TITLE 44: GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
SUBTITLE A: PROCUREMENT AND CONTRACT PROVISIONS
CHAPTER IV: CHIEF PROCUREMENT OFFICER FOR CAPITAL DEVELOPMENT BOARD
PART 8 CHIEF PROCUREMENT OFFICER FOR THE CAPITAL DEVELOPMENT BOARD
SECTION 8.5014 ENVIRONMENTAL PROTECTION ACT VIOLATIONS


 

Section 8.5014  Environmental Protection Act Violations

 

a)         Unless otherwise provided, no person or business found by a court or the Pollution Control Board to have committed a willful or knowing violation of the Environmental Protection Act shall do business with the State of Illinois or any State agency or enter into a subcontract from the date of the order containing the finding of violation until 5 years after that date, unless the person or business can show that no person involved with the violation continues to have any involvement with the business.  [30 ILCS 500/50-14(a)]

 

b)         A person or business otherwise barred from doing business with the State of Illinois and any State agency or any subcontractors under the Code by subsection (a) may be allowed to do business with the State of Illinois or any State agency if it is shown that there is no practicable alternative to the State to contracting with that person or business.  [30 ILCS 500/50-14(b)]

 

c)         Every bid submitted to and contract executed by the State and every subcontract subject to Section 20-120 of the Code shall contain a certification by the bidder, contractor and any subcontractor, respectively, that the bidder, contractor or subcontractor is not barred from being awarded a contract or subcontract under this Section and acknowledges that the CDB or CPO may declare the related contract void if any of the certifications completed pursuant to this subsection (c) are false.  If the false certification is made by a subcontractor, then the contractor's submitted bid and the executed contract may not be declared void, unless the contractor refuses to terminate the subcontract upon the State's request after a finding that the subcontractor's certification was false.  [30 ILCS 500/50-14(c)]