104TH GENERAL ASSEMBLY
State of Illinois
2025 and 2026
HB3349

 

Introduced 2/18/2025, by Rep. Curtis J. Tarver, II

 

SYNOPSIS AS INTRODUCED:
 
New Act

    Creates the Powering Up Illinois Act. Defines terms. Sets forth findings. Requires an electric utility that operates within the State to (i) upgrade the State's electrical distribution systems as needed and in time to achieve the State's decarbonization goals, and implement federal, State, regional, and local air quality and decarbonization standards, plans, and regulations, (ii) conduct sufficient advance planning, engineering, and construction of increased distribution of system capacity by advance ordering transformers and other needed equipment so that customers can be energized without substantial delay, (iii) promptly energize new customers, including by ensuring that new housing, new businesses, and new charging for light-duty, medium-duty, and heavy-duty vehicles and off-road vehicles, vessels, trains, and equipment can be used without delay caused by a failure of the utility to implement energization projects, (iv) promptly upgrade service when needed by customers, (v) allow customers seeking energization to choose an optional flexible connection agreement, which shall provide a tariffed, voluntary utility offering that requires customers to agree to specified service levels as a requirement of energization or interconnection through the use of demand response technology that limits the net import and export of electricity at the point of common coupling to remain within the rated capacity limits of a customer's existing service connection or distribution circuit, either on a permanent basis or to allow for immediate project operations before service or distribution system upgrades are completed, and (vi) recruit, train, and retain an adequately sized and qualified workforce to carry out the planning, engineering, and construction of electrical distribution systems needed to promptly serve customers seeking energization and service upgrades without sacrificing other necessary activities of the workforce. Sets forth provisions concerning: the staffing of an electrification team; electric utility requirements; recovery of costs; and safety standards. Effective immediately.


LRB104 10938 AAS 21020 b

 

 

A BILL FOR

 

HB3349LRB104 10938 AAS 21020 b

1    AN ACT concerning regulation.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 1. Short title. This Act may be cited as the
5Powering Up Illinois Act.
 
6    Section 5. Definitions. As used in this Act:
7    "Commission" means the Illinois Commerce Commission.
8    "Electric utility" means an electric utility serving more
9than 200,000 customers in this State.
10    "Electrification" means any new use of electricity,
11expanded use of electricity, or change in use of electricity,
12including, but not limited to, any change in the use of
13electricity in the industrial, commercial, agricultural,
14housing, or transportation sectors.
15    "Energization" and "energize" means the connection of new
16customers to the electrical grid, the establishment of
17adequate electrical capacity to provide service for a new
18customer, or upgrading electrical capacity to provide adequate
19service to an existing customer. "Energization" and "energize"
20do not include activities related to connecting electricity
21supply resources.
22    "Energization time period" means the period of time that
23begins when the electric utility receives a substantially

 

 

HB3349- 2 -LRB104 10938 AAS 21020 b

1complete energization project application and ends when the
2electric service associated with the project is installed and
3energized, consistent with the service obligations set forth
4in the Section 8-101 of the Public Utilities Act.
 
5    Section 10. Findings. The General Assembly finds the
6following:
7        (1) It is the policy of the State to increase the
8    amount of electric vehicles used in the State to 1,000,000
9    by 2030. That expanded infrastructure investment will help
10    Illinois more rapidly decarbonize the transportation
11    sector. Widespread use of electric vehicles and charging
12    equipment has the potential to provide customers with fuel
13    cost savings and provide electric utility customers with
14    cost-saving benefits. Widespread use of electric vehicles
15    stimulates innovation, competition, and increased choices
16    in charging equipment and networks, attracts private
17    capital investments to the State, and creates high-quality
18    jobs in the State. Accelerating the adoption of electric
19    vehicles will drive the decarbonization of the States'
20    transportation sector. To meet these goals and federal,
21    State, regional, and local air quality and decarbonization
22    standards, plans, and regulations, a large increase in
23    both the quantity of electricity used and the functions
24    for which electricity will be used is needed.
25        (2) To meet these decarbonization goals as well as

 

 

