois
22Power Agency and the owner of a clean coal SNG brownfield
23facility with its comments and recommended revisions to the
24draft sourcing agreement. Within 15 days after the receipt of
25the gas utility's comments and recommended revisions, the owner
26of the clean coal SNG brownfield facility shall submit its

 

 

SB3388 Enrolled- 58 -LRB096 20594 MJR 36292 b

1responsive comments and a further revised draft of the sourcing
2agreement to the Illinois Power Agency. The Illinois Power
3Agency shall review the draft sourcing agreement and comments.
4    If the parties to the sourcing agreement do not agree on
5the terms therein, then the Illinois Power Agency shall retain
6an independent mediator to mediate the dispute between the
7parties. If the parties are in agreement on the terms of the
8sourcing agreement, the Illinois Power Agency shall approve the
9final draft sourcing agreement. If after mediation the parties
10have failed to come to agreement, then the Illinois Power
11Agency shall revise the draft sourcing agreement as necessary
12to confirm that the final draft sourcing agreement contains
13only terms that are reasonable and equitable. The Illinois
14Power Agency shall adopt and make public a policy detailing the
15process for retaining a mediator under this subsection (h-1).
16Any mediator retained to assist with mediating disputes between
17the parties regarding the sourcing agreement shall be retained
18no later than 60 days after the effective date of this
19amendatory Act of the 96th General Assembly.
20    Upon approval of a final draft agreement, the Illinois
21Power Agency shall submit the final draft agreement to the
22Capital Development Board and the Commission no later than 90
23days after the effective date of this amendatory Act of the
2496th General Assembly. The gas utility and the clean coal SNG
25brownfield facility shall pay a reasonable fee as required by
26the Illinois Power Agency for its services under this

 

 

SB3388 Enrolled- 59 -LRB096 20594 MJR 36292 b

1subsection (h-1) and shall pay the mediator's reasonable fees,
2if any. The Illinois Power Agency shall adopt and make public a
3policy detailing the process for retaining a mediator under
4this Section.
5    The sourcing agreement between a gas utility and the clean
6coal SNG brownfield facility shall contain the following
7provisions:
8        (1) Any and all coal used in the gasification process
9    must be coal that has high volatile bituminous rank and
10    greater than 1.7 pounds of sulfur per million Btu content.
11        (2) Coal and petroleum coke are feedstocks for the
12    gasification process, with coal comprising at least 50% of
13    the total feedstock over the term of the sourcing agreement
14    and with the feedstocks to be procured in accordance with
15    requirements of Section 1-78 of the Illinois Power Agency
16    Act.
17        (3) The sourcing agreement once entered into
18    terminates no more than 30 years after the commencement of
19    the commercial production of SNG at the clean coal SNG
20    brownfield facility.
21        (4) The clean coal SNG brownfield facility guarantees a
22    minimum of $100,000,000 in consumer savings, calculated in
23    real 2010 dollars at the conclusion of the term of the
24    sourcing agreement by comparing the delivered SNG price to
25    the Chicago City-gate price on a weighted daily basis for
26    each day over the entire term of the sourcing agreement, to

 

 

SB3388 Enrolled- 60 -LRB096 20594 MJR 36292 b

1    be provided in accordance with subsection (h-2) of this
2    Section.
3        (5) Prior to the clean coal SNG brownfield facility
4    issuing a notice to proceed to construction, the clean coal
5    SNG brownfield facility shall establish a consumer
6    protection reserve account for the benefit of the customers
7    of the utilities that have entered into sourcing agreements
8    with the clean coal SNG brownfield facility pursuant to
9    this subsection (h-1), with cash principal in the amount of
10    $150,000,000. This cash principal shall only be
11    recoverable through the consumer protection reserve
12    account and not as a cost to be recovered in the delivered
13    SNG price pursuant to subsection (h-3) of this Section. The
14    consumer protection reserve account shall be maintained
15    and administered by an independent trustee that is mutually
16    agreed upon by the clean coal SNG brownfield facility, the
17    utilities, and the Commission in an interest-bearing
18    account in accordance with subsection (h-2) of this
19    Section.
20        (6) The clean coal SNG brownfield facility shall
21    identify and sell economically viable by-products produced
22    by the facility.
23        (7) 50% of all additional net revenue, defined as
24    miscellaneous net revenue after cost allowance for costs
25    associated with additional net revenue that are not
26    otherwise recoverable pursuant to subsection (h-3) of this

 

 

SB3388 Enrolled- 61 -LRB096 20594 MJR 36292 b

1    Section, including net revenue from sales of substitute
2    natural gas derived from the facility above the nameplate
3    capacity of the facility and other by-products produced by
4    the facility, shall be credited to the consumer protection
5    reserve account pursuant to subsection (h-2) of this
6    Section.
7        (8) The delivered SNG price per million btu to be paid
8    monthly by the utility to the clean coal SNG brownfield
9    facility, which shall be based only upon the following: (A)
10    a capital recovery charge, operations and maintenance
11    costs, and sequestration costs, only to the extent approved
12    by the Commission pursuant to paragraphs (1), (2), and (3)
13    of subsection (h-3) of this Section; (B) the actual
14    delivered and processed fuel costs pursuant to paragraph
15    (4) of subsection (h-3) of this Section; (C) actual costs
16    of SNG transportation pursuant to paragraph (6) of
17    subsection (h-3) of this Section; (D) certain taxes and
18    fees imposed by the federal government, the State, or any
19    unit of local government as provided in paragraph (6) of
20    subsection (h-3) of this Section; and (E) the credit, if
21    any, from the consumer protection reserve account pursuant
22    to subsection (h-2) of this Section. The delivered SNG
23    price per million Btu shall proportionately reflect these
24    elements over the term of the sourcing agreement.
25        (9) A formula to translate the recoverable costs and
26    charges under subsection (h-3) of this Section into the

 

 

SB3388 Enrolled- 62 -LRB096 20594 MJR 36292 b

1    delivered SNG price per million btu.
2        (10) Title to the SNG shall pass at a mutually
3    agreeable point in Illinois, and may provide that, rather
4    than the utility taking title to the SNG, a mutually agreed
5    upon third-party gas marketer pursuant to a contract
6    approved by the Illinois Power Agency or its designee, may
7    take title to the SNG pursuant to an agreement between the
8    utility, the owner of the clean coal SNG brownfield
9    facility, and the third-party gas marketer.
10        (11) A utility may exit the sourcing agreement without
11    penalty if the clean coal SNG brownfield facility does not
12    commence construction by July 1, 2014.
13        (12) A utility is responsible to pay only the
14    Commission determined unit price cost of SNG that is
15    purchased by the utility. Nothing in the sourcing agreement
16    will obligate a utility to invest capital in a clean coal
17    SNG brownfield facility.
18        (13) The quality of SNG must, at a minimum, be
19    equivalent to the equality required for an interstate
20    pipeline gas before a utility is required to accept and pay
21    for SNG gas.
22        (14) Nothing in the sourcing agreement will require a
23    utility to construct any facilities to accept delivery of
24    SNG. Provided, however, if a utility is required by law or
25    otherwise elects to connect the clean coal SNG brownfield
26    facility to an interstate pipeline, then the utility shall

 

 

