| | 10000SB1340sam001 | - 2 - | LRB100 08961 AXK 23711 a |
|
|
1 | | Society for Testing and Materials and shall include, but are |
2 | | not limited to: |
3 | | (1) a dispute resolution process that would address |
4 | | issues arising out of a pre-production meeting under AASHTO |
5 | | R 9-05 (2013) or its current equivalent full standard, |
6 | | which shall include third-party arbitration as a final |
7 | | step; |
8 | | (2) the use of a contractor's quality test results for |
9 | | hot-mix asphalt under 23 CFR 637 and AASHTO R 9-05 (2013) |
10 | | or its current equivalent full standard for consideration |
11 | | in the Department's acceptance decisions for the programs; |
12 | | (3) the use of third party laboratories to conduct |
13 | | verification testing, independent assurance testing, or |
14 | | dispute resolution testing under 23 CFR 637 and AASHTO R |
15 | | 9-05 (2013) or its current equivalent full standard on |
16 | | behalf of the Department; |
17 | | (4) the use of performance-based testing that utilizes |
18 | | the test methods developed by the American Association of |
19 | | State Highway and Transportation Officials or the American |
20 | | Society for Testing and Materials. In creating the criteria |
21 | | for the performance-based testing, the Department shall |
22 | | give priority consideration to the Federal Highway |
23 | | Administration's Techbriefs, Transportation Pooled Fund |
24 | | studies sponsored by the Federal Highway Administration or |
25 | | the Department, and completed National Cooperative Highway |
26 | | Research Program projects; |
|
| | 10000SB1340sam001 | - 3 - | LRB100 08961 AXK 23711 a |
|
|
1 | | (5) a procedure for addressing outlying test results |
2 | | under ASTM E178-16a or its current equivalent full |
3 | | standard; and |
4 | | (6) an acceptable quality limit and a pay factor |
5 | | equation that provides for a maximum pay adjustment of up |
6 | | to 105% and a defined maximum pay deduction under AASHTO R |
7 | | 9-05 (2013) or its current equivalent full standard. |
8 | | (b) Within 30 days after the revision of the Pay for |
9 | | Performance program and the Quality Control for Performance |
10 | | program, the Secretary of Transportation shall direct the |
11 | | Bureau of Materials and Physical Research to publish revised |
12 | | Pay for Performance and Quality Control for Performance Special |
13 | | Provisions for use in Department projects. Each Special |
14 | | Provision shall include a certification that the programs |
15 | | comply with non-provisional standards that have been formally |
16 | | adopted and published by the American Association of State |
17 | | Highway and Transportation Officials and the American Society |
18 | | for Testing and Materials.
|
19 | | Section 99. Effective date. This Act takes effect upon |
20 | | becoming law.".
|