Section 980.460  Effect on Current Contracts

 

Current CDB contracts may be terminated when an A/E is determined to be non-responsible and it is in the public interest to do so, whether or not the non-responsibility has a direct connection with the current contract.  Contracts may be terminated with or without further action on the A/E's prequalification.

 

(Source:  Old Section repealed at 24 Ill. Reg. 6663, effective April 17, 2000; new Section added at 25 Ill. Reg. 10759, effective August 10, 2001)