SB3388 Enrolled- 63 -LRB096 20594 MJR 36292 b

1    be entitled to recover pursuant to its tariffs all just and
2    reasonable costs that are prudently incurred. Any costs
3    incurred by the utility to receive, deliver, manage, or
4    otherwise accommodate purchases under the SNG sourcing
5    agreement will be fully recoverable through a utility's
6    purchased gas adjustment clause rider mechanism.
7        (15) Remedies for the clean coal SNG brownfield
8    facility's failure to deliver a designated amount for a
9    designated period.
10    (h-2) Consumer protection reserve account. The clean coal
11SNG brownfield facility shall guarantee a minimum of
12$100,000,000 in consumer savings, calculated in real 2010
13dollars at the conclusion of the term of the sourcing agreement
14by comparing the delivered SNG price to the Chicago City-gate
15price on a weighted daily basis for each day over the entire
16term of the sourcing agreement. Prior to the clean coal SNG
17brownfield facility issuing a notice to proceed to
18construction, the clean coal SNG brownfield facility shall
19establish a consumer protection reserve account for the benefit
20of the retail customers of the utilities that have entered into
21sourcing agreements with the clean coal SNG brownfield facility
22pursuant to subsection (h-1), with cash principal in the amount
23of $150,000,000. Such cash principal shall only be recovered
24through the consumer protection reserve account and not as a
25cost to be recovered in the delivered SNG price pursuant to
26subsection (h-3) of this Section. The consumer protection

 

 

SB3388 Enrolled- 64 -LRB096 20594 MJR 36292 b

1reserve account shall be maintained and administered by an
2independent trustee that is mutually agreed upon by the clean
3coal SNG brownfield facility, the utilities, and the Commission
4in an interest-bearing account in accordance with the
5following:
6        (1) The clean coal SNG brownfield facility monthly
7    shall calculate the difference between the monthly
8    delivered SNG price and the Chicago City-gate price, by
9    comparing the delivered SNG price, which shall include the
10    cost of transportation to the delivery point, if any, to
11    the Chicago City-gate price on a weighted daily basis for
12    each day of the prior month based upon a mutually agreed
13    upon published index.
14        (2) During the first 2 years of operation of the
15    facility:
16            (A) to the extent the monthly delivered SNG price,
17        is greater than the Chicago City-gate price, the
18        consumer protection reserve account shall be used to
19        provide a credit to reduce the SNG price by an amount
20        equal to the difference between the monthly delivered
21        SNG price and the Chicago City-gate price; and
22            (B) to the extent the monthly delivered SNG price
23        is less than or equal to the Chicago City-gate price,
24        the utility shall credit the difference between the
25        monthly delivered SNG price and the monthly Chicago
26        City-gate price, if any, to the consumer protection

 

 

SB3388 Enrolled- 65 -LRB096 20594 MJR 36292 b

1        reserve account. Such credit issued pursuant to this
2        paragraph (B) shall be deemed prudent and reasonable
3        and not subject to a Commission prudence review;
4        (3) After 2 years of operation of the facility, and
5    monthly, on an on-going basis, thereafter:
6            (A) to the extent that the monthly delivered SNG
7        price is less than or equal to the Chicago City-gate
8        price, calculated using the weighted average of the
9        daily Chicago City-gate price on a daily basis over the
10        entire month, the utility shall credit the difference,
11        if any, to the consumer protection reserve account.
12        Such credit issued pursuant to this subparagraph (A)
13        shall be deemed prudent and reasonable and not subject
14        to a Commission prudence review;
15            (B) any amounts in the consumer protection reserve
16        account in excess of $100,000,000 shall be distributed
17        to the clean coal SNG brownfield facility; provided,
18        however, that under no circumstances shall the total
19        cumulative amount distributed to the clean coal SNG
20        brownfield facility under this subparagraph (B) exceed
21        $150,000,000;
22            (C) to the extent the monthly delivered SNG price
23        is greater than the Chicago City-gate price, after
24        distributing the amounts pursuant to subparagraph (B)
25        of this paragraph (3), if any, the consumer protection
26        reserve account shall be used to provide a credit to

 

 

SB3388 Enrolled- 66 -LRB096 20594 MJR 36292 b

1        reduce the SNG price by an amount equal to the
2        difference between the monthly delivered SNG price and
3        the Chicago City-gate price;
4            (D) if retail customers have realized net consumer
5        savings, calculated by comparing the delivered SNG
6        price to the weighted average of the daily Chicago
7        City-gate price on a daily basis over the entire term
8        of the sourcing agreement to date, then after
9        distributing the amounts pursuant to subparagraphs (B)
10        and (C) of this paragraph (3), 50% of any additional
11        amounts in the consumer protection reserve account in
12        excess of $100,000,000 shall be distributed to the
13        clean coal SNG brownfield facility, with the remaining
14        50% of any such additional amounts being credited to
15        retail customers; provided, however, that if retail
16        customers have not realized such net consumer savings,
17        no such distribution shall be made to the clean coal
18        SNG brownfield facility, and 100% of such additional
19        amounts shall be credited to the retail customers to
20        the extent the consumer protection reserve account
21        exceeds $100,000,000.
22        (4) 50% of all additional net revenue, defined as
23    miscellaneous net revenue after cost allowance for costs
24    associated with additional net revenue that are not
25    otherwise recoverable pursuant to subsection (h-3) of this
26    Section, including net revenue from sales of substitute

 

 

SB3388 Enrolled- 67 -LRB096 20594 MJR 36292 b

1    natural gas derived from the facility above the nameplate
2    capacity of the facility and other by-products produced by
3    the facility, shall be credited to the consumer protection
4    reserve account.
5        (5) At the conclusion of the term of the sourcing
6    agreement, to the extent retail customers have not saved
7    the minimum of $100,000,000 in consumer savings as
8    guaranteed in this subsection (h-2), amounts in the
9    consumer protection reserve account shall be credited to
10    retail customers to the extent the retail customers have
11    saved the minimum of $100,000,000; 50% of any additional
12    amounts in the consumer protection reserve account shall be
13    distributed to the company, and the remaining 50% shall be
14    distributed to retail customers.
15        (6) If, at the conclusion of the term of the sourcing
16    agreement, the customers have not saved the minimum
17    $100,000,000 in savings as guaranteed in this subsection
18    (h-2) and the consumer protection reserve account has been
19    depleted, then the clean coal SNG brownfield facility shall
20    be liable for any remaining amount owed to the retail
21    customers to the extent that the customers are provided
22    with the $100,000,000 in savings as guaranteed in this
23    subsection (h-2). The retail customers shall have first
24    priority in recovering that debt above any creditors,
25    except the original senior secured lender to the extent
26    that the original senior secured lender has any senior

 

 

SB3388 Enrolled- 68 -LRB096 20594 MJR 36292 b

1    secured debt outstanding, including any clean coal SNG
2    brownfield facility parent companies or affiliates.
3        (7) The clean coal SNG brownfield facility, the
4    utilities, and the trustee shall work together to take
5    commercially reasonable steps to minimize the tax impact of
6    these transactions, while preserving the consumer
7    benefits.
8        (8) The clean coal SNG brownfield facility shall each
9    month, starting in the facility's first year of commercial
10    operation, file with the Commission, in such form as the
11    Commission shall require, a report as to the consumer
12    protection reserve account. The monthly report must
13    contain the following information:
14            (A) the extent the monthly delivered SNG price is
15        greater than, less than, or equal to the Chicago
16        City-gate price;
17            (B) the amount credited or debited to the consumer
18        protection reserve account during the month;
19            (C) the amounts credited to consumers and
20        distributed to the clean coal SNG brownfield facility
21        during the month;
22            (D) the total amount of the consumer protection
23        reserve account at the beginning and end of the month;
24            (E) the total amount of consumer savings to date;
25        and
26            (F) any other additional information the

 

 

SB3388 Enrolled- 69 -LRB096 20594 MJR 36292 b

1        Commission shall require.
2        When any report is erroneous or defective or appears to
3    the Commission to be erroneous or defective, the Commission
4    may notify the clean coal SNG brownfield facility to amend
5    the report within 30 days, and, before or after the
6    termination of the 30-day period, the Commission may
7    examine the trustee of the consumer protection reserve
8    account or the officers, agents, employees, books,
9    records, or accounts of the clean coal SNG brownfield
10    facility and correct such items in the report as upon such
11    examination the Commission may find defective or
12    erroneous. All reports shall be under oath.
13        All reports made to the Commission by the clean coal
14    SNG brownfield and the contents of the reports shall be
15    open to public inspection and shall be deemed a public
16    record under the Freedom of Information Act. Such reports
17    shall be preserved in the office of the Commission. The
18    Commission shall publish an annual summary of the reports
19    prior to February 1 of the following year. The annual
20    summary shall be made available to the public on the
21    Commission's website and shall be submitted to the General
22    Assembly.
23        Any facility that fails to file a report required under
24    this paragraph (8) to the Commission within the time
25    specified or to make specific answer to any question
26    propounded by the Commission within 30 days from the time