HB3349- 3 -LRB104 10938 AAS 21020 b

1    federal, State, regional, and local air quality and
2    decarbonization standards, plans, and regulations, the
3    following must occur:
4            (A) the State's electrical distribution systems
5        must be substantially upgraded;
6            (B) new customers must promptly connect to the
7        electrical distribution system; and
8            (C) existing customers must have the customer's
9        service level promptly upgraded.
10        (3) There are many reports of large housing
11    developments that are unable to be energized promptly. The
12    State has an urgent need to increase its supply of
13    housing, requiring both new electrical distribution
14    capacity and the prompt energization of new housing.
15        (4) There are many reports of individual customers who
16    are unable to have their electrical service promptly
17    upgraded or energized and charging stations for
18    light-duty, medium-duty, and heavy-duty vehicles and
19    off-road vehicles, vessels, trains, and equipment that are
20    unable to be energized promptly. These delays may inhibit
21    the State's ability to meet its decarbonization goals and
22    federal, State, regional, and local air quality and
23    decarbonization standards, plans, and regulations.
24        (5) To improve the speed at which energization and
25    service upgrades are performed, electric utilities that
26    distribute electricity need to do both of the following:

 

 

HB3349- 4 -LRB104 10938 AAS 21020 b

1            (A) accelerate the utility's advance planning,
2        engineering, and construction of increased
3        distribution and transmission system capacity; and
4            (B) advance order transformers, switchgear, and
5        other needed equipment to support acceleration of
6        activities in subparagraph (A).
7        (6) Electrifying transportation and buildings can put
8    downward pressure on rates by spreading fixed costs over
9    more kilowatt-hours of usage.
10        (7) Delays in energization, including service
11    upgrades, are costly both to the customers awaiting
12    service and to other customers who are deprived of the
13    downward pressure on rates.
14        (8) To carry out the planning, engineering, and
15    construction of electrical distribution systems needed to
16    promptly serve customers, electric utilities that
17    distribute electricity need to recruit, train, and retain
18    an adequately sized, qualified workforce.
19        (9) The Illinois Commerce Commission needs to
20    establish target deadlines for utilities that distribute
21    electricity to energize new customers and upgrade the
22    service of existing customers.
23        (10) The Illinois Commerce Commission needs to
24    establish reporting requirements for electric utilities
25    that distribute electricity to report the extent to which
26    they comply with the target deadlines and the reasons for

 

 

HB3349- 5 -LRB104 10938 AAS 21020 b

1    any noncompliance.
 
2    Section 15. Electrical distribution system upgrades. To
3fulfill the service obligations specified in Section 8-101 of
4the Public Utilities Act, an electric utility that operates
5within the State shall:
6        (1) upgrade the State's electrical distribution
7    systems as needed and in time to achieve the State's
8    decarbonization goals, and implement federal, State,
9    regional, and local air quality and decarbonization
10    standards, plans, and regulations;
11        (2) conduct sufficient advance planning, engineering,
12    and construction of increased distribution of system
13    capacity by advance ordering transformers and other needed
14    equipment so that customers can be energized without
15    substantial delay;
16        (3) promptly energize new customers, including by
17    ensuring that new housing, new businesses, and new
18    charging for light-duty, medium-duty, and heavy-duty
19    vehicles and off-road vehicles, vessels, trains, and
20    equipment can be used without delay caused by a failure of
21    the utility to implement energization projects;
22        (4) promptly upgrade service when needed by customers;
23        (5) allow customers seeking energization to choose an
24    optional flexible connection agreement, which shall
25    provide a tariffed, voluntary utility offering that

 

 

HB3349- 6 -LRB104 10938 AAS 21020 b

1    requires customers to agree to specified service levels as
2    a requirement of energization or interconnection through
3    the use of demand response technology that limits the net
4    import and export of electricity at the point of common
5    coupling to remain within the rated capacity limits of a
6    customer's existing service connection or distribution
7    circuit, either on a permanent basis or to allow for
8    immediate project operations before service or
9    distribution system upgrades are completed; and
10        (6) recruit, train, and retain an adequately sized and
11    qualified workforce to carry out the planning,
12    engineering, and construction of electrical distribution
13    systems needed to promptly serve customers seeking
14    energization and service upgrades without sacrificing
15    other necessary activities of the workforce.
 
