|
|
|
09600SB0052ham002 |
- 2 - |
LRB096 02025 MJR 27799 a |
|
|
1 |
| residents. The costs associated with preparing a facility cost |
2 |
| report for such a facility, which contains all of the |
3 |
| information required by subsection (b) of this Section, may be |
4 |
| paid or reimbursed pursuant to subsection (c) of this Section. |
5 |
| (b) The facility cost report for a facility that meets the |
6 |
| criteria set forth in subsection (a) of this Section shall be |
7 |
| prepared by a duly licensed engineering firm that details the |
8 |
| estimated capital costs payable to one or more contractors or |
9 |
| suppliers for the engineering, procurement, and construction |
10 |
| of the components comprising the facility and the estimated |
11 |
| costs of operation and maintenance of the facility. The report |
12 |
| must be provided to the General Assembly and the Agency on or |
13 |
| before April 30, 2010. The facility cost report shall include |
14 |
| all off the following: |
15 |
| (1) An estimate of the capital cost of the core plant |
16 |
| based on a front-end engineering and design study. The core |
17 |
| plant shall include all civil, structural, mechanical, |
18 |
| electrical, control, and safety systems. The quoted |
19 |
| construction costs shall be expressed in nominal dollars as |
20 |
| of the date that the quote is prepared and shall include: |
21 |
| (A) capitalized financing costs during |
22 |
| construction; |
23 |
| (B) taxes, insurance, and other owner's costs; and |
24 |
| (C) any assumed escalation in materials and labor |
25 |
| beyond the date as of which the construction cost quote |
26 |
| is expressed; |
|
|
|
09600SB0052ham002 |
- 3 - |
LRB096 02025 MJR 27799 a |
|
|
1 |
| (2) An estimate of the capital cost of the balance of |
2 |
| the plant, including any capital costs associated with site |
3 |
| preparation and remediation, sequestration of carbon |
4 |
| dioxide emissions, and all interconnects and interfaces |
5 |
| required to operate the facility, such as construction or |
6 |
| backfeed power supply, pipelines to transport substitute |
7 |
| natural gas or carbon dioxide, potable water supply, |
8 |
| natural gas supply, water supply, water discharge, |
9 |
| landfill, access roads, and coal delivery. The front-end |
10 |
| engineering and design study and the cost study for the |
11 |
| balance of the plant shall include sufficient design work |
12 |
| to permit quantification of major categories of materials, |
13 |
| commodities and labor hours, and receipt of quotes from |
14 |
| vendors of major equipment required to construct and |
15 |
| operate the facility. |
16 |
| (3) An operating and maintenance cost quote that will |
17 |
| provide the estimated cost of delivered fuel, personnel, |
18 |
| maintenance contracts, chemicals, catalysts, consumables, |
19 |
| spares, and other fixed and variable operating and |
20 |
| maintenance costs. This quote is subject to the following |
21 |
| requirements: |
22 |
| (A) The delivered fuel cost estimate shall be |
23 |
| provided by a recognized third party expert or experts |
24 |
| in the fuel and transportation industries. |
25 |
| (B) The balance of the operating and maintenance |
26 |
| cost quote, excluding delivered fuel costs shall be |
|
|
|
09600SB0052ham002 |
- 4 - |
LRB096 02025 MJR 27799 a |
|
|
1 |
| developed based on the inputs provided by a duly |
2 |
| licensed engineering firm performing the construction |
3 |
| cost quote, potential vendors under long-term service |
4 |
| agreements and plant operating agreements, or |
5 |
| recognized third-party plant operator or operators. |
6 |
| The operating and maintenance cost quote shall be |
7 |
| expressed in nominal dollars as of the date that the quote |
8 |
| is prepared and shall include (i) taxes, insurance, and |
9 |
| other owner's costs and (ii) any assumed escalation in |
10 |
| materials and labor beyond the date as of which the |
11 |
| operating and maintenance cost quote is expressed. |
12 |
| (c) Reasonable amounts paid or due to be paid by the owner |
13 |
| or owners of the clean coal SNG facility to third parties |
14 |
| unrelated to the owner or owners to prepare the facility cost |
15 |
| report will may be reimbursed or paid up to $10 million through |
16 |
| Coal Development Bonds , through funding authorized pursuant to |
17 |
| 20 ILCS 3501/825-65 . |
18 |
| (d) The Agency shall review the facility report and based |
19 |
| on that report, consider whether to enter into long term |
20 |
| contracts to purchase SNG from the facility pursuant to Section |
21 |
| 1-20 of this Act. To assist with its evaluation of the report, |
22 |
| the Agency may hire one or more experts or consultants, the |
23 |
| reasonable costs of which, not to exceed $250,000, shall be |
24 |
| paid for by the owner or owners of the clean coal SNG facility |
25 |
| submitting the facility cost report. The Agency may begin the |
26 |
| process of selecting such experts or consultants prior to |
|
|
|
09600SB0052ham002 |
- 5 - |
LRB096 02025 MJR 27799 a |
|
|
1 |
| receipt of the facility cost report.