 

 

SB3388 Enrolled- 70 -LRB096 20594 MJR 36292 b

1    it is lawfully required to do so, or within such further
2    time not to exceed 90 days as may in its discretion be
3    allowed by the Commission, shall pay a penalty of $500 to
4    the Commission for each day it is in default.
5        Any person who willfully makes any false report to the
6    Commission or to any member, officer, or employee thereof,
7    any person who willfully in a report withholds or fails to
8    provide material information to which the Commission is
9    entitled under this paragraph (8) and which information is
10    either required to be filed by statute, rule, regulation,
11    order, or decision of the Commission or has been requested
12    by the Commission, and any person who willfully aids or
13    abets such person shall be guilty of a Class A misdemeanor.
14    (h-3) Recoverable costs and revenue by the clean coal SNG
15brownfield facility.
16        (1) A capital recovery charge approved by the
17    Commission shall be recoverable by the clean coal SNG
18    brownfield facility under a sourcing agreement. The
19    capital recovery charge shall be comprised of capital costs
20    and a reasonable rate of return. "Capital costs" means
21    costs to be incurred in connection with the construction
22    and development of a facility, as defined in Section 1-10
23    of the Illinois Power Agency Act, and such other costs as
24    the Capital Development Board deems appropriate to be
25    recovered in the capital recovery charge.
26            (A) Capital costs. The Capital Development Board

 

 

SB3388 Enrolled- 71 -LRB096 20594 MJR 36292 b

1        shall calculate a range of capital costs that it
2        believes would be reasonable for the clean coal SNG
3        brownfield facility to recover under the sourcing
4        agreement. In making this determination, the Capital
5        Development Board shall review the final draft of the
6        sourcing agreement and the rate of return approved by
7        the Commission. In addition, the Capital Development
8        Board may: (i) review the facility cost report, if any,
9        of the clean coal SNG brownfield facility; (ii) consult
10        as much as it deems necessary with the clean coal SNG
11        brownfield facility; and (iii) conduct whatever
12        research and investigation it deems necessary.
13            The Capital Development Board shall retain an
14        engineering expert to assist in determining both the
15        range of capital costs and the range of operations and
16        maintenance costs that it believes would be reasonable
17        for the clean coal SNG brownfield facility to recover
18        under the sourcing agreement. Provided, however, that
19        such expert shall: (i) not have been involved in the
20        clean coal SNG brownfield facility's facility cost
21        report, if any, (ii) not own or control any direct or
22        indirect interest in the initial clean coal facility;
23        and (iii) have no contractual relationship with the
24        clean coal SNG brownfield facility. In order to qualify
25        as an independent expert, a person or company must
26        have:

 

 

SB3388 Enrolled- 72 -LRB096 20594 MJR 36292 b

1                (i) direct previous experience conducting
2            front-end engineering and design studies for
3            large-scale energy facilities and administering
4            large-scale energy operations and maintenance
5            contracts, which may be particularized to the
6            specific type of financing associated with the
7            clean coal SNG brownfield facility;
8                (ii) an advanced degree in economics,
9            mathematics, engineering, or a related area of
10            study;
11                (iii) ten years of experience in the energy
12            sector, including construction and risk management
13            experience;
14                (iv) expertise in assisting companies with
15            obtaining financing for large-scale energy
16            projects, which may be particularized to the
17            specific type of financing associated with the
18            clean coal SNG brownfield facility;
19                (v) expertise in operations and maintenance
20            which may be particularized to the specific type of
21            operations and maintenance associated with the
22            clean coal SNG brownfield facility;
23                (vi) expertise in credit and contract
24            protocols;
25                (vii) adequate resources to perform and
26            fulfill the required functions and

 

 

SB3388 Enrolled- 73 -LRB096 20594 MJR 36292 b

1            responsibilities; and
2                (viii) the absence of a conflict of interest
3            and inappropriate bias for or against an affected
4            gas utility or the clean coal SNG brownfield
5            facility.
6            The clean coal SNG brownfield facility and the
7        Illinois Power Agency shall cooperate with the Capital
8        Development Board in any investigation it deems
9        necessary. The Capital Development Board shall make
10        its final determination of the range of capital costs
11        confidentially and shall submit that range to the
12        Commission in a confidential filing within 120 days
13        after the effective date of this amendatory Act of the
14        96th General Assembly. The clean coal SNG brownfield
15        facility shall submit to the Commission its estimate of
16        the capital costs to be recovered under the sourcing
17        agreement. Only after the clean coal SNG brownfield
18        facility has submitted this estimate shall the
19        Commission publicly announce the range of capital
20        costs submitted by the Capital Development Board.
21            In the event that the estimate submitted by the
22        clean coal SNG brownfield facility is within or below
23        the range submitted by the Capital Development Board,
24        the clean coal SNG brownfield facility's estimate
25        shall be approved by the Commission as the amount of
26        capital costs to be recovered under the sourcing

 

 

SB3388 Enrolled- 74 -LRB096 20594 MJR 36292 b

1        agreement. In the event that the estimate submitted by
2        the clean coal SNG brownfield facility is above the
3        range submitted by the Capital Development Board, the
4        amount of capital costs at the lowest end of the range
5        submitted by the Capital Development Board shall be
6        approved by the Commission as the amount of capital
7        costs to be recovered under the sourcing agreement.
8        Within 15 days after the Capital Development Board has
9        submitted its range and the clean coal SNG brownfield
10        facility has submitted its estimate, the Commission
11        shall approve the capital costs for the clean coal SNG
12        brownfield facility.
13            The Capital Development Board shall monitor the
14        construction of the clean coal SNG brownfield facility
15        for the full duration of construction to assess
16        potential cost overruns. The Capital Development
17        Board, in its discretion, may retain an expert to
18        facilitate such monitoring. The clean coal SNG
19        brownfield facility shall pay a reasonable fee as
20        required by the Capital Development Board for the
21        Capital Development Board's services under this
22        subsection (h-3) to be deposited into the Capital
23        Development Board Revolving Fund, and such fee shall
24        not be passed through to a utility or its customers. If
25        an expert is retained by the Capital Development Board
26        for monitoring of construction, then the clean coal SNG

 

 

SB3388 Enrolled- 75 -LRB096 20594 MJR 36292 b

1        brownfield facility must pay for the expert's
2        reasonable fees and such costs shall not be passed
3        through to a utility or its customers.
4            (B) Rate of Return. No later than 30 days after the
5        date on which the Illinois Power Agency submits a final
6        draft sourcing agreement, the Commission shall hold a
7        public hearing to determine the rate of return to be
8        recovered under the sourcing agreement. Rate of return
9        shall be comprised of the clean coal SNG brownfield
10        facility's actual cost of debt, including
11        mortgage-style amortization, and a reasonable return
12        on equity. The Commission shall post notice of the
13        hearing on its website no later than 10 days prior to
14        the date of the hearing. The Commission shall provide
15        the public and all interested parties, including the
16        gas utilities, the Attorney General, and the Illinois
17        Power Agency, an opportunity to be heard.
18            In determining the return on equity, the
19        Commission shall select a commercially reasonable
20        return on equity taking into account the return on
21        equity being received by developers of similar
22        facilities in or outside of Illinois, the need to
23        balance an incentive for clean-coal technology with
24        the need to protect ratepayers from high gas prices,
25        the risks being borne by the clean coal SNG brownfield
26        facility in the final draft sourcing agreement, and any