16    Section 20. Commission requirements.
17    (a) Within 180 days after the effective date of this Act,
18the Commission shall adopt rules that meet all of the
19following requirements:
20        (1) Rules that establish reasonable average and
21    maximum target energization time periods. The targets
22    shall ensure that work is completed in a safe and reliable
23    manner that minimizes delay in meeting the date requested
24    by the customer for completion of the project to the
25    greatest extent possible and prioritizes work in a manner

 

 

HB3349- 7 -LRB104 10938 AAS 21020 b

1    consistent with Sections 25 and 30. The targets may vary
2    depending on the complexity and magnitude of the work
3    required and uncertainties regarding the readiness of the
4    customer project needing energization. The targets may
5    also recognize any factors beyond the electric utility's
6    control.
7        (2) Rules that establish requirements for an electric
8    utility to report to the Commission, at least annually, in
9    order to track and improve electric utility performance.
10    The report shall include the average, median, and standard
11    deviation time between receiving an application for
12    electrical service and energizing the electrical service,
13    explanations for energization time periods that exceed the
14    target maximum for energization projects, constraints and
15    obstacles to each type of energization, including, but not
16    limited to, funding limitations, qualified staffing
17    availability, or equipment availability, and any other
18    information requested by the Commission.
19        (3) Rules that establish a procedure for customers to
20    report energization delays to the Illinois Commerce
21    Commission.
22    (b) If energization time periods exceed the Commission's
23target averages or if the electric utility has a substantial
24number of energization projects that exceed the Commission's
25target maximums, the electric utility shall include in its
26report pursuant to rules adopted under paragraph (2) of

 

 

HB3349- 8 -LRB104 10938 AAS 21020 b

1subsection (a) a strategy for meeting the targets in the
2future. The Commission may request modification of the
3electric utility's strategy to ensure that the electric
4utility meets targets promptly and consistent with the
5policies set forth in Section 25.
6    (c) Data reported by electric utilities shall be
7anonymized or aggregated to the extent necessary to prevent
8identifying individual customers. The Commission shall require
9all reports to be publicly available.
10    (d) The Commission shall require the electric utility to
11take any remedial actions necessary to achieve the
12Commission's targets, including the use of incentives or
13penalties.
 
14    Section 25. Electrification team; staffing.
15    (a) The Commission shall require each electric utility to
16establish a dedicated electrification team that shall, at a
17minimum, do the following:
18        (1) serve as a single point of contact for customers
19    throughout the entire energization process;
20        (2) proactively engage with customers to understand
21    and support electrification plans; and
22        (3) provide customers with consolidated and
23    coordinated access to all beneficial electrification
24    customer programs, accounts, and relevant information to
25    support electrification and the energization process.

 

 

HB3349- 9 -LRB104 10938 AAS 21020 b

1    (b) The Commission shall require each electric utility to
2have adequate qualified staffing needed for the
3electrification team to achieve the policies and requirements
4of this Act.
5    (c) For job classifications that have apprentice training
6requirements, the Commission shall require each electric
7utility to maintain a pipeline of apprentices sufficient to
8meet future qualified staffing needs, subject to any
9limitations based on safe staffing ratios.
10    (d) As part of each report required pursuant to rules
11adopted under paragraph (2) of subsection (a) of Section 20,
12and in each general rate case application, each electric
13utility shall include a detailed analysis of its current
14qualified staffing level and future required qualified
15staffing level for each job classification needed to achieve
16the policies and requirements of this Act.
 