|
2 |
| (Source: 09600SB0658eng with ham003.) |
3 |
| Section 10. If and only if Senate Bill 658 of the 96th |
4 |
| General Assembly (as amended by House Amendment No. 3) becomes |
5 |
| law, the General Obligation Bond Act is amended by changing |
6 |
| Section 7 as follows:
|
7 |
| (30 ILCS 330/7) (from Ch. 127, par. 657)
|
8 |
| Sec. 7. Coal and Energy Development. The amount of |
9 |
| $698,200,000 is
authorized to be used by the Department of |
10 |
| Commerce and Economic Opportunity (formerly Department of |
11 |
| Commerce and Community Affairs) for
coal and energy development |
12 |
| purposes, pursuant to Sections 2, 3 and 3.1 of the
Illinois |
13 |
| Coal and Energy Development Bond Act, for the purposes
|
14 |
| specified
in Section 8.1 of the Energy Conservation and Coal |
15 |
| Development Act, for
the purposes specified in Section 605-332 |
16 |
| of the Department of Commerce and
Economic Opportunity Law of |
17 |
| the Civil Administrative Code of Illinois, and for the purpose |
18 |
| of facility cost reports prepared pursuant to Sections 1-56 or |
19 |
| Section 1-75(d)(4) of the Illinois Power Agency Act and for the |
20 |
| purpose of development costs pursuant to Section 8.1 of the |
21 |
| Energy Conservation and Coal Development Act . Of this
amount:
|
22 |
| (a) $115,000,000 is
for the specific purposes of |
23 |
| acquisition,
development, construction, reconstruction, |
24 |
| improvement, financing,
architectural and technical planning |
|
|
|
09600SB0052ham002 |
- 6 - |
LRB096 02025 MJR 27799 a |
|
|
1 |
| and installation of capital facilities
consisting of |
2 |
| buildings, structures, durable equipment, and land for the
|
3 |
| purpose of capital development of coal resources within the |
4 |
| State and for the
purposes specified in Section 8.1 of the |
5 |
| Energy Conservation and Coal
Development Act;
|
6 |
| (b) $35,000,000 is for the purposes specified in Section |
7 |
| 8.1 of the
Energy
Conservation and Coal Development Act and |
8 |
| making a grant to the owner of a
generating station
located in |
9 |
| Illinois and having at least three coal-fired generating units
|
10 |
| with accredited summer capability greater than 500 megawatts |
11 |
| each at such
generating station as provided in Section 6 of |
12 |
| that Bond Act;
|
13 |
| (c) $13,200,000 is for research, development and |
14 |
| demonstration
of forms of energy
other than that derived from |
15 |
| coal, either on or off State property;
|
16 |
| (d) $500,000,000 is for the purpose of providing financial |
17 |
| assistance to
new
electric generating facilities as provided in |
18 |
| Section 605-332 of the Department
of Commerce and Economic |
19 |
| Opportunity Law of the Civil Administrative Code of
Illinois; |
20 |
| and
|
21 |
| (e) $35,000,000 is for the purpose of facility cost reports |
22 |
| prepared pursuant to Sections 1-56 or Section 1-75(d)(4) of the |
23 |
| Illinois Power Agency Act and for the purpose of development |
24 |
| costs pursuant to Section 8.1 of the Energy Conservation and |
25 |
| Coal Development Act . |
26 |
| (Source: P.A. 94-793, eff. 5-19-06; 95-1026, eff. 1-12-09.)
|