 

 

SB3388 Enrolled- 76 -LRB096 20594 MJR 36292 b

1        other information that the Commission may deem
2        relevant. The Commission may establish a return on
3        equity that varies with the amount of savings, if any,
4        to customers during the term of the sourcing agreement,
5        comparing the delivered SNG price to a daily weighted
6        average price of natural gas, based upon an index. The
7        Illinois Power Agency shall recommend a return on
8        equity to the Commission using the same criteria.
9        Within 60 days after receiving the final draft sourcing
10        agreement from the Illinois Power Agency, the
11        Commission shall approve the rate of return for the
12        clean coal brownfield facility. Within 30 days after
13        obtaining debt financing for the clean coal SNG
14        brownfield facility, the clean coal SNG brownfield
15        facility shall file a notice with the Commission
16        identifying the actual cost of debt.
17        (2) Operations and maintenance costs approved by the
18    Commission shall be recoverable by the clean coal SNG
19    brownfield facility under the sourcing agreement. The
20    operations and maintenance costs mean costs that have been
21    incurred for the administration, supervision, operation,
22    maintenance, preservation, and protection of the clean
23    coal SNG brownfield facility's physical plant.
24        The Capital Development Board shall calculate a range
25    of operations and maintenance costs that it believes would
26    be reasonable for the clean coal SNG brownfield facility to

 

 

SB3388 Enrolled- 77 -LRB096 20594 MJR 36292 b

1    recover under the sourcing agreement. In making this
2    determination, the Capital Development Board shall review
3    the final draft of the sourcing agreement and the rate of
4    return approved by the Commission. In addition, the Capital
5    Development Board may: (i) review the facility cost report,
6    if any, of the clean coal SNG brownfield facility; (ii)
7    consult as much as it deems necessary with the clean coal
8    SNG brownfield facility; and (iii) conduct whatever
9    research and investigation it deems necessary. As set forth
10    in subparagraph (A) of paragraph (1) of this subsection
11    (h-3), the Capital Development Board shall retain an
12    independent engineering expert to assist in determining
13    both the range of operations and maintenance costs that it
14    believes would be reasonable for the clean coal SNG
15    brownfield to recover under the sourcing agreement. The
16    clean coal SNG brownfield facility and the Illinois Power
17    Agency shall cooperate with the Capital Development Board
18    in any investigation it deems necessary. The Capital
19    Development Board shall make its final determination of the
20    range of operations and maintenance costs confidentially
21    and shall submit that range to the Commission in a
22    confidential filing within 120 days after the effective
23    date of this amendatory Act of the 96th General Assembly.
24        The clean coal SNG brownfield facility shall submit to
25    the Commission its estimate of the operations and
26    maintenance costs to be recovered under the sourcing

 

 

SB3388 Enrolled- 78 -LRB096 20594 MJR 36292 b

1    agreement. Only after the clean coal SNG brownfield
2    facility has submitted this estimate shall the Commission
3    publicly announce the range of operations and maintenance
4    costs submitted by the Capital Development Board. In the
5    event that the estimate submitted by the clean coal SNG
6    brownfield facility is within or below the range submitted
7    by the Capital Development Board, the clean coal SNG
8    brownfield facility's estimate shall be approved by the
9    Commission as the amount of operations and maintenance
10    costs to be recovered under the sourcing agreement. In the
11    event that the estimate submitted by the clean coal SNG
12    brownfield facility is above the range submitted by the
13    Capital Development Board, the amount of operations and
14    maintenance costs at the lowest end of the range submitted
15    by the Capital Development Board shall be approved by the
16    Commission as the amount of operations and maintenance
17    costs to be recovered under the sourcing agreement. Within
18    15 days after the Capital Development Board has submitted
19    its range and the clean coal SNG brownfield facility has
20    submitted its estimate, the Commission shall approve the
21    operations and maintenance costs for the clean coal SNG
22    brownfield facility.
23        The clean coal SNG brownfield facility shall pay for
24    the independent engineering expert's reasonable fees and
25    such costs shall not be passed through to a utility or its
26    customers. The clean coal SNG brownfield facility shall pay

 

 

SB3388 Enrolled- 79 -LRB096 20594 MJR 36292 b

1    a reasonable fee as required by the Capital Development
2    Board for the Capital Development Board's services under
3    this subsection (h-3) to be deposited into the Capital
4    Development Board Revolving Fund, and such fee shall not be
5    passed through to a utility or its customers.
6        (3) Sequestration costs approved by the Commission
7    shall be recoverable by the clean coal SNG brownfield
8    facility. "Sequestration costs" means costs to be incurred
9    by the clean coal SNG brownfield facility in accordance
10    with its Commission-approved carbon capture and
11    sequestration plan to:
12            (A) capture carbon dioxide;
13            (B) build, operate, and maintain a sequestration
14        site in which carbon dioxide may be injected;
15            (C) build, operate, and maintain a carbon dioxide
16        pipeline; and
17            (D) transport the carbon dioxide to the
18        sequestration site or a pipeline.
19        The Commission shall assess the prudency of the
20    sequestration costs for the clean coal SNG brownfield
21    facility before construction commences at the
22    sequestration site or pipeline. Any revenues the clean coal
23    SNG brownfield facility receives as a result of the
24    capture, transportation, or sequestration of carbon
25    dioxide shall be first credited against all sequestration
26    costs, with the positive balance, if any, treated as

 

 

SB3388 Enrolled- 80 -LRB096 20594 MJR 36292 b

1    additional net revenue.
2        The Commission may, in its discretion, retain an expert
3    to assist in its review of sequestration costs. The clean
4    coal SNG brownfield facility shall pay for the expert's
5    reasonable fees if an expert is retained by the Commission,
6    and such costs shall not be passed through to a utility or
7    its customers. Once made, the Commission's determination
8    of the amount of recoverable sequestration costs shall not
9    be increased unless the clean coal SNG brownfield facility
10    can show by clear and convincing evidence that (i) the
11    costs were not reasonably foreseeable; (ii) the costs were
12    due to circumstances beyond the clean coal SNG brownfield
13    facility's control; and (iii) the clean coal SNG brownfield
14    facility took all reasonable steps to mitigate the costs.
15    If the Commission determines that sequestration costs may
16    be increased, the Commission shall provide for notice and a
17    public hearing for approval of the increased sequestration
18    costs.
19        (4) Actual delivered and processed fuel costs shall be
20    set by the Illinois Power Agency through a SNG feedstock
21    procurement, pursuant to Sections 1-20, 1-77, and 1-78 of
22    the Illinois Power Agency Act, to be performed at least
23    every 5 years and purchased by the clean coal SNG
24    brownfield facility pursuant to feedstock procurement
25    contracts developed by the Illinois Power Agency, with coal
26    comprising at least 50% of the total feedstock over the

 

 

SB3388 Enrolled- 81 -LRB096 20594 MJR 36292 b

1    term of the sourcing agreement and petroleum coke
2    comprising the remainder of the SNG feedstock. If the
3    Commission fails to approve a feedstock procurement plan or
4    fails to approve the results of a feedstock procurement
5    event, then the fuel shall be purchased by the company
6    month-by-month on the spot market and those actual
7    delivered and processed fuel costs shall be recoverable
8    under the sourcing agreement. If a supplier defaults under
9    the terms of a procurement contract, then the Illinois
10    Power Agency shall immediately initiate a feedstock
11    procurement process to obtain a replacement supply, and,
12    prior to the conclusion of that process, fuel shall be
13    purchased by the company month-by-month on the spot market
14    and those actual delivered and processed fuel costs shall
15    be recoverable under the sourcing agreement.
16        (5) Taxes and fees imposed by the federal government,
17    the State, or any unit of local government applicable to
18    the clean coal SNG brownfield facility, excluding income
19    tax, shall be recoverable by the clean coal SNG brownfield
20    facility under the sourcing agreement to the extent such
21    taxes and fees were not applicable to the facility on the
22    date of this amendatory Act of the 96th General Assembly.
23        (6) The actual transportation costs, in accordance
24    with the applicable utility's tariffs, and third-party
25    marketer costs incurred by the company, if any, associated
26    with transporting the SNG from the clean coal SNG

