SB3070 Enrolled |
- 2 - |
LRB096 17183 JDS 32522 b |
|
|
1 |
| finished water. |
2 |
| (b) For purposes of this Section: |
3 |
| (1) "Carcinogen" means carcinogen as defined in |
4 |
| Section 58.2 of this Act. |
5 |
| (2) "Community water system", "finished water", |
6 |
| "maximum contaminant level", "method detection limit", and |
7 |
| "volatile organic compound" shall have the meanings |
8 |
| ascribed to them in rules adopted by the Board at Part 611 |
9 |
| of Title 35 of the Illinois Administrative Code. |
10 |
| (c) If a carcinogenic volatile organic compound is detected |
11 |
| in the finished water of a community water system at a |
12 |
| concentration that equals or exceeds 50 percent of the |
13 |
| carcinogenic volatile organic compound's maximum contaminant |
14 |
| level and the Agency issues a notice under subdivision |
15 |
| (a)(2)(B) of Section 25d-3 of this Act based on the presence of |
16 |
| the carcinogenic volatile organic compound, the owner or |
17 |
| operator of the community water system shall, within 45 days |
18 |
| after the date the Agency issues the notice under subdivision |
19 |
| (a)(2)(B) of Section 25d-3 of this Act, submit to the Agency a |
20 |
| response plan designed to (i) prevent an exceedence of the |
21 |
| maximum contaminant level in the finished water and (ii) reduce |
22 |
| the concentration of the carcinogenic volatile organic |
23 |
| compound so that it does not exceed the applicable method |
24 |
| detection limit in the finished water. The response plan shall |
25 |
| also include periodic sampling designed to measure and verify |
26 |
| the effectiveness of the response plan. |
|
|
|
SB3070 Enrolled |
- 3 - |
LRB096 17183 JDS 32522 b |
|
|
1 |
| (1) Upon Agency approval of the plan, with or without |
2 |
| modifications, the owner or operator of the community water |
3 |
| system shall implement the plan. In approving, modifying, |
4 |
| or denying a plan required under this Section, the Agency |
5 |
| shall take into account the technical feasibility and |
6 |
| economic reasonableness of the plan and any modification to |
7 |
| the plan. The owner or operator shall submit status reports |
8 |
| on the plan's implementation in accordance with a schedule |
9 |
| approved by the Agency. Upon completion of the plan the |
10 |
| owner or operator shall submit to the Agency for review and |
11 |
| approval a response completion report. |
12 |
| (2) Any action by the Agency to disapprove or modify a |
13 |
| plan or report required under this Section shall be subject |
14 |
| to appeal to the Board in accordance with the procedures of |
15 |
| Section 40 of this Act. |
16 |
| (d)(1) No person required to submit a response plan under |
17 |
| subsection (c) of this Section shall fail to submit the plan in |
18 |
| accordance with the requirements of subsection (c). |
19 |
| (2) No person required to implement a response plan |
20 |
| under subdivision (c)(1) of this Section shall fail to |
21 |
| implement the plan in accordance with the requirements of |
22 |
| subdivision (c)(1). |
23 |
| (3) No person required to submit a status report or a |
24 |
| response completion report under subdivision(c)(1) of this |
25 |
| Section shall fail to submit the report in accordance with |
26 |
| the requirements of subdivision (c)(1).
|