17    Section 30. Electric utility requirements. The Commission
18shall require an electric utility to do the following:
19        (1) consider, in its internal distribution planning
20    process and in the development of the Multi-Year
21    Integrated Grid Plans required by Section 16-105.17 of the
22    Public Utilities Act, all of the following:
23            (A) federal, State, regional, and local air
24        quality and decarbonization standards, plans, and
25        regulations;

 

 

HB3349- 10 -LRB104 10938 AAS 21020 b

1            (B) the transportation and building
2        electrification policies of State law;
3            (C) State agency, local agency, and local
4        government plans and requirements related to housing,
5        economic development, critical facilities,
6        transportation, and building electrification; and
7            (D) load and electrification forecasts that
8        include the following:
9                (I) known load and projections of load
10            conducted by State agencies and projections of
11            load that exceed forecasts conducted by State
12            agencies;
13                (II) a minimum of 3 time horizons, including
14            short-term (one to 2 years), medium-term (3 to 5
15            years), and long-term (6 to 10 years) time
16            horizons;
17                (III) scenarios that are consistent with
18            implementing the laws, standards, plans, and
19            regulations described in subparagraphs (A), (B),
20            and (C) of paragraph (1);
21                (IV) forecasts of peak demand at the
22            federal-level; and
23                (V) a consideration of the impact of
24            distributed energy resource forecasts and,
25            specifically, local generation;
26        (2) consider all of the following in its site

 

 

HB3349- 11 -LRB104 10938 AAS 21020 b

1    evaluation and design process:
2            (A) automated load management, managed charging,
3        and distributed energy resources to defer or mitigate
4        energization-related grid upgrades; and
5            (B) if the above solutions cannot defer or
6        mitigate an upgrade, the electric utility shall
7        evaluate traditional system upgrades;
8        (3) adopt and implement rules to satisfy the policies
9    set forth in Section 20 and to meet the energization time
10    periods established under paragraph (1) of subsection (a)
11    of Section 20; and
12        (4) submit supplemental applications between the
13    4-year cycles specified for the submission of the
14    Multi-Year Integrated Grid Plans required by Section
15    16-105.17 of the Public Utilities Act as needed to comply
16    with the energization time periods established under
17    paragraph (1) of subsection (a) of Section 20 and to
18    accommodate the load growth necessary to implement the
19    laws, standards, plans, and regulations described in
20    subparagraphs (A), (B), and (C) of paragraph (1).
 
21    Section 35. Recovery of costs. The Commission shall ensure
22that electric utilities have sufficient and timely recovery of
23costs to be consistent with the findings and achieve the
24policies and requirements of this Act and Section 16-105.17 of
25the Public Utilities Act.
 

 

 

HB3349- 12 -LRB104 10938 AAS 21020 b

1    Section 40. Safety. To ensure the safety and reliability
2of electrical infrastructure associated with charging electric
3vehicles:
4        (1) The Commission, Environmental Protection Agency,
5    and Department of Transportation shall require that all
6    electric vehicle charging infrastructure and equipment
7    located on the customer side of the electrical meter that
8    is funded or authorized, in whole or in part, by those
9    State entities shall be installed by a licensed, bonded,
10    and insured electrical contractor registered in the
11    municipality where work is to be performed, and who has at
12    least one electrician on each crew, at any given time, who
13    holds an Electric Vehicle Infrastructure Training Program
14    certification.
15        (2) The Commission, Environmental Protection Agency,
16    and Department of Transportation shall require the
17    projects that are funded or authorized, in whole or in
18    part, by those State entities and that install a charging
19    port supplying 25 kilowatts or more to a vehicle to have at
20    least 25% of the total electricians working on the crew
21    for the project, at any given time, hold an Electric
22    Vehicle Infrastructure Training Program certification.
23        (3) One member of each crew may be both the contractor
24    and an electrician certified by Electric Vehicle
25    Infrastructure Training Program.

 

 

HB3349- 13 -LRB104 10938 AAS 21020 b

1        (4) Paragraph (1) does not apply to the following:
2            (A) electric vehicle charging infrastructure
3        installed by employees of an electric utility or local
4        publicly owned electric utility; or
5            (B) single-family home residential electric
6        vehicle chargers.
7        (5) An electrical apprenticeship program registered
8    with United States Department of Labor that provides
9    training to apprentices and continuing education to
10    journey-level workers may provide Electric Vehicle
11    Infrastructure Training Program training with the
12    apprenticeship program's own instructors certified by an
13    Electric Vehicle Infrastructure Training Program. The
14    Electric Vehicle Infrastructure Training Program
15    certification exam shall be administered by the Electric
16    Vehicle Infrastructure Training Program.
 
17    Section 99. Effective date. This Act takes effect upon
18becoming law.