 

 

SB3388 Enrolled- 82 -LRB096 20594 MJR 36292 b

1    brownfield facility to the Chicago City-gate to sell such
2    SNG into the natural gas markets shall be recoverable under
3    the sourcing agreement.
4        (7) Unless otherwise provided, within 30 days after a
5    decision of the Commission on recoverable costs under this
6    Section, any interested party to the Commission's decision
7    may apply for a rehearing with respect to the decision. The
8    Commission shall receive and consider the application for
9    rehearing and shall grant or deny the application in whole
10    or in part within 20 days after the date of the receipt of
11    the application by the Commission. If no rehearing is
12    applied for within the required 30 days or an application
13    for rehearing is denied, then the Commission decision shall
14    be final. If an application for rehearing is granted, then
15    the Commission shall hold a rehearing within 30 days after
16    granting the application. The decision of the Commission
17    upon rehearing shall be final.
18        Any person affected by a decision of the Commission
19    under this subsection (h-3) may have the decision reviewed
20    only under and in accordance with the Administrative Review
21    Law. Unless otherwise provided, the provisions of the
22    Administrative Review Law, all amendments and
23    modifications to that Law, and the rules adopted pursuant
24    to that Law shall apply to and govern all proceedings for
25    the judicial review of final administrative decisions of
26    the Commission under this subsection (h-3). The term

 

 

SB3388 Enrolled- 83 -LRB096 20594 MJR 36292 b

1    "administrative decision" is defined as in Section 3-101 of
2    the Code of Civil Procedure.
3        (8) The Capital Development Board shall adopt and make
4    public a policy detailing the process for retaining experts
5    under this Section. Any experts retained to assist with
6    calculating the range of capital costs or operations and
7    maintenance costs shall be retained no later than 45 days
8    after the effective date of this amendatory Act of the 96th
9    General Assembly.
10    (h-4) No later than 60 days after the Illinois Power Agency
11submits the final draft sourcing agreement pursuant to
12subsection (h-1), the Commission shall approve a sourcing
13agreement containing the capital costs, rate of return, and
14operations and maintenance costs. Once the sourcing agreement
15is approved, then the gas utility subject to that sourcing
16agreement shall have 45 days after the date of the Commission's
17approval to enter into the sourcing agreement.
18    (h-5) The Attorney General, on behalf of the people of the
19State of Illinois, may specifically enforce the requirements of
20this subsection (h-5). All contracts under subsection (h) of
21this Act and all sourcing agreements under subsection (h-1) of
22this Act, regardless of duration, shall require the owner of
23any facility supplying SNG under the contract or sourcing
24agreement to provide documentation to the Commission each year,
25starting in the facility's first year of commercial operation,
26accurately reporting the quantity of carbon dioxide emissions

 

 

SB3388 Enrolled- 84 -LRB096 20594 MJR 36292 b

1from the facility that have been captured and sequestered and
2reporting any quantities of carbon dioxide released from the
3site or sites at which carbon dioxide emissions were
4sequestered in prior years, based on continuous monitoring of
5those sites. If, in any year, the owner of the facility
6described in subsection (h) of this Act fails to demonstrate
7that the SNG facility captured and sequestered at least 90% of
8the total carbon dioxide emissions that the facility would
9otherwise emit or that sequestration of emissions from prior
10years has failed, resulting in the release of carbon dioxide
11into the atmosphere, then the owner of the facility must offset
12excess emissions. Any such carbon dioxide offsets must be
13permanent, additional, verifiable, real, located within the
14State of Illinois, and legally and practicably enforceable;
15provided that the owner of the facility described in subsection
16(h) of this Act shall not be obligated to acquire carbon
17dioxide emission offsets to the extent that the cost of
18acquiring such offsets would exceed $40 million in any given
19year. No costs of any purchases of carbon offsets may be
20recovered from a utility or its customers. All carbon offsets
21purchased for this purpose must be permanently retired.
22    If, in any year, the owner of a clean coal SNG brownfield
23facility fails to demonstrate that the clean coal SNG
24brownfield facility captured and sequestered at least 85% of
25the total carbon dioxide emissions that the facility would
26otherwise emit, then the owner of the clean coal SNG brownfield

 

 

SB3388 Enrolled- 85 -LRB096 20594 MJR 36292 b

1facility must pay a penalty of $20 per ton of excess carbon
2emissions up to $20,000,000, which shall be deposited into the
3Energy Efficiency Trust Fund and distributed pursuant to
4subsection (b) of Section 6-6 of the Renewable Energy, Energy
5Efficiency, and Coal Resources Development Law of 1997.
6Provided, however, to the extent that the owner of the clean
7coal SNG brownfield facility can demonstrate that the failure
8was as a result of acts of God (including fire, flood,
9earthquake, tornado, lightning, hurricane, or other natural
10disaster); any amendment, modification, or abrogation of any
11applicable law or regulation that would prevent performance;
12war; invasion; act of foreign enemies; hostilities (regardless
13of whether war is declared); civil war; rebellion; revolution;
14insurrection; military or usurped power or confiscation;
15terrorist activities; civil disturbances; riots;
16nationalization; sabotage; blockage; or embargo, the owner of
17the clean coal SNG brownfield facility shall not be subject to
18a penalty if and only if (i) it promptly provides notice of its
19failure to the Commission; (ii) as soon as practicable and
20consistent with any order or direction from the Commission, it
21submits to the Commission proposed modifications to its carbon
22capture and sequestration plan; and (iii) it carries out its
23proposed modifications in the manner and time directed by the
24Commission. If the Commission finds that the facility has not
25satisfied each of these requirements, then the facility shall
26be subject to the penalty. If the owner of a clean coal SNG

 

 

SB3388 Enrolled- 86 -LRB096 20594 MJR 36292 b

1brownfield facility demonstrates that the clean coal SNG
2brownfield facility captured and sequestered more than 85% of
3the total carbon emissions that the facility would otherwise
4emit, the owner of the clean coal SNG brownfield facility may
5credit such additional amounts to reduce the amount of any
6future penalty to be paid. The penalty resulting from the
7failure to capture and sequester at least the minimum amount of
8carbon dioxide shall not be passed on to a utility or its
9customers.
10    In addition to any penalty for the clean coal SNG
11brownfield facility's failure to capture and sequester at least
12its minimum sequestration requirement, the Attorney General,
13on behalf of the People of the State of Illinois, shall bring
14an action for specific performance of this subsection (h-5).
15Such action may be filed in any circuit court in Illinois. By
16entering into a sourcing agreement pursuant to subsection (h-1)
17of this Section, the clean coal SNG brownfield facility agrees
18to waive any objections to venue or to the jurisdiction of the
19court with regard to the Attorney General's action for specific
20performance under this subsection (h-5).
21     In addition, carbon dioxide emission credits equivalent to
2250% of the amount of credits associated with the required
23sequestration of carbon dioxide from the facility must be
24permanently retired. Compliance with the sequestration
25requirements and the offset purchase requirements specified in
26this subsection (h-5) for the facility described in subsection

 

 

SB3388 Enrolled- 87 -LRB096 20594 MJR 36292 b

1(h) of this Act shall be assessed annually by an independent
2expert retained by the owner of the SNG facility described in
3subsection (h) of this Act, with the advance written approval
4of the Attorney General. Compliance with the sequestration
5requirements and penalty requirements specified in this
6subsection (h-5) for the clean coal SNG brownfield facility
7shall be assessed annually by the Commission, which may in its
8discretion retain an expert to facilitate its assessment. If an
9expert is retained by the Commission, then the clean coal SNG
10brownfield facility shall pay for the expert's reasonable fees,
11and such costs shall not be passed through to a utility or its
12customers. A SNG facility operating pursuant to this subsection
13(h-5) shall not forfeit its designation as a clean coal SNG
14facility or a clean coal SNG brownfield facility if the
15facility fails to fully comply with the applicable carbon
16sequestration requirements in any given year, provided the
17requisite offsets are purchased or requisite penalties are
18paid.
19    Responsibility for compliance with the sequestration
20requirements specified in this subsection (h-5) for the clean
21coal SNG brownfield facility shall reside solely with the clean
22coal SNG brownfield facility regardless of whether the facility
23has contracted with another party to capture, transport, or
24sequester carbon dioxide.
25    (h-7) Sequestration permitting, oversight, and
26investigations.

