TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE J: CLEAN CONSTRUCTION OR DEMOLITION DEBRIS CHAPTER II: ENVIRONMENTAL PROTECTION AGENCY PART 1150 PROCEDURES FOR OPERATION OF THE CLEAN CONSTRUCTION OR DEMOLITION DEBRIS FILL OPERATION FEE SYSTEM SECTION 1150.205 DAILY FILL RECORD
Section 1150.205 Daily Fill Record
a) The Daily Fill Records must be maintained at the site of the CCDD fill operation and must include the Agency designated site number and the site name.
b) For each load of CCDD or uncontaminated soil accepted for use as fill material at the CCDD fill operation the following information must be recorded in the Daily Fill Record, in addition to any other information required by the Act and rules adopted under the Act:
1) The date and day of the week the load was accepted.
2) The quantity, in tons weighed or cubic yards measured, of CCDD or uncontaminated soil accepted for use as fill material at the CCDD fill operation. |