 

 

SB3388 Enrolled- 88 -LRB096 20594 MJR 36292 b

1        (1) No clean coal facility or clean coal SNG brownfield
2    facility may transport or sequester carbon dioxide unless
3    the Commission approves the method of carbon dioxide
4    transportation or sequestration. Such approval shall be
5    required regardless of whether the facility has contracted
6    with another to transport or sequester the carbon dioxide.
7    Nothing in this subsection (h-7) shall release the owner or
8    operator of a carbon dioxide sequestration site or carbon
9    dioxide pipeline from any other permitting requirements
10    under applicable State and federal laws, statutes, rules,
11    or regulations.
12        (2) The Commission shall review carbon dioxide
13    transportation and sequestration methods proposed by a
14    clean coal facility or a clean coal SNG brownfield facility
15    and shall approve those methods it deems reasonable and
16    cost-effective. For purposes of this review,
17    "cost-effective" means a commercially reasonable price for
18    similar carbon dioxide transportation or sequestration
19    techniques. In determining whether sequestration is
20    reasonable and cost-effective, the Commission may consult
21    with the Illinois State Geological Survey and retain third
22    parties to assist in its determination, provided that such
23    third parties shall not own or control any direct or
24    indirect interest in the facility that is proposing the
25    carbon dioxide transportation or the carbon dioxide
26    sequestration method and shall have no contractual

 

 

SB3388 Enrolled- 89 -LRB096 20594 MJR 36292 b

1    relationship with that facility. If a third party is
2    retained by the Commission, then the facility proposing the
3    carbon dioxide transportation or sequestration method
4    shall pay for the expert's reasonable fees, and these costs
5    shall not be passed through to a utility or its customers.
6        No later than 6 months prior to the date upon which the
7    owner intends to commence construction of a clean coal
8    facility or the clean coal SNG brownfield facility, the
9    owner of the facility shall file with the Commission a
10    carbon dioxide transportation or sequestration plan. The
11    Commission shall hold a public hearing within 30 days after
12    receipt of the facility's carbon dioxide transportation or
13    sequestration plan. The Commission shall post notice of the
14    review on its website upon submission of a carbon dioxide
15    transportation or sequestration method and shall accept
16    written public comments. The Commission shall take the
17    comments into account when making its decision.
18        The Commission may not approve a carbon dioxide
19    sequestration method if the owner or operator of the
20    sequestration site has not received (i) an Underground
21    Injection Control permit from the Illinois Environmental
22    Protection Agency pursuant to the Environmental Protection
23    Act; (ii) an Underground Injection Control permit from the
24    Illinois Department of Natural Resources pursuant to the
25    Illinois Oil and Gas Act; or (iii) a permit similar to
26    items (i) or (ii) from the state in which the sequestration

 

 

SB3388 Enrolled- 90 -LRB096 20594 MJR 36292 b

1    site is located if the sequestration will take place
2    outside of Illinois. The Commission shall approve or deny
3    the carbon dioxide transportation or sequestration method
4    within 90 days after the receipt of all required
5    information.
6        (3) At least annually, the Illinois Environmental
7    Protection Agency shall inspect all carbon dioxide
8    sequestration sites in Illinois. The Illinois
9    Environmental Protection Agency may, as often as deemed
10    necessary, monitor and conduct investigations of those
11    sites. The owner or operator of the sequestration site must
12    cooperate with the Illinois Environmental Protection
13    Agency investigations of carbon dioxide sequestration
14    sites.
15        If the Illinois Environmental Protection Agency
16    determines at any time a site creates conditions that
17    warrant the issuance of a seal order under Section 34 of
18    the Environmental Protection Act, then the Illinois
19    Environmental Protection Agency shall seal the site
20    pursuant to the Environmental Protection Act. If the
21    Illinois Environmental Protection Agency determines at any
22    time a carbon dioxide sequestration site creates
23    conditions that warrant the institution of a civil action
24    for an injunction under Section 43 of the Environmental
25    Protection Act, then the Illinois Environmental Protection
26    Agency shall request the State's Attorney or the Attorney

 

 

SB3388 Enrolled- 91 -LRB096 20594 MJR 36292 b

1    General institute such action. The Illinois Environmental
2    Protection Agency shall provide notice of any such actions
3    as soon as possible on its website. The SNG facility shall
4    incur all reasonable costs associated with any such
5    inspection or monitoring of the sequestration sites, and
6    these costs shall not be recoverable from utilities or
7    their customers.
8        (4) At least annually, the Commission shall inspect all
9    carbon dioxide pipelines in Illinois that transport carbon
10    dioxide to ensure the safety and feasibility of those
11    pipelines. The Commission may, as often as deemed
12    necessary, monitor and conduct investigations of those
13    pipelines. The owner or operator of the pipeline must
14    cooperate with the Commission investigations of the carbon
15    dioxide pipelines.
16        In circumstances whereby a carbon dioxide pipeline
17    creates a substantial danger to the environment or to the
18    public health of persons or to the welfare of persons where
19    such danger is to the livelihood of such persons, the
20    State's Attorney or Attorney General, upon the request of
21    the Commission or on his or her own motion, may institute a
22    civil action for an immediate injunction to halt any
23    discharge or other activity causing or contributing to the
24    danger or to require such other action as may be necessary.
25    The court may issue an ex parte order and shall schedule a
26    hearing on the matter not later than 3 working days after

 

 

SB3388 Enrolled- 92 -LRB096 20594 MJR 36292 b

1    the date of injunction. The Commission shall provide notice
2    of any such actions as soon as possible on its website. The
3    SNG facility shall incur all reasonable costs associated
4    with any such inspection or monitoring of the sequestration
5    sites, and these costs shall not be recoverable from a
6    utility or its customers.
7    (h-9) The clean coal SNG brownfield facility shall have the
8right to recover prudently incurred increased costs or reduced
9revenue resulting from any new or amendatory legislation or
10other action. The State of Illinois pledges that the State will
11not enact any law or take any action to:
12        (1) break, or repeal the authority for, sourcing
13    agreements approved by the Commission and entered into
14    between public utilities and the clean coal SNG brownfield
15    facility;
16        (2) deny public utilities full cost recovery for their
17    costs incurred under those sourcing agreements; or
18        (3) deny the clean coal SNG brownfield facility full
19    cost and revenue recovery as provided under those sourcing
20    agreements that are recoverable pursuant to subsection
21    (h-3) of this Section.
22    These pledges are for the benefit of the parties to those
23sourcing agreements and the issuers and holders of bonds or
24other obligations issued or incurred to finance or refinance
25the clean coal SNG brownfield facility. The clean coal SNG
26brownfield facility is authorized to include and refer to these

 

 

SB3388 Enrolled- 93 -LRB096 20594 MJR 36292 b

1pledges in any financing agreement into which it may enter in
2regard to those sourcing agreements.
3    The State of Illinois retains and reserves all other rights
4to enact new or amendatory legislation or take any other
5action, without impairment of the right of the clean coal SNG
6brownfield facility to recover prudently incurred increased
7costs or reduced revenue resulting from the new or amendatory
8legislation or other action, including, but not limited to,
9such legislation or other action that would (i) directly or
10indirectly raise the costs the clean coal SNG brownfield
11facility must incur; (ii) directly or indirectly place
12additional restrictions, regulations, or requirements on the
13clean coal SNG brownfield facility; (iii) prohibit
14sequestration in general or prohibit a specific sequestration
15method or project; or (iv) increase minimum sequestration
16requirements for the clean coal SNG brownfield facility to the
17extent technically feasible. The clean coal SNG brownfield
18facility shall have the right to recover prudently incurred
19increased costs or reduced revenue resulting from the new or
20amendatory legislation or other action as described in this
21subsection (h-9).
22    (h-10) Contract costs for SNG incurred by an Illinois gas
23utility are reasonable and prudent and recoverable through the
24purchased gas adjustment clause and are not subject to review
25or disallowance by the Commission. Contract costs are costs
26incurred by the utility under the terms of a contract that

 

 

SB3388 Enrolled- 94 -LRB096 20594 MJR 36292 b

1incorporates the terms stated in subsection (h) of this Section
2as confirmed in writing by the Illinois Power Agency as set
3forth in subsection (h-20) of this Section, which confirmation
4shall be deemed conclusive, or as a consequence of or condition
5to its performance under the contract, including (i) amounts
6paid for SNG under the SNG contract and (ii) costs of
7transportation and storage services of SNG purchased from
8interstate pipelines under federally approved tariffs. Any
9contract, the terms of which have been confirmed in writing by
10the Illinois Power Agency as set forth in subsection (h-20) of
11this Section and the performance of the parties under such
12contract cannot be grounds for challenging prudence or cost
13recovery by the utility through the purchased gas adjustment
14clause, and in such cases, the Commission is directed not to
15consider, and has no authority to consider, any attempted
16challenges.
17    The contracts entered into by Illinois gas utilities
18pursuant to subsection (h) of this Section shall provide that
19the utility retains the right to terminate the contract without
20further obligation or liability to any party if the contract
21has been impaired as a result of any legislative,
22administrative, judicial, or other governmental action that is
23taken that eliminates all or part of the prudence protection of
24this subsection (h-10) or denies the recoverability of all or
25part of the contract costs through the purchased gas adjustment
26clause. Should any Illinois gas utility exercise its right

 

 

SB3388 Enrolled- 95 -LRB096 20594 MJR 36292 b

1under this subsection (h-10) to terminate the contract, all
2contract costs incurred prior to termination are and will be
3deemed reasonable, prudent, and recoverable as and when
4incurred and not subject to review or disallowance by the
5Commission. Any order, issued by the State requiring or
6authorizing the discontinuation of the merchant function,
7defined as the purchase and sale of natural gas by an Illinois
8gas utility for the ultimate consumer in its service territory
9shall include provisions necessary to prevent the impairment of
10the value of any contract hereunder over its full term.
11    (h-11) All costs incurred by an Illinois gas utility in
12procuring SNG, including procuring SNG from a clean coal SNG
13brownfield facility or a third-party marketer pursuant to
14subsection (h-1), are reasonable and prudent and recoverable
15through the purchased gas adjustment clause and are not subject
16to review or disallowance by the Commission. Sourcing agreement
17costs are costs incurred by the utility under the terms of a
18sourcing agreement that incorporates the terms stated in
19subsection (h-1) of this Section as approved by the Commission
20as set forth in subsection (h-4) of this Section, which
21approval shall be deemed conclusive, or as a consequence of or
22condition to its performance under the contract, including (i)
23amounts paid for SNG under the SNG contract and (ii) costs of
24transportation and storage services of SNG purchased from
25interstate pipelines under federally approved tariffs. Any
26sourcing agreement, the terms of which have been approved by

 

 

SB3388 Enrolled- 96 -LRB096 20594 MJR 36292 b

1the Commission as set forth in subsection (h-4) of this
2Section, and the performance of the parties under the sourcing
3agreement cannot be grounds for challenging prudence or cost
4recovery by the utility through the purchased gas adjustment
5clause, and in these cases, the Commission is directed not to
6consider, and has no authority to consider, any attempted
7challenges.
8    (h-15) With respect to each contract entered into by the
9company with an Illinois utility in accordance with the terms
10stated in subsection (h) of this Section, within 60 days
11following the completion of purchases of SNG, the Illinois
12Power Agency shall conduct an analysis to determine (i) the
13average contract SNG cost, which shall be calculated as the
14total amount paid to a company for SNG over the contract term,
15plus the cost to the utility of the required transportation and
16storage services of SNG, divided by the total number of MMBtus
17of SNG actually purchased under the utility contract; (ii) the
18average natural gas purchase cost, which shall be calculated as
19the total annual supply costs paid for natural gas (excluding
20SNG) purchased by such utility over the contract term, plus the
21costs of transportation and storage services of such natural
22gas (excluding such costs for SNG), divided by the total number
23of MMBtus of natural gas (excluding SNG) actually purchased by
24the utility during the contract term; (iii) the cost
25differential, which shall be the difference between the average
26contract SNG cost and the average natural gas purchase cost;

 

 

SB3388 Enrolled- 97 -LRB096 20594 MJR 36292 b

1and (iv) the revenue share target, which shall be the cost
2differential multiplied by the total amount of SNG purchased
3under such utility contract. If the average contract SNG cost
4is equal to or less than the average natural gas purchase cost,
5then the company shall have no further obligation to the
6utility. If the average contract SNG cost for such SNG contract
7is greater than the average natural gas purchase cost for such
8utility, then the company shall market the daily production of
9SNG and distribute on a monthly basis 5% of amounts collected
10with respect to such future sales to the utilities in
11proportion to each utility's SNG purchases from the company
12during the term of the SNG contract to be used to reduce the
13utility's natural gas costs through the purchased gas
14adjustment clause; such payments to the utility shall continue
15until such time as the sum of such payments equals the revenue
16share target of that utility. The company or utilities shall
17have no obligation to repay the revenue share target except as
18provided for in this subsection (h-15).
19    (h-20) The General Assembly authorizes the Illinois
20Finance Authority to issue bonds to the maximum extent
21permitted to finance coal gasification facilities described in
22this Section, which constitute both "industrial projects"
23under Article 801 of the Illinois Finance Authority Act and
24"clean coal and energy projects" under Sections 825-65 through
25825-75 of the Illinois Finance Authority Act. The General
26Assembly further authorizes the Illinois Power Agency to become

 

 

SB3388 Enrolled- 98 -LRB096 20594 MJR 36292 b

1party to agreements and take such actions as necessary to
2enable the Illinois Power Agency or its designate to (i) review
3and confirm in writing that the terms stated in subsection (h)
4of this Section are incorporated in the SNG contract, and (ii)
5conduct an analysis pursuant to subsection (h-15) of this
6Section. Administrative costs incurred by the Illinois Finance
7Authority and Illinois Power Agency in performance of this
8subsection (h-20) shall be subject to reimbursement by the
9company on terms as the Illinois Finance Authority, the
10Illinois Power Agency, and the company may agree. The utility
11and its customers shall have no obligation to reimburse the
12company, the Illinois Finance Authority, or the Illinois Power
13Agency for any such costs.
14    (i) If a gas utility or an affiliate of a gas utility has
15an ownership interest in any entity that produces or sells
16synthetic natural gas, Article VII of this Act shall apply.
17(Source: P.A. 95-1027, eff. 6-1-09; 96-1364, eff. 7-28-10.)
 
18    Section 15. The Illinois Gas Pipeline Safety Act is amended
19by changing Sections 2.02, 2.03, 2.04, and 3 as follows:
 
20    (220 ILCS 20/2.02)  (from Ch. 111 2/3, par. 552.2)
21    Sec. 2.02. "Gas" means natural gas, flammable gas or gas
22which is toxic or corrosive. "Gas" also means carbon dioxide in
23any physical form, whenever transported by pipeline for the
24purpose of sequestration.

 

 

SB3388 Enrolled- 99 -LRB096 20594 MJR 36292 b

1(Source: P.A. 76-1588.)
 
2    (220 ILCS 20/2.03)  (from Ch. 111 2/3, par. 552.3)
3    Sec. 2.03. "Transportation of gas" means the gathering,
4transmission, or distribution of gas by pipeline or its
5storage, within this State and not subject to the jurisdiction
6of the Federal Energy Regulatory Commission under the Natural
7Gas Act, except that it includes the transmission of gas
8through pipeline facilities within this State that transport
9gas from an interstate gas pipeline to a direct sales customer
10within this State purchasing gas for its own consumption.
11"Transportation of gas" also includes the conveyance of gas
12from a gas main through the primary fuel line to the outside
13wall of residential premises. If the gas meter is placed within
143 feet of the structure, the utility's responsibility shall end
15at the outlet side of the meter. "Transportation of gas" also
16includes the conveyance of carbon dioxide in any physical form
17for the purpose of sequestration.
18(Source: P.A. 87-1092; 88-314.)
 
19    (220 ILCS 20/2.04)  (from Ch. 111 2/3, par. 552.4)
20    Sec. 2.04. "Pipeline facilities" includes new and existing
21pipe rights-of-way and any equipment, facility, or building
22used in the transportation of gas or the treatment of gas
23during the course of transportation and includes facilities
24within this State that transport gas from an interstate gas

 

 

SB3388 Enrolled- 100 -LRB096 20594 MJR 36292 b

1pipeline to a direct sales customer within this State
2purchasing gas for its own consumption, but "rights-of-way" as
3used in this Act does not authorize the Commission to
4prescribe, under this Act, the location or routing of any
5pipeline facility. "Pipeline facilities" also includes new and
6existing pipes and lines and any other equipment, facility, or
7structure, except customer-owned branch lines connected to the
8primary fuel lines, used to convey gas from a gas main to the
9outside wall of residential premises, and any person who
10provides gas service directly to its residential customer
11through these facilities shall be deemed to operate such
12pipeline facilities for purposes of this Act irrespective of
13the ownership of the facilities or the location of the
14facilities with respect to the meter, except that a person who
15provides gas service to a "master meter system", as that term
16is defined at 49 C.F.R. Section 191.3, shall not be deemed to
17operate any facilities downstream of the master meter.
18"Pipeline facilities" also includes new and existing pipe
19rights-of-way and any equipment, facility, or building used in
20the transportation of carbon dioxide in any physical form for
21the purpose of sequestration.
22(Source: P.A. 87-1092; 88-314.)
 
23    (220 ILCS 20/3)  (from Ch. 111 2/3, par. 553)
24    Sec. 3. (a) As soon as practicable, but not later than 3
25months after the effective date of this Act, the Commission

 

 

SB3388 Enrolled- 101 -LRB096 20594 MJR 36292 b

1shall adopt rules establishing minimum safety standards for the
2transportation of gas and for pipeline facilities. Such rules
3shall be at least as inclusive, as stringent, and compatible
4with, the minimum safety standards adopted by the Secretary of
5Transportation under the Federal Act. Thereafter, the
6Commission shall maintain such rules so that the rules are at
7least as inclusive, as stringent, and compatible with, the
8minimum standards from time to time in effect under the Federal
9Act. The Commission shall also adopt rules establishing minimum
10safety standards for the transportation of carbon dioxide in
11any physical form for the purpose of sequestration and for
12pipeline facilities used for that function.
13    (b) Standards established under this Act may apply to the
14design, installation, inspection, testing, construction,
15extension, operation, replacement, and maintenance of pipeline
16facilities. Standards affecting the design, installation,
17construction, initial inspection and initial testing are not
18applicable to pipeline facilities in existence on the date such
19standards are adopted. Whenever the Commission finds a
20particular facility to be hazardous to life or property, it may
21require the person operating such facility to take the steps
22necessary to remove the hazard.
23    (c) Standards established by the Commission under this Act
24shall, subject to paragraphs (a) and (b) of this Section 3, be
25practicable and designed to meet the need for pipeline safety.
26In prescribing such standards, the Commission shall consider:

 

 

SB3388 Enrolled- 102 -LRB096 20594 MJR 36292 b

1similar standards established in other states; relevant
2available pipeline safety data; whether such standards are
3appropriate for the particular type of pipeline
4transportation; the reasonableness of any proposed standards;
5and the extent to which such standards will contribute to
6public safety.
7    Rules adopted under this Act are subject to "The Illinois
8Administrative Procedure Act", approved September 22, 1975, as
9amended.
10(Source: P.A. 83-333.)
 
11    Section 20. The Illinois Environmental Protection Act is
12amended by adding Section 13.7 as follows:
 
13    (415 ILCS 5/13.7 new)
14    Sec. 13.7. Carbon dioxide sequestration sites.
15    (a) For purposes of this Section, the term "carbon dioxide
16sequestration site" means a site or facility for which the
17Agency has issued a permit for the underground injection of
18carbon dioxide.
19    (b) The Agency shall inspect carbon dioxide sequestration
20sites for compliance with this Act, rules adopted under this
21Act, and permits issued by the Agency.
22    (c) If the Agency issues a seal order under Section 34 of
23this Act in relation to a carbon dioxide sequestration site, or
24if a civil action for an injunction to halt activity at a

 

 

SB3388 Enrolled- 103 -LRB096 20594 MJR 36292 b

1carbon dioxide sequestration site is initiated under Section 43
2of this Act at the request of the Agency, then the Agency shall
3post notice of such action on its website.
4    (d) Persons seeking a permit or permit modification for the
5underground injection of carbon dioxide shall be liable to the
6Agency for all reasonable and documented costs incurred by the
7Agency that are associated with review and issuance of the
8permit, including, but not limited to, costs associated with
9public hearings and the review of permit applications. Once a
10permit is issued, the permittee shall be liable to the Agency
11for all reasonable and documented costs incurred by the Agency
12that are associated with inspections and other oversight of the
13carbon dioxide sequestration site. Persons liable for costs
14under this subsection (d) must pay the costs upon invoicing, or
15other request or demand for payment, by the Agency. Costs for
16which a person is liable under this subsection (d) are in
17addition to any other fees, penalties, or other relief provided
18under this Act or any other law.
19    Moneys collected under this subsection (d) shall be
20deposited into the Environmental Protection Permit and
21Inspection Fund established under Section 22.8 of this Act. The
22Agency may adopt rules relating to the collection of costs due
23under this subsection (d).
24    (e) The Agency shall not issue a permit or permit
25modification for the underground injection of carbon dioxide
26unless all costs for which the permitee is liable under

 

 

SB3388 Enrolled- 104 -LRB096 20594 MJR 36292 b

1subsection (d) of this Section have been paid.
2    (f) No person shall fail or refuse to pay costs for which
3the person is liable under subsection (d) of this Section.
 
4    Section 85. Rulemaking. The Illinois Environmental
5Protection Agency, the Illinois Commerce Commission, the
6Capital Development Board, and the Illinois Department of
7Natural Resources shall have rulemaking authority to implement
8the provisions of this amendatory Act of the 96th General
9Assembly.
 
10    Section 90. Inseverability. The provisions of this Act are
11mutually dependent and inseverable. If any provision is held
12invalid, then this entire Act, including all new and amendatory
13provisions, is invalid.
 
14    Section 99. Effective date. This Act takes effect upon
15becoming law.